Summary. How to write the perception data of the completion and acceptance of the landscaping project.
Want**.
-
Article 60 of the Construction Law of the People's Republic of China The quality of the foundation works and the main structure of the building must be ensured within a reasonable service life. When the construction project is completed, the roof and wall shall not be left with quality defects such as leakage and cracking; The construction enterprise shall repair the quality defects that have been discovered. Article 61 of the Construction Law of the People's Republic of China The construction project delivered for completion and acceptance must meet the specified construction project quality standards, have complete technical and economic information of the project and the signed project warranty, and have other completion conditions stipulated by the state.
The construction project can only be delivered after the completion experience is qualified; If it is not experienced or is not qualified for acceptance, it shall not be delivered.
-
The project contains landscape, greening projects, and materials are required for completion acceptance.
Completion acceptance refers to the completion of the construction project after the development and construction unit together with the design, construction, equipment unit and engineering quality supervision department, whether the project meets the planning and design requirements and the quality of construction and equipment installation to conduct a comprehensive inspection, and obtain the completion of qualified information, data and vouchers.
Completion acceptance is an important part of the comprehensive assessment of the construction work, checking whether it meets the design requirements and project quality, and plays an important role in promoting the timely commissioning of construction projects (projects), giving full play to the investment effect, and summarizing construction experience.
Project completion acceptance refers to the completion of the construction project after the development and construction unit together with the design, construction, equipment unit and engineering quality supervision department, whether the project meets the planning and design requirements and the quality of construction and equipment installation for a comprehensive inspection, to obtain the completion of qualified information, data and vouchers. It should be pointed out that the completion acceptance is based on the phased acceptance, and the projects that have completed the acceptance before are generally not re-accepted when the house is completed and accepted.
-
This depends on whether you are a general contractor or a subcontractor, and whether Party A is a real estate company or a ** agency.
If Party A is a public unit, then it should be information, because at least urban construction should be archived.
If Party A is a private unit, if you are a general contractor construction unit, you should also provide acceptance information, if you are a subcontractor, you can be lazy if you have a general contracting company. Of course, you'd better ask the supervisor or the person in charge of Party A.
-
It definitely needs to, otherwise who will ask for money, hehe.
-
The landscaping project was completed.
Receipt report.
Unit Project Name: Bund Palm Springs Landscaping Landscape Project.
Name of construction unit: Hubei Provincial Railway Company, New Hongji Real Estate Company.
Landscaping project completion acceptance report.
The name of the unit project.
Project Type 1, Greening; 2. Garden architecture and sketches, mountains, stacked stones; 3. Miscellaneous.
1. New construction; 2. Expansion; 3. Reconstruction.
Green area Landscape architecture (sketch) area
The project cost is 2.86 million yuan.
Construction unit: Wuhan Hanxi Nursery.
Survey unit. Design unit.
Supervision unit: Wuhan Lancheng Supervision Company.
Construction application time Commencement time project.
Overview The Bund Palm Springs Landscaping Project is located at 234 Shengli Street, Jiang'an District
With a total land area of 20,300 square meters, a total of 9 high-rise buildings. The project will be green.
The aesthetics and landscape, the improvement of the living environment, the ecological benefits and the window demonstration and other functions are integrated to create a landscape, environmental protection and ecological "green landscape". Completion.
Acceptance organization. Form Completion acceptance procedure: The project has met the completion conditions, and our company has received the construction party Wuhan.
After the completion report of the Hanxi Nursery and the quality assessment report of Wuhan Lancheng Supervision Company, the organization set up an acceptance team, formulated the acceptance plan, and carried out the pre-acceptance internally, through actively sorting out the relevant engineering information, sent to the relevant departments for review, and made an appointment for completion and acceptance after passing the examination, and determined to be carried out on the morning of March 26, 2009, location: The Bund Palm Springs Community.
Completion acceptance content: greening, garden architecture sketches, water and electricity. Completion.
Acceptance opinion Acceptance of the construction unit: The project is organized by our company for acceptance, acceptance personnel, organizational form, acceptance procedures, implementation standards, and acceptance content is correct. The quality of the project is a symbol of the following requirements, in line with the requirements of the current mandatory standards for engineering construction, in line with the requirements of the design documents and legal norms, the quality assurance information is complete and effective, and the quality level is qualified.
Supervision and construction unit evaluation: After inspection, the quality of the project is in line with the requirements of China's current laws and regulations and the mandatory standards of the project, and also meets the requirements and specifications of the design documents (design changes), the quality assurance data is complete and effective, the verification quality is qualified grade, and the self-assessment quality is qualified grade.
Project completion acceptance conclusion:
Note: The conclusion is: whether it meets the national quality standards; Whether you can agree to use it.
-
1. To declare the completion of acceptance, it is necessary to provide a complete set of completion information, which everyone knows.
Second, the project completion settlement information is submitted to the construction unit or the construction unit on behalf of the audit unit, including the content can fully prove the project cost from beginning to end of all kinds of basis information, including the contract part, the change part, the on-site visa part, the acceptance of the relevant certification part of the construction unit of the settlement declaration information.
-
What should be written in the application report for acceptance of garden engineering? So, how to write the application report for the acceptance of the garden project, do you know how to write? If you don't know, let's take a look at the content of my whole cover!
**Supervision Company:
Built by our company. The first phase of the greening landscape project will be completed on the date of year, month and day according to the quantity and quality requirements of the contract. It has now been a month since the maintenance. Our company now proposes to carry out the completion acceptance of the first phase of the project.
If no, please verify the approval!
Landscape Engineering LLC.
Project Department. Date.
Project Name: Xinda Waterfront Mingdu 16 Completion Date:
Acceptance of organizational units (chapters).
The construction committee of the XX printed Tan Chi Trouble.
Doing a good job in the management of project completion acceptance and filing is important to ensure the quality of the project, maintain the order of the construction market, and protect the legitimate rights and interests of the project users.
To function. The project completion acceptance report is a certification document for the completion and acceptance of the project, and an important basis for handling the completion acceptance filing procedures and housing ownership certificate.
The project completion hail acceptance report is uniformly printed by the Hefei Municipal Construction Committee, and no unit or individual may print it privately.
Project Completion Acceptance Report" in quadruplicate, which shall be held by the construction unit, the quality supervision agency and the filing authority respectively.
If the construction unit delivers the following projects without authorization and causes losses to the user, the construction unit shall bear the liability for compensation in accordance with the law.
1. Projects that have not been completed and accepted;
2. Projects that fail to pass the completion acceptance (including projects without the "Project Completion Acceptance Report");
3. The unqualified project shall be accepted in accordance with the qualified project;
Fourth, the engineering quality supervision agency shall order the use of the project to stop and reorganize the completion and acceptance of the project.