Can the post pouring belt be continuously poured in the construction project, and on what basis?

Updated on society 2024-06-18
11 answers
  1. Anonymous users2024-02-12

    Post-pouring belt in construction projects.

    It cannot be poured continuously.

    The post-cast belt is a cast-in-place reinforced concrete structure in building construction to prevent it.

    Harmful cracks that may be produced due to uneven shrinkage or uneven settlement, in accordance with the requirements of the design or construction specifications, temporary construction joints left at the corresponding positions of the foundation floor, wall and beam.

    The structure is temporarily divided into several parts, and after the internal shrinkage of the components, the concrete of the construction joint is poured after a certain period of time, and the structure is connected into a whole.

    There are two types of post-pouring belts: settlement post-pouring belts and telescopic post-pouring belts: to solve high-rise buildings.

    The post-pouring construction zone set up by the settlement difference between the main building and the podium is called the settlement post-pouring zone. In order to prevent the construction area from being too large, the structure is due to temperature changes, and the concrete shrinkage and cracking are set up as the expansion and post-pouring belt.

    The pouring belt after settlement should be poured after the main structure project is completed and the settlement of the building is basically stable. Generally, it is poured 14 days after the completion of the main structure.

    The telescopic post-pouring belt should be poured 60 days after the original concrete has been poured, because the hardening shrinkage of the concrete is completed after 60 days of concrete pouring.

  2. Anonymous users2024-02-11

    The post-pouring belt of the construction project can not be continuously poured, and the classification of the post-pouring belt is: 1. It is used to solve the difference between the high-rise main body and the low-rise podium, which is called the post-pouring settlement zone. It must be poured after the completion of the main structure 2, used to solve the shrinkage deformation of reinforced concrete, called the post-pouring shrinkage zone 3, used to solve the concrete temperature stress, called the post-pouring temperature zone.

    To prime at a lower temperature. Therefore, the post-pouring belt generally cannot be poured continuously.

  3. Anonymous users2024-02-10

    28 days after the end of the general main project, the pouring settlement beganPost-pouring tape;60 days after the concrete on both sides is formed, it can be poured after shrinkage pouring belt.

    The re-pouring time of post-pouring concrete is not less than 14 days, some are not less than 42 days, some are not less than 60 days, and some are 28 days after the capping. "High-rise building.

    The Technical Specification for Concrete Structures (JGJ3-2010) stipulates that it is poured after 45 days. The third edition of the Concrete Structure Construction Handbook China Architecture & Building Press stipulates that it is 28 days.

  4. Anonymous users2024-02-09

    Hello dear, here is the reason why you can find out that the post-pouring belt is a temporary construction joint set up in order to overcome harmful cracks due to temperature, shrinkage and settlement during the construction of cast-in-place concrete structures. The joint needs to be retained for a period of time according to the design requirements before pouring, and the setting distance of the pouring belt after connecting the whole structure into a whole should be determined by calculation under the condition of considering the effective reduction of temperature difference and shrinkage stress. Under normal construction conditions, the general spacing is 30 50m, and after taking special measures, it can be increased appropriately.

    The retention time of the post-pouring belt should be determined according to the design, if there is no design requirement, it is generally retained for at least 28 days. The width of the post-pouring belt is generally 70 200cm, and the steel bars in the post-pouring belt should be well protected. Before the construction of the post-pouring belt, the entire concrete surface must be treated in accordance with the requirements of the construction joint.

    The concrete filled with the post-pouring belt can be made of micro-expansion or low-shrinkage concrete, and the concrete strength grade should be increased by one level compared with the original structural concrete strength grade, and the wet curing must be maintained for more than 14 days.

  5. Anonymous users2024-02-08

    Generally, the post-pouring belt is divided into telescopic post-pouring belt and settlement post-pouring belt, and the triangular post-pouring belt is generally poured in the concrete after the shrinkage is basically stable, and it can only be carried out after 60 days after the pouring is completed.

  6. Anonymous users2024-02-07

    It depends on what is the nature of the post-pouring belt on your project, and the general drawings have a description of the time of post-pouring belt construction, if there is no explanation, according to the following time processing (construction):

    If it is a post-settlement pouring belt: it is necessary to wait for the main structure to be completed (no longer loaded on the structure) and the settlement is stable before construction.

    If it is a shrinkage (temperature) post-pouring belt: only 60 days after the concrete on both sides is formed, it can be constructed.

  7. Anonymous users2024-02-06

    Now the reinforcing belt is mostly used instead of the post-construction pouring belt. The general design of the pouring belt after settlement is given, and there are those that are capped for 28 days and poured after 42 days.

  8. Anonymous users2024-02-05

    If it is poured after construction, that is, 60 days after the pouring of concrete on both sides, if it is poured after settlement, it needs to be poured after the main structure is completed.

  9. Anonymous users2024-02-04

    Pouring belt after settlement: pouring is carried out after the main structure is completed and the settlement is stable.

    Pouring belt after shrinkage: The concrete on both sides can be poured 60 days after molding.

  10. Anonymous users2024-02-03

    After the construction of the construction project, the pouring time of the pouring belt should be more than half a year.

  11. Anonymous users2024-02-02

    1. After the main body of the building structure is capped, according to the settlement observation record, the pouring belt can be poured and closed only after the settlement is relatively stable and confirmed by the design unit.

    2. Early shrinkage post-pouring belt: It should be closed after the concrete age on both sides reaches 60 days.

Related questions
11 answers2024-06-18

GRC is the abbreviation of glass fiber reinforced cement in English, which refers to the mixed material of glass fiber reinforced cement. >>>More

8 answers2024-06-18

The post-pouring belt is a temporary construction joint.

In order to prevent the harmful cracks that may occur in the cast-in-place reinforced concrete structure due to temperature and uneven shrinkage in the building construction, in accordance with the requirements of the design or construction specifications, temporary construction joints are left at the corresponding positions of the foundation bottom plate, wall and beam, and the structure is temporarily divided into several parts, and after the internal shrinkage of the components, the concrete of the construction joint is poured after a certain period of time, and the structure is connected into a whole. The pouring time of the post-pouring belt should be selected when the temperature is low, and the cement can be poured or the concrete mixed with a trace amount of aluminum powder in the cement, and its strength grade should be one level higher than the strength of the component, so as to prevent cracks between the new and old concrete, resulting in weak parts. The location of the post-pouring belt should also consider the different consumption factors of the template and other measures. >>>More

8 answers2024-06-18

First of all, based on my years of experience, the content of 44kg m2 of steel bar in the small high-rise of 11 floors is reasonable. 80-90kg m2 is unreasonable, please check your information**. >>>More

6 answers2024-06-18

Post-pouring tape. It is a cast-in-place reinforced concrete structure in building construction to prevent it. >>>More

9 answers2024-06-18

The safety distance is the distance between the front of the vehicle and the rear of the vehicle in front. When driving on a highway and the speed of the vehicle is more than 100 km/h, the safe distance should be more than 100 meters. When the speed of the vehicle is above 60kmh, the safe distance should be equal to the speed; For example, at a speed of 80 km/h, the safe distance between the vehicles is 80 meters. >>>More