It can't be equated. Supervision parallel inspection is a means of supervision and control of project quality. If you do the parallel inspection of that sub-item, you can do the supervision parallel inspection record form of that sub-item, and you can not do it if you don't do it.
The sub-project and inspection batch inspection and acceptance records are the construction quality acceptance data of building and structural engineering, which must be done.
How to fill in the supervision parallel inspection record form:
1. The construction unit shall first carry out the self-inspection of materials, components and equipment, concealed projects, inspection batches, sub-items, divisions and unit projects, etc., and report to the supervision unit for inspection after passing the self-inspection.
2. After the supervision unit receives the inspection information, the supervision engineer reviews the inspection information; When qualified, the supervising engineer shall conduct parallel inspection of the materials, components, equipment, concealed works, inspection batches, sub-items, divisions and unit projects according to the agreed time, and return to the construction unit when unqualified, and the construction unit shall re-submit for inspection after modification.
3, the supervision engineer for parallel inspection is generally based on data records, after the actual measurement, fill in the parallel inspection record form, and the test data and the standard value of the inspection project is compared, give conclusive opinions, Fenhu standard requirements to be signed for acceptance, when unqualified, according to the severity of the non-conformance issued "non-conformance notice" or "supervision engineer notice", after the construction unit rectification, and after the supervision personnel confirm that qualified, can be signed for acceptance.
-
The supervision belongs to the supervision of the construction party, and we will do a good job of technical information. As for the superintendent not to sign. Find the boss!
-
Supervision parallel inspection is the project supervision agency uses certain inspection or testing methods, on the basis of the contractor's self-inspection, according to a certain proportion of independent inspection or testing activities.
"Parallel inspection" means that one party is the contractor for the inspection and acceptance of the project for which it is responsible for construction, and the other party is the supervision agency, which is entrusted by the construction unit to carry out independent inspection and acceptance of the project on the basis of the self-inspection of the construction unit and in accordance with a certain proportion. Two inspections and acceptances of the performance of the same batch of inspection items within the specified time. The project supervision agency uses certain inspection or testing methods to independently carry out inspection or testing activities in accordance with a certain proportion on the basis of the contractor's self-inspection.
As an important means of engineering construction supervision in quality process control, parallel inspection is also an important method for quality control in other industries.
"Parallel test" has the following meanings:
1. The implementer of the "parallel inspection" must be the project supervision agency and the chief engineer;
2. The "parallel inspection" implemented by the project supervision agency must be carried out on the basis of the contractor's self-inspection;
3. The inspection or testing activities of "parallel inspection" must be carried out independently by the supervision machine;
4. The inspection or testing activities of "parallel inspection" must be carried out in accordance with a certain proportion.
Legal basis] Regulations on the Quality Management of Construction Projects
Article 26 The construction unit shall be responsible for the construction quality of the construction project.
The construction unit shall establish a quality responsibility system and determine the project manager, technical person in charge and construction management person in charge of the project.
If the construction project is contracted generally, the general contractor shall be responsible for the quality of all construction projects; If one or more of the survey, design, construction and equipment procurement of construction projects are subject to general contracting, the general contractor shall be responsible for the quality of the construction projects contracted or the equipment purchased. Article 36 The project supervision unit shall, in accordance with laws, regulations and relevant technical standards, design documents and construction contracts, supervise the construction quality on behalf of the construction unit, and assume supervision responsibility for the construction quality.
-
Parallel inspection means that one party is the contractor for the inspection and acceptance of the project for which it is responsible for construction, and the other party is the supervision agency, which is entrusted by the construction unit to carry out independent inspection and acceptance of the project on the basis of the self-inspection of the construction unit and in accordance with a certain proportion of nonsense. Sampling inspection is two inspections and acceptances carried out by Zao Xiang on the performance of the inspected items within the specified time.
-
The difference between the sub-project quality inspection and evaluation form and the project inspection batch quality acceptance file is as follows:
1. The essence of acceptance is different.
The sub-project quality inspection and evaluation form is made on the basis of the quality acceptance of the engineering inspection batch, which usually plays a role in induction and sorting, and is a statistical table, without substantive acceptance content. The quality acceptance record of the engineering inspection batch is whether the acceptance quality is qualified or not, and there is the acceptance content.
2. The evaluation results are different.
The sub-project quality inspection and evaluation form is to score the quality, and the quality acceptance record of the engineering inspection batch is to evaluate the quality whether it is qualified or not.
3. The acceptance personnel are different.
The sub-project quality inspection and evaluation form shall be accepted by the supervising engineer (the professional and technical person in charge of the project of the construction unit) and the person in charge of the professional technical operation of the project; The quality acceptance record of the inspection batch shall be filled in by the professional quality inspector of the construction project, and the supervising engineer (the professional and technical person in charge of the project of the construction unit) shall organize the professional quality inspector of the project for acceptance.
-
What is included in the supervision of parallel inspections is introduced as follows:
1. The implementer of the "parallel inspection" must be the project supervision agency and the chief engineer;
2. The "parallel inspection" implemented by the project supervision agency must be carried out on the basis of the contractor's self-inspection;
3. The inspection or testing activities of "parallel inspection" must be carried out independently by the supervision agency;
4. The inspection or testing activities of "parallel inspection" must be carried out in accordance with a certain proportion.
The state clearly stipulates that the chief engineer shall, in accordance with the requirements of the engineering construction supervision foundation dust burial specifications, take the form of "side station", "patrol brother" and "parallel inspection" to supervise the construction project. The state stipulates in the form of law that the supervision agency has three important means for the quality control of the project in the construction stage.
This also makes it clear that the implementer of "parallel inspection", one of the control means, must be the supervision agency and the chief engineer.
-
One is the quality inspection and evaluation, and the other is the quality acceptance record.
The quality inspection and evaluation of the sub-project is required to score, such as the bricklaying sub-item is completed, the plastering sub-item is completed, and the quality inspection department will do the assessment according to the specification to give how many points.
The quality acceptance record is also a way to inspect the quality, only divided into qualified and unqualified, such as the quality department of the finished rib binding will pass the inspection of the bar to pass the next process, but to sign on the acceptance record.
-
The supervision agency uses certain inspection or testing methods, on the basis of the contractor's self-inspection, and independently conducts inspection or testing activities in accordance with a certain proportion. The quality assessment of the concealed works, inspection batches, divisions and sub-projects submitted by the contractor for inspection by the supervision personnel cannot be fully based on the data reported by the contractor. The conclusion of the quality of the project should be made by the supervision agency on the basis of verifying the correctness of the data after the "parallel inspection" review.
-
It can be the content of the inspection, such as axis lofting, various measured quantities, reinforcement acceptance, and formwork acceptance. It can also be the content of the inspection: concrete test block strength, steel bar tensile test, welded steel bar test.
-
The project supervision department shall inspect and accept the project in accordance with the actual construction and according to the acceptance specifications and construction drawings, including: concealed engineering, inspection batches, sub-projects and sub-projects.