How to set budget quota items for brick through valve wells

Updated on society 2024-04-29
12 answers
  1. Anonymous users2024-02-08

    Calculation rules. 1. Artificial earthwork.

    1. Manual excavation of earthwork, silt, quicksand.

    2. Manually dig trenches and foundation pit earthwork.

    3. Manual transportation of earthwork, silt and quicksand.

    4. Backfilling, tamping, leveling the site, and tidying up the slope.

    5. Cutting down trees, digging roots, and shoveling turf by hand.

    6 retaining plates.

    7. Manually excavate the steps of the embankment and clean the foundation of the embankment.

    8. Manually chisel and cut stones.

    9. Manually chisel (cut) trenches, foundation pit stones, and stone branch ditches.

    10. Artificial stalls and slope trimming.

    11 Artificial stone transportation.

    12 Manually dug piles.

    Second, mechanical earthwork.

    1 Mechanical excavation.

    2. Mechanical digging of silt and quicksand.

    3. Mechanical shipment of earthworks.

    4 people load the machine to transport the earth.

    5. Mechanical leveling of the site, filling (stone) rolling.

    6 Mechanical drilling blasting flat cornerstone.

    7. Mechanical drilling and blasting of trench stones.

    8. Mechanical drilling and blasting of foundation pit stones.

    9. Mechanical chiseling of rock, concrete and reinforced concrete.

    10. Mechanical digging of gravel.

    11 Mechanical shipment of stones.

    12 people loaded the machine to transport stones.

    13. Pre-cracking blasting and drilling damping holes.

    14 Strong compaction of the foundation.

  2. Anonymous users2024-02-07

    1. If it is a municipal project and it is constructed in accordance with the standard drawing, it can be set according to the "seat". Select the appropriate well depth. This is the most convenient and simple.

    2. If it is not a municipal project constructed in accordance with the standard drawing, the project should be separated. Generally, it is the cushion, well masonry, plastering, and manhole cover installation.

    3. Construction engineering and non-stereotyped municipal engineering projects are the same.

  3. Anonymous users2024-02-06

    There is a supplementary quota, set for each increase or subheading.

  4. Anonymous users2024-02-05

    Increase the coefficient. As long as the audit agrees, it's OK, and the main thing is to negotiate.

  5. Anonymous users2024-02-04

    Labor and material costs are not adjustable.

  6. Anonymous users2024-02-03

    Question 1: What is the quota of the valve well sleeve Generally, the valve well is a municipal quota and there is an outdoor water supply valve well quota. But I don't know that there are several ways to do the valve wells you mentioned, some are brick and some are concrete.

    There are brickwork and concrete covers. The quotas are all different. You take a good look at the valve well design instructions in the more appropriate.

    Question 2: How to set the quota of the valve well 1, if it is a municipal project and is constructed in accordance with the standard drawing, it can be set according to the "seat". Select the appropriate well depth. This is the most convenient and simple.

    2. If it is not a municipal project that is constructed in accordance with the standard drawing, the project must be separated. Generally, it is the cushion, well masonry, plastering, and manhole cover installation.

    3. Construction engineering and non-stereotyped municipal engineering projects are the same.

    Question 3: What is the quota of the valve well sleeve There are various valve wells in the civil engineering quota, if the amount is small and afraid of being complicated, it is OK to estimate the price with an independent fee.

    Question 4: What is the quota for the production and installation of steel valve wells 1, I don't know how high the well is, and I calculate a ** product according to the height.

    2. Suggested production application: install the "Carbon Steel Flat Bottom Flat Cap Container Overall Equipment Production VN 1 or VN2 Quota" in Volume 5 of the quota.

    3. Recommended installation application: carbon steel stainless steel container installation medium and low pressure elevation of 10m and internal weight within 2t.

    Question 5: How to set the budget quota sub-item of the brick through valve well 1, if it is a municipal project and is constructed in accordance with the standard drawing, it can be set according to the "seat". Select the appropriate well depth. This is the most convenient and simple.

    2. If it is not a municipal project constructed in accordance with the standard drawing, the project should be separated. Generally, it is the cushion, well masonry, plastering, and manhole cover installation.

    3. Construction engineering and non-stereotyped municipal engineering projects are the same.

    Question 6: Who knows what quota for the valve well sleeve borrows the civil construction quota.

    Question 7: The valve well is made by the fire department, how to set the quota This valve well chamber is calculated according to the building quota.

    Question 8: Valve well, steel manhole cover production quota? The valve well can be set of civil engineering related quotas, and the steel manhole cover can be made and installed with metal brackets, or the steel components of civil engineering can be made and installed, and the installation quota is slightly higher.

