How to write the record sheet of the supervision concrete side station

Updated on society 2024-03-04
11 answers
  1. Anonymous users2024-02-06

    1. Construction: precast concrete, concrete strength grade C30, impermeability grade P8, mix ratio number 200T-0148; A car pump was used for concrete construction on site.

    2. Supervision situation: the collapse of concrete was inspected 3 times on site, and the measured collapse was 60mm, and the strength of the concrete met the requirements of the mix ratio after inspection. 2 groups of concrete test blocks were made, and the pouring process met the requirements.

  2. Anonymous users2024-02-05

    It must be written, which part of the concrete is poured today, how many square meters, what time does the bonus start, what time does it end, what is the opening identification slump, what is the slump in the middle spot check, and finally add a witness to the retention of the test block, a total of several groups.

    There are also problems in the process, depending on your on-site situation.

  3. Anonymous users2024-02-04

    Just fill in the content of this **.

    B11 side station supervision record sheet.

    Project Name: No.: B11

    Date & Climate: Project Location:

    The part or process of the side station supervision:

    Construction Situation: Supervision Situation:

    Problems found: Handling opinions:

    Remarks: Contractor:

    Project Management Department:

    Quality Inspector (Signed):

    Year, Month and Day Supervision Unit:

    Project Supervision Agency:

    Side Station Supervisor (Signed):

    YYYYYYYYYYYYYYYYY

    Supervised by Jiangsu Provincial Department of Construction.

  4. Anonymous users2024-02-03

    How to fill in the record of the construction supervision side station:1. Fill in the general situation of the main project in the specification:

    1) Project name.

    2) Record number.

    3) Date and climate: the date of the station and the weather conditions of the day.

    4) The position or process of the side station supervision.

    2. Fill in the construction situation

    1) Whether the main construction personnel and construction management personnel are on duty.

    2) Main construction machinery and tools.

    3) A brief description of the design of the construction drawings of this part.

    4) Points to note in the construction of this part.

    5) Whether the construction conditions meet the construction requirements.

    3. Fill in the supervision situation

    Notes for Documentation:

    As a true record of the supervision work of the side station, the side station record should be different from the "supervision log", therefore, in addition to the record in the supervision day, it should also be recorded separately for future reference.

    The side station record of the supervision personnel is reviewed by the professional supervision engineer or the chief engineer through the review of the side station record, from which the key parts or key processes can be grasped, and the problems that arise, analyze the causes, formulate measures to ensure the quality of the key parts or key processes, and this is also the responsibility of the supervision work.

    The supervisor shall regularly sort out the records of the side station and report to the construction unit for review. A good side station record can not only enable the construction unit to grasp the dynamics of the project, but more importantly, to enable the construction unit to understand the supervision work, understand the service tenet and service direction of the supervision unit, and establish a good image of the enterprise, at the same time, the supervision personnel can also listen to the opinions of the construction unit, improve the supervision work in a timely manner, and improve the quality of service.

  5. Anonymous users2024-02-02

    Fill in the record of the supervision side station (concrete pouring as an example).

    1. Climate: sunny, rainy, air temperature (average temperature).

    2. Part or process: plane position (axis interval), floor (or elevation) component name: column, shear wall, beam, plate and other concrete pouring and smashing.

    3. Construction situation.

    1) Concrete strength grade: cubic meters of pouring concrete.

    2) Concrete ** method: commercial concrete (or on-site stirred concrete).

    3) Mechanical equipment used: pumping concrete (or tower crane hopper), number of vibrating rods: sets.

    4) the number of construction people: pouring people, looking at the steel bar, formwork people.

    4. Supervision: Supervision of the whole process

    1) Check the concrete mix notice and feeding list;

    2) Check the record of the on-site quality inspector or the post foreman on duty, name:

    3) Check the pouring method: meet the requirements of the construction plan, and the pouring is good (or problematic);

    4) Observe the position of the steel bar and the deformation of the formwork during the pouring process;

    5) random witness sampling to do concrete test block group;

    6) Observe the workability of concrete, and the collapse degree of the concrete is mm, and it is strictly forbidden to add water on site;

    7) to the commercial concrete mixing plant spot check computer proportioning single;

    8) During on-site mixing, spot check the measurement of concrete ingredients, and record the measured weight of cement, sand, stone, water and admixtures.

    5. Find problems:

    1) The concrete mix ratio is inconsistent with the design mix ratio;

    2) It is found that the position of the reinforcement is too large or the floor reinforcement collapses seriously or the thickness of the concrete protective layer is not well controlled;

    3) It is found that there is a phenomenon of mold expansion and slurry leakage;

    4) The concrete pouring and pounding sequence is not continuous, and the connection between the old and new concrete is not good; The debris at the joint is not cleaned up; The concrete vibration sequence is not good, and the vibration strength is not enough somewhere, and there may be leakage vibration;

    5) The concrete is too thin or too dry, which affects the pouring or blocking of the pipe;

  6. Anonymous users2024-02-01

    Backfill side station supervision record template:

    1. The mortar marking (mix ratio) of the load-bearing wall of the bricklaying project is full, the ash joints are full, the staggered joints are correct, the door and window holes are correct, the embedded parts and the buried pipeline mortar mix ratio test is measured at the side station, and the on-site inspection and measurement are measured.

