You also design what the requirements are, and write down the areas that are prone to problems based on experience.
-
Install the control panel, install the lamp, install the lightning protection and grounding! Bridge installation system commissioning.
-
Name of the construction unit.
The name of the unit project.
Construction site. The construction content is universal.
Security technology. Disclosure content.
1) Operators must strictly abide by the safety production discipline when entering the site, memorize and abide by the safety technical operation procedures, and use personal protective equipment correctly.
2) The scaffolding for high-altitude work is stable, covered with scaffolding, set up maintenance railings, probe boards are strictly prohibited, pad height operations are not allowed, tools and materials must be placed securely, and it is strictly forbidden to throw objects downward.
3) The wooden benches and brackets used must be stable and firm, and it is strictly forbidden to stand on the balcony railings, doors and windows, radiators, washbasins and other parts of the work, and it is strictly forbidden to step on the scaffolding up and down the outer window sill.
4) Derricks, gantries and self-standing frames to lift materials must be docked before they can enter the plate to pull materials, and they are not allowed to walk backwards. When the hanging plate is lowered, it is strictly forbidden to put hands and heads into the frame, and it is not allowed to rest, laugh and play on the edge of the unloading platform.
5) Ropes and pulleys must be tied firmly, the ropes are strong, and the hanging objects are not allowed to collide with the hanging scaffolding.
6) The power cord of the hand-held power tool must be in good condition, equipped with a leakage protector, one machine and one gate, and it is strictly forbidden to temporarily erect the power cord on the lighting or other lines.
7) Operators must go up and down by passages or ladders, and it is strictly forbidden to climb scaffolding, derricks, self-standing frames, gantries or take hanging plates up and down. Construction.
On-site targeting. Sexually safe intercourse.
Bottom writers.
Reviewers. Signature of the approver and the person who submitted the former.
Accept the confession. Signature of the person in charge.
Disclosure time. Signature of the operator.
This form is in duplicate, one copy is kept by the team and one copy is archived.
-
First, the principle of preparation of safety technology disclosure.
The safety technical disclosure should be based on the safety measures in the construction organization design, combined with the specific construction methods, combined with the on-site operating conditions and environment, and the written materials for the safety technical disclosure with strong operability and pertinence.
Second, the main content of the safety technology disclosure.
1. Project overview;
2. Dangerous parts of engineering projects and sub-projects;
3. Specific precautionary measures to be taken for dangerous parts;
4. Safety precautions that should be paid attention to during operation;
5. Safety operation procedures and specifications that operators should abide by;
6. Correct operation of safety precautions;
7. Measures to be taken when discovering potential accidents;
8. Avoidance and first aid measures that should be taken in time after the accident is discovered;
9 Miscellaneous. Third, the basic requirements for safety technology disclosure.
1. Implement step-by-step disclosure: the general contractor of the construction department shall make a disclosure to the project department, the project department to the construction team, and the construction team leader to the operator;
2. The content of safety technology disclosure should be comprehensive, specific and targeted;
3. According to the characteristics of different projects and different construction methods, the safety technology disclosure should be based on the construction site and the surrounding environment, and the corresponding safety measures and requirements should be put forward from the protection and technology;
4. The safety technology disclosure must be carried out in writing, and the person who discloses the information, the person who receives the bottom, and the full-time safety officer must strictly perform the signing procedures;
5. The safety technology disclosure of each type of work is generally carried out at the same time as the safety technology disclosure of the sub-project project. For projects with complex construction technology, technical difficulty and dangerous operating conditions, the type of work can be disclosed separately.
Fourth, the basic project of safety technology disclosure of sub-projects.
1. Foundation engineering: including excavation engineering, backfill engineering, foundation pit support, etc.
2. Main engineering: including masonry engineering, formwork engineering, reinforcement engineering, concrete engineering, floor installation engineering, steel structure and iron parts production engineering, component hoisting engineering, etc.
3. Roofing engineering: including reinforced concrete roof construction, membrane roof construction, coating waterproof layer construction, tile roof construction, FRP roof construction, etc.
4. Decoration engineering: interior and exterior wall decoration, etc.
5. Door and window engineering: including wooden doors and windows, aluminum alloy doors and windows, plastic steel doors and windows, steel doors and windows engineering, etc.
6. Scaffolding works: including floor-mounted scaffolding, cantilever scaffolding, portal scaffolding, hanging basket scaffolding, and attached lifting scaffolding (integral lifting frame or climbing frame).
7. Temporary electrical works.
8. Vertical transportation machinery: including the disassembly and use of tower cranes, non-material hoists, external elevators, winches and other mechanical equipment.
9. Construction machinery and equipment: installation and use of woodworking, rebar, concrete, electrical welding and other machinery and equipment.
10. Plumbing and ventilation engineering.
11 Electrical installation engineering.
12. Fire prevention engineering: including electrical fire protection, carpentry shed (workshop) fire prevention, staff dormitory fire prevention and building materials fire prevention, etc.
13 Other works.