    But in the installation budget, these are small projects that have little impact on the overall price.

    Question 9: What is the quota of the brick-built valve well sleeve The civil engineering quota of the brick-built valve well sleeve.

    Question 10: The gate valve sleeve sleeve (valve well) of the outdoor fire hydrant should be the quota, and the outdoor fire hydrant in the factory area is generally not needed. If you really want to put it, just refer to the indoor one, and you shouldn't need to put it.

  7. Anonymous users2024-02-02

    In the well set quota used (brick well, pool wall depth within 3m), the set of this quota sub-item includes the price of materials, such as: cement, sand, bricks. If the brick-built sewage well needs construction engineering or municipal engineering, the municipal engineering can directly apply the shaping well; If it is a construction project, it is necessary to calculate a separate set of items, involving sub-items, such as cushioning, masonry, plastering, covering, etc.

  8. Anonymous users2024-02-01

    The cost of brick wells is applied to the municipal engineering quota.

    1) The masonry cement mortar of each layer of brick masonry must be filled with full, and the cement mortar number shall not be less than the number.

    2) The launder in the inspection well should be masonry at the same time as the wall of the well. The launder of the manwell should be masonry when the wall of the well is built below the top of the pipe, and it should be compacted and wiped with mortar layers.

    3) The gap between the nozzle and the wall of the manhole access round pipe should be tightly sealed, and when the diameter of the access pipe is greater than 300mm, the brick ring should be reinforced.

    4), the plastering inside and outside the well must be carried out in strict accordance with the requirements of the technical specifications, and the plastering of the inner and outer walls must be carried out before the backfill, and the water in the wellbore is drained at one time.

  9. Anonymous users2024-01-31

    If there is no complete set of quota items that can be applied, the well body should be applied separately to the quota items, such as brick well body, stucco, cushion, earthwork excavation, etc.

  10. Anonymous users2024-01-30

    Hello: If it is a stereotyped well, it can be set in the second chapter of the sixth volume of the "Shandong Provincial Municipal Consumption Quota", and the appropriate item is selected according to the size, if it is a non-shaped well, it can be set in the third chapter of the non-stereotyped well, and you can also refer to the "Shandong Province Construction Consumption Quota" Chapter VIII Part IV inspection wells, septic tanks and others to select the appropriate items to apply.

  11. Anonymous users2024-01-29

    Which quota is applied to the cost of brick wells? . .

    If the wall and the bottom of the well are unified materials, whether they are uniformly applied. . .

    It's better to have a detailed explanation, the quota of any province is fine, it's better to give a data...

  12. Anonymous users2024-01-28

    Outdoor water supply valve well, fire hydrant well, diameter 800mm and depth 1500mm, red brick well. How to set a quota? First, it can be used by borrowing the relevant inspection well quota sub-items in the municipal quota.

    The second is to calculate the engineering quantity of wall masonry, plastering, bottom and cover of the water supply valve well according to the practice marked in the drawings, and then set the corresponding quota items in the building quota.

    Municipal projects (according to municipal quotas) can be distinguished by diameter and depth according to the seat cover, and the corresponding quota sub-item of the sub-project quantity set can be calculated (according to the civil engineering quota) in the plant area.

    1. Outdoor water supply valve well, fire hydrant well, diameter 800mm deep 1500mm, red brick well; 2. According to the type of valve, according to the shape of the set, the fire hydrant well is divided into above-ground type and underground type; 3. As shown in the figure

Related questions
9 answers2024-04-29

Here are some of the well-known brands recognized in the valve industry, which are widely recognized and have a high reputation. While rankings may vary depending on time and market conditions, the following brands are generally considered to be among the top brands in the valve industry: >>>More

12 answers2024-04-29

1. If the round well is 1 brick wall: (.

2. If the rectangular well is 1 brick wall: (. >>>More

21 answers2024-04-29

Smoking is an act that harms others and does not benefit oneself, and smoking not only harms the health of those around you, but also causes harm to your own health. Quitting smoking early and completely is beneficial to yourself and others. So how can you quit smoking completely? >>>More

12 answers2024-04-29

This is a small home remedy collected by yourself.

30 grams of dandelion, cork, red peony and danpi, 20 grams of peach kernels, 30 grams of Poria cocos, and 15 grams of Angelica dahurica. One pair can be used 3 times a day. Add 3000 ml of water first, after boiling, remove the dregs, then pour the liquid medicine into the basin, smoke it while it is hot and then wash the affected area, about 20 minutes each time. >>>More

7 answers2024-04-29

Deal with silverfish insects.

Rely on professional pesticides. >>>More