    2. The position and size of the indoor wooden doors and windows are correct, flat and square, not warped, close-seam aluminum alloy doors and windows, measurement inspection, and measurement.

    3. The leveling layer, thickness, flatness, anti-crack insulation layer thickness, flatness of the roof waterproofing engineering are filled and embedded tightly, firmly bonded, wrinkle-free, non-empty, and the water drop pipe is installed firmly, the joints are tight, the drainage is smooth, there is no leakage observation, measurement observation, measurement observation and observation.

    4. The surface of the high-grade decorative veneer is smooth, the joints are tight, the geometric size of the skeleton is accurate, the installation is firm, the wallpaper wallcovering is firmly pasted, there is no hollow drum, the edge wrinkles are evenly distributed, the texture is clear, the uniform is straight, the color is coordinated, there are no joint traces of observation, measurement observation, measurement observation and observation.

    5. The wood grain of the varnish project is clear, bright and smooth, no flow wrinkle skin sandblasting, spraying and pasting firm, smooth and without delamination and cracks.

  7. Anonymous users2024-01-31

    The sample record of the supervision of the backfill side station is as follows:

    Entrusted by the company, the company undertook the supervision project of the project, and supervised the whole process of all the construction contents of the project.

    After the signing of the project supervision contract, our company immediately set up a supervision team to station at the user site, and carried out supervision work in accordance with the supervision procedures under the unified organization and arrangement of the chief engineer.

    At all stages of project construction, according to the national policies, laws, regulations, standards, norms, national standards for information technology process supervision, the project construction contract signed by the construction unit and the contractor, and the supervision contract signed by the construction unit and the supervision unit control the quality, progress, investment and change of the project, and manage the contract and information documents of the project. Hold regular supervision meetings to check the completion of various tasks and coordinate and solve existing problems;

    Submit stage summaries to users from time to time; Grasp the problems existing in the project in a timely manner and put forward supervision suggestions; Fair and impartial coordination and handling of problems encountered in the implementation of the project to ensure the quality and smooth progress of the project construction. The project supervision department fully fulfilled the obligations and responsibilities given by the supervision entrustment contract, successfully completed the supervision task of the project, and the supervision control objectives met the contract requirements.

    1. Material requirements.

    1) Crushed stone soil, sand (the consent of the design unit should be obtained when using fine and silty sand) and blasted stone slag can be used as fillers below the surface. Its maximum particle size shall not exceed 2 3 or 3 4 of the thickness of each layer (when vibrating rolling is used), and the moisture content shall comply with the regulations.

    2) The moisture content of cohesive soil should be tested, and it must meet the requirements of the design and construction specifications before it can be used.

    3) Saline soil is generally not usable. However, the filler shall not contain salt crystals, salt blocks or rhizomes of salt-containing plants, and can be used in accordance with the provisions of Table 1 8 of Appendix I of the Code for Construction and Acceptance of Earthwork and Blasting Engineering.

    2. Main equipment.

    1) Shipping earthmoving machinery includes: bulldozers, dump trucks, bulldozers, scrapers, half-bucket trucks, etc.

    2) Rolling machinery includes: hand rolling, sheep foot rolling and vibrating rolling, etc.

    3) General tools are: frog or diesel tamping machine, trolley, shovel (flat and pointed two kinds of m steel tape measure, 20 lead wire, rubber tube, etc.).

  8. Anonymous users2024-01-30

    Carry out the side station work according to your side station plan and the requirements of the contract, record the start and end time in detail, the number of workers and the equipment, and whether any problems are found. The side station supervision is basically the side station of concrete pouring, and other such as waterproofing, beam and column node reinforcement, etc., are not engaged, and the project or concealed engineering supervision that needs to be controlled by the key has to be next to the station.

  9. Anonymous users2024-01-29

    The parts that need to be recorded by the supervision side station are:

    Concealed engineering, key parts, key parts, the construction process. For example, the rebar binding process is taken on patrols. After the binding is completed, the inspection will be carried out when applying for the transfer of order. The steel bar is qualified, and when the concrete construction is carried out, the side station is carried out and the side station record is written.

    Housing construction project construction side station supervision management measures (trial) "these measures stipulate the key parts of the housing construction project, key processes, in the foundation engineering including: earthwork backfill, concrete cast-in-place pile pouring, underground diaphragm wall, soil nail wall, post-pouring belt and other structural concrete, waterproof concrete pouring, membrane waterproof layer detail structure processing, steel structure installation; In terms of main structure engineering, it includes: beam-column joint reinforcement concealment process, concrete pouring, prestressed tensioning, prefabricated structure installation, steel structure installation, grid structure installation, cable membrane installation.

