Geothermal pipes cannot be laid directly on the cement floor, and it is necessary to lay an insulation layer and reflective film on top of the cement, and then lay geothermal pipes.
Process: Floor heating laying process - leveling the ground.
Before the floor heating officially begins to be laid, the indoor ground should be cleaned to ensure the flatness of the ground and eliminate the unevenness and debris on the ground. Then, a site visit of the entire home is required to determine where the wall-hung boiler and manifold will be installed.
Underfloor heating laying process - installation of main water pipes.
The main water pipe of floor heating must use hot water pipe, PP-R or aluminum-plastic pipe can be used, and the pipe must be strictly installed in the design drawings, and the installation is straight and neat.
Underfloor heating laying process - installation of temperature control lines.
Make a groove where the manifold is installed, bury the temperature control wire, and place the relevant temperature control line around it for easy connection.
Floor heating laying process - laying insulation.
Lay the insulation layer on the flat ground, and when laying the insulation layer, be sure to cut the insulation board according to the actual size to ensure that the insulation board is cut neatly, and then lay. When laying, pay attention to maintaining the flatness of the insulation board, paste the joints of the board firmly with glue, and leave a gap for the pipeline.
Floor heating laying process - laying reflective film.
Paste it on the laid insulation board layer, be sure to keep the reflective film flat and tight, and there can be no wrinkles and misalignment, and the reflective film must be pasted with tape. After the reflective film is laid, the steel wire mesh needs to be laid on it, and the edges of the two fast steel wire mesh should be connected with special cable ties.
Floor heating laying process - laying floor heating pipes.
In strict accordance with the design drawings calibrated pipe spacing and direction of the laying of floor heating pipes, in the heat consumption of large areas to encrypt when laying, in the laying should keep the pipe straight, and with plastic nails in accordance with the drawings to fix the pipe on the insulation layer and reflective film. When the installation is interrupted or completed, the open part of the pipeline should be blocked at any time.
Underfloor heating laying process - installation of manifolds.
The assembled manifold is directly and firmly attached to the wall according to the position and elevation determined in advance according to the actual situation of the user's home, and is fixed with expansion bolts.
-
No, the bottom of the floor heating pipe should be laid with a benzene board of more than 2cm, and a layer of reflective film should be laid on the benzene board, and the anti-cracking steel wire mesh, fine gravel, etc., should be used to spread the floor heating pipe with cement mortar, and the floor tiles should be leveled or paved.
If it is a building, the upper and lower floors are underfloor heating, and even if there is no heating in the house, the temperature will be 20 degrees. But it's better to have your own.
-
Laying 10 cm of cement on top of the underfloor heating pipes may affect the thermal benefits of underfloor heating. Although cement is a good thermal insulation material, when it is very thick, it may reduce the heat transfer efficiency of floor heating, resulting in heat can not be transferred well to the room, affecting the heating effect of floor heating. Therefore, it is advisable to lay only a thin layer of cement on top of the underfloor heating pipes or use other flooring materials to pave them directly.
Will it be hot to lay 10 cm of cement on top of the floor heating pipe?
The floor heating pipe is paved with 10 cm cement Li Bei, which may affect the thermal efficiency of floor heating. Although cement is a good thermal insulation material, when it is very thick, it may reduce the heat transfer efficiency of floor heating, resulting in heat can not be transferred well to the room, affecting the heating effect of floor heating. Therefore, it is advisable to lay only one layer of trillage thin cement on top of the floor heating pipes or use other flooring materials to pave them directly.
Here are the related extensions, I hope you find it helpful! <>
In addition, if 10 cm of cement is laid, it is necessary to take into account the impact of the added weight on the structure. If the load-bearing capacity of the floor slab is insufficient, it may cause the floor to deform or create a safety hazard. Therefore, before laying cement, it is necessary to understand the load-bearing capacity of the floor slab, and find a professional to evaluate and design.
In addition, if cement is used to pave the floor heating pipe, it is also necessary to pay attention to moisture-proof and leakage-proof. Before laying floor heating pipes, it is necessary to do a good job of waterproofing and drainage to ensure that the ground is dry and water-free. Otherwise, water may accumulate under the cement, causing the floor heating pipes to be soaked, affecting the service life and safety.
In short, before paving cement, it is necessary to comprehensively consider the thermal benefits of floor heating pipes, the load-bearing capacity of floor slabs, waterproof and leak-proof factors to ensure the quality and safety of pavement. <>
Is it too thick, 14 cm from the insulation board to the floor tile? What about the impact on indoor temperature?
The total thickness from the insulation board to the floor tile is 14 cm, which may affect the indoor temperature. It is recommended to choose an appropriate amount of insulation board and floor thickness according to the local rental rotten ear climate and indoor temperature requirements. If the thickness of the thermal insulation plate and floor is too large, it may weaken the radiant effect of the underfloor heating, causing the indoor temperature to be uneven or take longer to reach the set temperature.
At the same time, the operation of the floor heating system should also be reasonably controlled to avoid overheating or downtime for too long, so as to achieve the best indoor temperature and energy efficiency. <>
-
Hello dear, lay 10 cm thick water reed mud above the floor heating pipe, because this will affect the heat transfer and reduce the effect of floor heating. The underfloor heating pipes are equipped with low-temperature radiation, and the heat needs to be directly radiated to the room through the insulation layer and the ground to achieve a comfortable temperature. If a thick cement is laid above the floor heating pipe, it will increase the heat loss and conduction thermal resistance, making the indoor heating speed slower and the thermal effect worse.
