How to make a construction plan for the construction of elevator foundation with calculation formul

Updated on society 2024-03-27
5 answers
  1. Anonymous users2024-02-07

    a.Approximate calculation of the load P borne by the foundation: p = (cage weight + outer cage weight + counterweight + total weight of guide rail + load) For example, the erection height of SCD200 200 is 150 meters, and the maximum pressure is pmax = 710kn);

    b.The ground bearing pressure under the concrete foundation slab shall not be less than, the foundation is poured C30 concrete, and the thickness of the foundation concrete is not less than 330mm;

    c.Reinforcement grid: diameter of 8mm steel bar, square interval of 250 250 250mm;

    d.The concrete foundation plane should be smooth and clean, and the levelness error of the foundation plane should not be greater than 5mm;

    e.The anchor bolt hook must hook the rebar of the rebar grid and weld it firmly;

    f.The strength of the foundation concrete must reach more than 70% of the design strength before the machine can be erected.

    Approximate calculation of the base bearing p.

    p = (cage weight + outer cage weight + total weight of guide rail frame + counterweight + load weight).

    For example, SCD200 200 elevator has an erection height of 150m (see "Lift Performance Parameter Table" for weight).

    Cage weight (double cage): 1600 2kg

    Outer cage weight (fence): 820kg The total weight of the rail frame (a total of 100 standard sections is required, each section weighs 184kg), 184 kg 100

    Counterweight (double weight) 1100 kg 2

    Each car has a load capacity of 2000kg 2000 kg 2

    The base bearing is approximately equal to:

    p = [(1600×2)+820+(184×100)+(1100×2)+(2000×2)]×

    60102 kg

    60102 kg × n/kg = 589000 n = 589 kn

    If the foundation is made according to the maximum pressure pmax = 710 kN, it meets the requirements for the use of the lift. The pressure on the ground shall not be less than.

  2. Anonymous users2024-02-06

    , internal matching? 4@2000 double-layer two-way rebar? ?p lb= Due to the construction process of the three parts of the foundation underground, the verticality and settlement of the construction hoist are regularly monitored, and the safety is done

  3. Anonymous users2024-02-05

    Summary. The high point of local concrete pouring on the roof of the basement will be added, and the roof will be reinforced and supported by steel pipes or temporary structural columns;

    Is elevator foundation concrete calculated according to drawings? Generally, the engineering quantity is calculated according to the drawings.

    Is it a permanent elevator or a temporary elevator for construction?

    The contract generally stipulates that the main structure is calculated according to the drawings.

    Yes, the concrete and steel bars of the main structure are calculated according to the drawings.

    What if it's a temporary elevator for construction?

    The permanent elevator foundation and design drawings will have side walls and bottom plates in the basement drawings.

    Construction elevators, there are.

    There is an invoice, ** part of the elevator foundation, I think it should be a temporary elevator construction, should be calculated according to the facts, right?

    The high point of local concrete pouring on the roof of the basement will be added, and the roof will be reinforced and supported by steel pipes or temporary structural columns;

    Some don't have a basement, so they pour a similar independent foundation, and put steel bars inside.

    In the case of an independent foundation, the basic part is calculated based on facts?

    It is estimated that it is a construction elevator. Permanent elevator foundations are generally contained in the basement.

    There are also drawings for the independent foundation, and the supporting drawings given by the construction elevator manufacturer, how long and wide and how thick the site can be done according to this.

    Oh, that is, whether it is a construction elevator or a permanent elevator, it should be calculated according to the drawings?

    Yes, it is calculated according to the drawing. Regardless of whether it is permanent or temporary.

  4. Anonymous users2024-02-04

    a.The load p of the foundation is approximated: p = (cage weight + outer cage weight + counterweight + total rail weight + load).

