What are the contents of the materials submitted to the supervision office for review of wires and c

Updated on society 2024-05-17
17 answers
  1. Anonymous users2024-02-10

    The type, quantity, specification of the material entering the site, the factory certificate, the inspection certificate, the re-inspection report, and then the inspection form.

  2. Anonymous users2024-02-09

    The manufacturer certificate, quantity table, and high-voltage cable of the cable are required to do electrical tests.

  3. Anonymous users2024-02-08

    Certificate, factory inspection report, inspection report, production license, national compulsory product certification 3C, manufacturer business license.

  4. Anonymous users2024-02-07

    Insulation test material for material testing.

  5. Anonymous users2024-02-06

    Report and talk about limb tung materials: enterprise qualifications, personnel qualifications, construction organization design, general construction schedule, various special construction plans, safe and civilized construction plans.

    Measurement and verification data:

    Engineering positioning measurement pay-off record, line inspection record

    Quality certification documents for materials, equipment, and components:

    Certificate, factory inspection report and retest report, commercial concrete qualification, commercial concrete information, other materials of the certificate, record certificate and application form.

    Check the test data:

    Rebar test welding, finished welding retest report, test block test report and other test data, material laboratory qualification application form.

    Basis for compilation

    1) Project supervision, planning and supervision contract, construction contract;

    2) Design drawings, design changes and explanatory documents;

    3) Engineering geology, water ripple geological survey report, meteorological data, etc.;

    4) The laws and regulations of the state and Shaanxi Province related to engineering construction;

    5) Relevant technical specifications, procedures, standards and management procedures issued by the state, Shaanxi Province and Xi'an City;

    6) The approved construction organization design and special construction plan submitted by the contractor.

    The above content refers to: Encyclopedia - Construction Engineering Supervision.

  6. Anonymous users2024-02-05

    All the materials, equipment and semi-finished products used in the project entity and construction safety facilities shall be reported to the supervisor for inspection and approval. Otherwise, what is quality control and safety monitoring?

    The inspection form is attached to the list of incoming batches, quantities, places of origin, and factory quality certificates.

    Among them, cement, steel, blocks, sand, stone, waterproof materials, energy-saving insulation materials, etc. must also have a retest report for entering the site to witness and send samples.

    The construction unit shall report the information of the supervision before the official start of the project

    1. A copy of the notice of winning the bid---

    2. A copy --- the bidding documents.

    3. Construction contract.

    4. Commencement application report.

    5. Qualification certification materials.

    Unit qualification materials: qualification certificate business license. Work safety license. Organizational Certificate. Tax registration certificate.

    Personnel qualification certificate: project manager and constructor certificate. Technical person in charge of engineer certificate. Quality inspector certificate. Constructor's certificate. Safety Officer Certificate. Material Personnel Certificate. Including special types of personnel operation certificates: electricians, scaffolders, welders, etc.

    Survey lofting record: measurement control point review record control **) point layout record leveling point layout record.

    Original terrain retest records, etc.

    Equipment and materials for review: The construction machinery used for this project includes the driver's mechanical operation certificate, and if you need to use special equipment, you must have the acceptance certificate of the local ** regulatory department and the factory qualification certificate of the special equipment.

    6. Construction organization design.

    7. Special construction plan for safety.

  7. Anonymous users2024-02-04

    The material review first reviews the results of the self-inspection, sees whether the specifications and quantity list are consistent with the warranty certificate in the production, and then reviews whether the warranty certificate is valid, and finally the data results of the on-site spot check.

  8. Anonymous users2024-02-03

    The application form for the entry inspection of the batch of materials, the factory inspection report (or certificate) of the batch of materials, and the sampling test report of the batch of materials.

  9. Anonymous users2024-02-02

    Cement, sand, steel bars, etc., almost all of the raw materials imported by the construction unit must be reported to the supervision unit for inspection.

  10. Anonymous users2024-02-01

    How does the supervisor review the qualifications of the laboratories selected by the construction project department?

  11. Anonymous users2024-01-31

    1. Information that should be provided to the supervisor before the start of construction.

    1) Unit qualification (including subcontractor qualification), personnel qualification, and employment certificate;

    2) Quality management system, quality management procedures and systems, safety technical measures, etc.;

    3) Construction organization design;

    4) Datum point and baseline retest data;

    5) Horizontal control network data.

    6) Commencement report.

    2. The materials that the construction party should provide to the supervision;

    1) Construction unit qualification certificate and safety construction certificate application form, 2) construction organization design, construction plan and approval form, project commencement application form 3) temporary facilities special plan, safety construction special plan, special operation personnel post certificate and application form, 4) material entry record and material application form.

    5) Sub-project quality acceptance records, construction inspection batches, concealed engineering records.

    6) Division project acceptance application and construction summary.

  12. Anonymous users2024-01-30

    You don't need to provide any information to the supervisor! Wires and cables are needed! Add a margin of fifteen percent to the dimensions on the drawings provided according to the design and you're good to go!

  13. Anonymous users2024-01-29

    Must have a certificate of conformity. inspection report. and 3C certification.

  14. Anonymous users2024-01-28

    Manufacturer, certificate, cable sample.

  15. Anonymous users2024-01-27

    Qualification certificate, safety production license, business license, tax registration, etc. of the construction enterprise (copy);

    The construction enterprise appoints the project manager and the members of the project department, the project manager and the members of the project department have their respective job certificates, safety officer certificates, etc. (copies);

    The formal construction organization design document of the project (pending the approval of the superintendent); Notice of winning the bid, general contract, etc. (copy).

    The construction organization design document of the project shall contain the specific division of the inspection batch and the retention plan of the test block of the unit project; The contract shall contain the construction budget of the unit project.

  16. Anonymous users2024-01-26

    1. The construction organization design (plan) is submitted for review.

    2. Drawing review record.

    3. Technical (safety) disclosure.

    4. Commencement report.

    5. List of management personnel 6. Engineering and technical documents application form.

    The construction organization plan is attached.

    7. Subcontractor qualification application form.

    The table attaches the qualification of the enterprise.

    8. List of project management personnel.

    A copy of the qualification certificate is attached.

    9. Go through the entry procedures with Party A and sign a security agreement.

  17. Anonymous users2024-01-25

    First of all, of course, is the report on the commencement of construction

    Then the on-site building materials are submitted for review

Related questions
10 answers2024-05-17

1. The prefabricated pile is prefabricated first, in the prefabrication process, it has been maintained, and it does not need to be maintained after driving into the soil. >>>More

8 answers2024-05-17

The project supervision is well managed, and it is over every day to find a little fault, and there is a sign after completing the progress, how simple it is. The salary is a little lower, but there is a lot of oil and water, and you have just graduated. After two years, you'll know that it's not a problem to get more than 100,000 a year. >>>More

11 answers2024-05-17

GRC is the abbreviation of glass fiber reinforced cement in English, which refers to the mixed material of glass fiber reinforced cement. >>>More

8 answers2024-05-17

1. Information required for construction project application: >>>More

8 answers2024-05-17

First of all, based on my years of experience, the content of 44kg m2 of steel bar in the small high-rise of 11 floors is reasonable. 80-90kg m2 is unreasonable, please check your information**. >>>More