  10. Anonymous users2024-01-28

    (A) the basic information including the project name, number, date and climate, the location of the project, the location or process of the side station supervision, the start time of the side station supervision, the end time of the side station supervision. The number should be reasonably determined to facilitate sorting and searching. If 2002102802 is used, it means a side station supervision record that occurred in the 02 part or process on October 28, 2002, so that it can be clear at a glance and is not easy to confuse.

    It is best to organize and bind the side station supervision record sheet regularly (such as one month) to facilitate future use and management. The climate includes cloudy, sunny, rainy, snowy, and temperature variations (maximum, minimum), wind. Accurate weather conditions can allow supervisors to judge whether the supervision part of the side station has weather conditions or require the construction unit to take corresponding operational measures according to the weather conditions.

    Weather temperature has a significant impact on the growth rate of concrete and mortar strength, and rain will affect the moisture content of sand and stone, which is related to the mix ratio of concrete and mortar, and then affects its strength, so it is very important to carefully record the weather conditions. The part or process of the side station supervision should be written clearly the line, elevation, or a branch (sub-division) project, sub-project, inspection batch.

    2) The construction situation mainly records the construction process, test and inspection of the construction unit in the key parts or key processes, the use of machinery and equipment and materials, and the safe and civilized construction.

    3) The supervision situation mainly reflects the project supervision agency in the process of supervision of the station three control (investment, progress, quality control), two management (contract, information management), a coordination (coordination of the relationship between the parties) behavior.

    4) Problems and handling include three aspects: finding problems, dealing with opinions, and remarks. Problems can be found by supervisors, or by personnel of construction, design, and construction units. The handling opinion should be a conclusion reached after analyzing the problem (not necessarily the final conclusion, such as the project supervision agency forwards the analysis of the problem to the design or construction department for processing).

    Remarks are the tracking record of the problem and the treatment, and the final conclusion record after the problem is handled, that is, the "closure" of the entire problem after it is handled.

    5) Construction, supervision personnel sign to confirm on time to sign confirmation is one of the important aspects of the station supervision record, no construction quality inspectors, station supervision personnel to sign the station supervision record is invalid. If you don't sign in time, you don't pay attention to and are not responsible for the supervision of the side station, so you must have a rigorous timeliness. It is recommended that the supervision personnel of the side station should write, confirm and sign within 24 hours after the end of the supervision of the side station, and send it to the construction quality inspector; The construction quality inspector confirms the signature within 24 hours after receiving the supervision record of the side station, and returns it to the side station supervisor, if there is any doubt in the middle, the two sides should discuss and solve it within 24 hours.

  11. Anonymous users2024-01-27

    Summary. Hello, glad to answer for you! Need to fill in the side station supervision record: according to your side station plan and the requirements of the contract to carry out the side station work, detailed record of the start and end time, the number of workers and equipment, whether any problems are found.

    What is the need to fill in the side station supervision record?

    Hello, glad to answer for you! Need to fill in the side station supervision record: according to your side station plan and the requirements of the contract to carry out the side station work, detailed record of the start and end time, the number of workers and equipment, whether any problems are found.

    The parts that need to be next to the station are determined in the supervision rules when starting, and the key parts, key nodes, and key parts should be selected, and the concrete pouring inspection of other parts can be done. 2. Construction situation: construction methods, construction technology, quality assurance measures, and the implementation of concrete construction plans in the winter rainy season; (such as the slump of concrete, the geometric size of the pouring components, temperature measurement records, site coverage, etc.) and special professional construction technology; Axis, elevation, etc.; A total of 4 pages 2 construction supervision limited liability company construction machinery and equipment use (main equipment name, specifications, quantity, whether the operation is normal, etc.); Material usage.

Related questions
10 answers2024-03-04

Look at the backfill thickness. The compaction check meets the design requirements.

9 answers2024-03-04

The quality objectives and level of the project are concretized through design supervision, which is used as the basis for construction. The quality of the design directly affects the use value and function of the project, and is the decisive link of the project quality. >>>More

6 answers2024-03-04

Before the supervision company signs the contract with the decoration company, the first review of the decoration company's procedures are complete, whether it is legal and valid, if the customer insists on inviting the decoration team without procedures, the supervision company will not be jointly and severally liable. If the customer entrusts a formal decoration company, the supervision company will supervise the construction company to repair and rectify the quality problems after the end of the project, and the warranty period is free of charge. >>>More

15 answers2024-03-04

Responsibilities of a professional supervising engineer.

4 answers2024-03-04

This is some of the information I found on the Wuhan Home Improvement ** Internet, if you still have some questions about decoration, you can check it, you should be able to find out what you need to know. The following is for reference only: >>>More