-
Solution: For this project, it takes 24 days, 20 days, and 30 days for A, B, and C to do it separately.
Then A, B, and C complete 30 of the total works every day
Therefore, A, B, and C can work together to complete the total project in one day (1 24 + 1 20 + 1 30) = 1 8
Therefore, the joint completion of this project A, B, and C requires: 1 (1 8) = 8 (days).
In 8 days, A did 8 * 1 24 = 1 3 of the amount of work, so A's contract fee should be: 24000 * 1 3 = 8000 (yuan).
In 8 days, B did 8 * 1 20 = 2 5, so A's contract fee should be: 24000 * 2 5 = 9600 (yuan).
In 8 days, C has done 8 * 1 30 = 4 15, so A's contract fee should be: 24000 * 4 15 = 6400 (yuan).
Answer: The contracting fees of teams A, B and C are: 8,000 yuan, 9,600 yuan and 6,400 yuan.
-
Set A, B, and C to do x days each.
x(1/24+1/20+1/30)=1
x=8A: 8 1 24=1 3 24000 1 3=8000 yuan.
B: 8 1 20 = 2 5 24000 2 5 = 9600 yuan.
C: 8 1 30 = 4 15 24000 4 15 = 6400 yuan.
-
The work efficiency of A, B and C is 1 24, 1 20, 1 30, and the work efficiency of three-person cooperation is: 1 8
It takes 8 days for the three to work together.
The total project cost is 24,000 yuan.
A: 24000*1 24*8=8000
B: 24000*1 20*8=9600
C: 24000*1 30*8=6400
-
Time is certain, and the ratio of the amount of work completed by team A, B and C is the ratio of the work efficiency of team A, B and C.
Therefore, the ratio of the amount of work completed by team A, B and C = (1 24) :( 1 20) :(1 30) = 5:6:4
A24000*5 (5+6+4)=8000 yuan.
B 24000*6 (5+6+4)=9600 yuan.
C24000*4 (5+6+4)=6400 yuan.
-
Time = total amount of work Sum of efficacy.
5 (days) Congratulations: 5 days, 2, 3 4 (1 20 + 1 30 + 1 15) = 5 days, 2, time = total amount of work Efficacy and.
3 4 2 Zen Rough 20
5 (days) Answer: 5 days, 1, a project, A alone to do 20 days to complete, B alone to do 30 days to complete, C alone to do 15 days to complete, how many days can the three teams to complete the project 3 4?
-
After 5 days, A is left with 1-5 20=3 4
The remaining A, B and C cooperation still needs 3 4 (1 20 + 1 24 + 1 30) Kai bend = 6 days.
So when the finger is finished, A does all (5+6) 20=11 20 B does all 6 24=1 4
C does all 6 30 = 1 5
Therefore, A gets 6000 11 20 = 3300 yuan.
B gets 6000 1 4 = 1500 yuan.
C gets 6000 1 5 = 1200 yuan.
-
1/36+1/30=11/180
C is 1 48 per day, so let the number of days A and B work together is x, and the number of days C works is y x>=y
11 180*x+y 48=1 Then find the integer solution.
There is only one set of integer solutions, y=4 x=15. C. Number of days off = x-y = 11
-
Let B be x days, then C is x - 3 days.
14 40+(14-x) 30+(14-x+3) 24=1 multiplied by 120
42+4(14-x)+5(17-x)=12042+56-4x+85-5x=120
9x=183-120
9x=63x=7
-
Let B leave x days halfway, then C leaves x 3 days, A does 1 40 per day alone, B does 1 30 per day alone, C does 1 24 per day alone, A does 14 days, B does 14-x, and C does 14-(x-3)=17-x
1 40*14+1 30*(14-x)+1 24*(17-x)=1 multiplied by 120 on both sides
3*14+4*(14-x)+5*(17-x)=12042+56-4x+85-5x=120
4x-5x=120-42-56-85
9x=-63
x=7 so B leaves for 7 days.
-
Let B leave for x days.
A did it for 14 days, B for (14-x) days, and C for (17-x) days.
14/40+(14-x)/30+(17-x)/24=1x=7
-
Team A completes in 20 days, which means that Team A completes 1/20 in 1 day.