    For example, the SCD200 200 type has an erection height of 150 meters and a maximum pressure of Pmax=710kN);

    b.The ground bearing pressure under the concrete foundation slab shall not be less than, the foundation is poured C30 concrete, and the thickness of the foundation concrete is not less than 330mm;

    c.Reinforcement grid: diameter of 8mm steel bar, square interval of 250 250 250mm;

    d.The concrete foundation plane should be smooth and clean, and the levelness error of the foundation plane should not be greater than 5mm;

    e.The anchor bolt hook must hook the steel bar of the Qinzhou ridge grid of the reinforcement mesh and be welded firmly;

    f.The strength of the foundation concrete must reach more than 70% of the design strength before the machine can be erected.

    Approximate calculation of the trace rent of the foundation bearing p.

    p = (cage weight + outer cage weight + total weight of guide rail frame + counterweight + load weight).

    For example, SCD200 200 elevator has an erection height of 150m (see "Lift Performance Parameter Table" for weight).

    Cage weight (double cage): 1600 2kg

    Outer cage weight (fence): 820kg

    The total weight of the rail frame (a total of 100 standard sections is required, each section weighs 184kg) 184

    kg×100

    Double-weight (double) 1100

    kg 2, each cage has a load capacity of 2000kg

    kg 2 base bearing approximately equal to: p

    kgkgn/kg

    nkn can withstand the maximum pressure pmax=

    The foundation made by kn meets the requirements of the use of the lift. The pressure on the ground shall not be less than.

  5. Anonymous users2024-02-03

    Table of Contents. 1. Project overview 2

    Second, the equipment overview 3

    3. Lift foundation 5

    Fourth, attached to the wall frame 10

    5. Preparation before the installation of the elevator 12

    Sixth, install the outer cage chassis 12

    7. Install the foundation section and two standard sections 12

    8. Install the cage (left) 13

    9. Install the cage (right) 13

    10. Install the outer cage 14

    Ten. 1. Guide rail installation (the height of the standard section guide rail frame is installed according to the height requirements of the first attached wall) 14

    Ten. Second, the installation of the transmission mechanism - drive body assembly (external), (built-in installation in the cage) 15

    Ten. 3. Install the attached wall frame 15

    Ten. 4. Power cord installation and electrical safety test 16

    Ten. 5. Install cable pulleys and conductive devices 16

    Ten. 6. Cable protection frame (barrel type) installation 17

    Ten. 7. Windproof ring installation 18

    Ten. 8. Installation of limit iron 18

    Ten. 9. Landing door installation 18

    Two. 10. Climatic conditions at the time of installation 19

    Two. Ten. 1. Post-installation inspection 19

    Two. Ten. Second, delivery and acceptance 20

    Two. Ten. 3. Preparation before disassembly 20

    Two. Ten. Fourth, the dismantling of the construction hoist 20

    Two. Ten. 5. Safety matters for dismantling the construction hoist 21

    Two. Ten. Sixth, the construction elevator (repair, maintenance) quality acceptance system 21 I have a template, leave an email to send it to you.

Related questions
20 answers2024-03-27

1. The nature is different.

On-site visa, when there is a problem during the construction process, because it takes time to submit for approval, it is a process of approval by the person in charge of the site on the spot at the construction site. The on-site representative of the employer (or its authorized supervisor or project cost consultant) and the on-site representative of the contractor shall sign and certify the liability events involved in the construction process. >>>More

6 answers2024-03-27

First of all, whether you are an interesting woman or an interesting man, you must learn to read. People who read books are really interesting. I once knew a girl who came from a scholarly family, her parents were both university professors, and she started reading from a few years old until she was in her twenties, and every night when she went home and washed up, she had to read for two hours, and she took out a book from her bag to read in her free time. >>>More

11 answers2024-03-27

1. Work under the direct leadership of the project manager and implement safety first. >>>More

11 answers2024-03-27

First of all, you must have a kind heart. On the basis of doing your own job to help others. Help others when they are in trouble, regardless of their own gains and losses. >>>More

13 answers2024-03-27

A good mother is a role model for her daughter or son. Don't just be reasonable, learn to lead by example. >>>More