It is generally recommended that the thickness of the cement pour be controlled below 5 cm, and it is necessary to ensure that there is space around the underfloor heating pipes to ensure that the heat can be fully dissipated into the room. At the same time, it is also necessary to pay attention to laying insulation and waterproofing layers. If a thick layer of cement is required above the underfloor heating pipes, it needs to be professionally designed and calculated to ensure the proper operation of the underfloor heating system and the maintenance of the acorns.
-
Summary. Floor heating pipes are usually covered with barbed wire or cement.
1. On the floor heating pipe, laying barbed wire can play the role of reinforcing ribs, strengthen the strength of the backfill, and prevent cracking.
2. In addition, the same effect can also be achieved by adding anti-cracking agent to the cement backfill. Cement is alkaline and has a porous structure, absorbs water and breathes, and the barbed wire will rust for a long time. Therefore, the concrete reinforcement is usually cracked from the joint, and if it touches the heated and softened floor heating pipe, there will be unnecessary trouble, so it is not recommended to add barbed wire, there are many ways to achieve the same effect as barbed wire.
1. Lay benzene board or lint as insulation layer;
2. Tin foil as a reflective layer;
3. laying steel wire mesh;
4. Lay geothermal pipes and fix them with karting;
5. Backfill pebbles and concrete;
6. leveling; 7. Lay decorative layers such as tiles or wooden floors.
The above materials are benzene board, lint, tin foil, steel wire mesh, tile and wood flooring are selected according to the size of the aspect.
Can geotextiles be laid on geothermal pipes.
Your question has been received, it will take a little time to type, please wait a while, please don't end the consultation, you can also provide more effective information about Jian Kai, so that I can better answer for you.
Floor heating pipes are usually covered with barbed wire or cement. 1. On the floor heating pipe, laying barbed wire can play the role of reinforcing ribs, strengthen the strength of the backfill, and prevent cracking. 2. In addition, the same effect can also be achieved by adding anti-cracking agent to the cement backfill.
Cement is alkaline and has a porous structure, absorbs water and breathes, and the barbed wire will rust for a long time. Therefore, the concrete reinforcement is usually cracked from the joint, and if it touches the floor heating pipe that has been softened by the morning bucket heat, there will be unnecessary trouble, so it is not recommended to add barbed wire, there are many ways to achieve the same effect as barbed wire. So what materials are needed for the whole process of laying floor heating pipes?
The following is an explanation of the laying materials and components: 1. Lay benzene board or lint as an insulation layer; 2. Tin foil as a reflective layer; 3. laying steel wire mesh; 4. Lay geothermal pipes and fix them with karting; 5. Backfill goose finches and pebbles and concrete; 6. leveling; 7. Lay decorative layers such as tiles or wooden floors. The above materials are benzene board, lint, tin foil, steel wire mesh, tile and wood flooring are selected according to the size of the aspect.
If my answer is helpful to you, please give a thumbs up (comment in the lower left corner), look forward to your like, your efforts are very important to me, and your support is also the driving force for my progress. If you feel that I am satisfied with the answer of Fu Lu, you can click on my avatar for one-on-one consultation. Finally, I wish you good health and a good mood!
-
Hello dear! Glad to hear your question! Can the floor heating pipes be moved after the cement is paved
It can't not be affected, because when installing floor heating, he is not the time of winter heating delivery, at this time, the cement is paved, the tiles are paved, and when the heating comes, the cement has already solidified, so it will not affect the solidification of cement, the floor heating on the slope of the home is often paved when there is no heating, and the cement at this time has been completely solidified, so it will not affect the solidification of cement when the heating comes in winter.
-
Is it okay to lay floor tiles directly on the floor heating pipe, you are dear, I haven't done it so much, I'm afraid it is not possible, because the floor tiles may be cracked by the thermal expansion and contraction of the floor heating pipe, after all, there is not enough buffer space between the floor tiles and the floor heating pipe, in addition, the floor tiles do not have enough mortar to lay the base, and may not be able to resist the impact of people stepping on it. Hope it helps. If my answer is helpful to you, please give a thumbs up (evaluate it in the lower left gladiatorial fight), look forward to your like, your efforts are very important to me, and your support is also the driving force for my progress.
I wish you good health and a happy mood again!
-
<> No, you can't. At this time, there is no buffer space between the floor tiles directly laid on the floor heating pipe and the floor heating pipe, and the lead skin is easy to crack; On the other hand, there is not enough cement and mortar between the floor tiles and the floor heating pipe to make a base as a support, which is easy to crush the floor heating pipe, and the floor tile will collapse and be uneven. When laying floor tiles, it is first necessary to mix the mortar with dry sand and cement, and lay the floor heating pipes on the ground as a cushion.
Then the floor tiles are laid on the cushion, and the cushion plays a supporting role to prevent the floor tiles from sinking and blind lead.
To judge the number of circuits of the floor heating pipeline, it is necessary to consider the form of heating, which should be calculated: >>>More