Team B completed in 30 days, indicating that Team B completed 30/1 in 1 day.
Team C completed in 40 days, indicating that Team C completed 1/40 in 1 day.
A and B cooperate, one day to complete 2/20 + 1/30 = 5/60 = 1/12. 1/12 a day, which means that it can be completed in 12 days.
A and C cooperation, one day to complete 20 + 1 40 = 3 40, that is, 3 out of 40 days can be completed. 40/3<15 is also available.
B and C are known as slow work, one day to complete one-30th + one-40th = 7/120, that is, 7-ths of the Qinghuai mold can be completed in 120 days. But 120/7 of a day is 15 days, so it can't be done in 15 days.
A, B and C cooperate, 13/120 can be completed in one day, that is, 120/13 can be completed, 120/13 < 15 days, so it can also be.
Therefore, the cooperation of A and B, the cooperation of A and C, and the cooperation of A, B and C can be completed in 15 days, but B can not cooperate with C.
-
As you can tell from the title.
The amount of A doing for two days = the amount for B doing four days.
A's velocity = 2 times B's velocity.
A does it for 10 days first, and B does it for 24 days, so A does it for 10 days, and then it can be completed after 12 days.
A alone can be completed in 22 days.
Because A's velocity = 2 times B's velocity.
then B alone can be completed in 44 days.
If my is helpful to you, please choose it as a satisfactory answer in time, thank you
-
Suppose A works alone and takes x days to complete, then A does 1 x of the project every day.
1-10/x)/24=(1-12/x )/20
x=22 (1-10 22) 24=1 44 1 1 44=44, so it takes 22 days for A to work alone, and 44 days for B to work alone.
-
A do. 12 10 2 (day).
B needs to do it. 24 20 4 (day).
A alone is required to complete the completion.
10 24 4 2 22 (days).
B alone does the completion of the need.
24 10 2 4 44 (day).
-
Let A and B do m days, and B does n days, then you can get the equation m 36 + m 30 + n 48 = 1, and after finishing it you can get 44m + 15n = 720, because m and n are integers, and 720 and 15n can be divisible by Zen cave 15, then 44m must be divisible by good brother 15 to ensure that mn is a positive integer, so friendly attack m must be a multiple of 15, and m 16, then m = 15, and n = 4.
-
Let C rest for x days, then according to the question (1+x 48) (1 30+1 36+1 48)=integer, from this equation can be calculated (x+48) 48 59 720=(x+48) 48 720 59, this equation in the fraction situation 48+x to 59 about the whole bucket of missing numbers, 48 and 720 divide to get the integer (15), but 59 is a prime number, so 48 + x must be a multiple of 59, so in line with the unprecedented debate of the topic there is only one answer x=11
-
1+x 48) (1 30+1 36+1 48) = integer, the result of this equation is (48+x) 48 720 59 = integer, in this equation 48 and 720 are approximately divided into 15 1, 48+x) to be divided with 59, since 59 is a prime number, so 48+x can only be a multiple of 59 to get the imitation only integer, closed.
As a result, only one x=11 was prepared
-
For a project, A completes it in 15 days alone, B does it in 20 days, and C does it alone in 30 days. If A and B cooperate, how many days can this project be completed?
1 (1 15 + 1 20) = 60 7 days.
If A and C cooperate, two-thirds of the project can be completed in a few days?
2 3 (1 15 + 1 30) = 20 3 daysAfter 5 days of cooperation between A and B, how many days does it take for the remaining C to do it alone?
1-(1 15+1 20) 5] 1 30=25 2 days.
-
solution, let the total workload be 1, then the work efficiency of A is 1 15, B is 1 20, and C is 1 30
Then 1 (1 15+1 20)=60 7
A, B and C completed a project together, completed all 1 5 in 3 days, and then A rested for 3 days, B rested for 2 days, and C did not rest, if A's workload in one day is 3 times that of C's workload in one day, and B's workload in one day is 4 times that of C's workload in one day, then how many days does this work be completed from the beginning? >>>More
If you look at it from a purely economic point of view, it is indeed a long-term investment, and this investment is very risky. Investment is your hard work, and the expected return is the joy that your children bring to you and support the elderly. >>>More
The blood routine examination mainly looks at: WBC, RBC, HGB, PLT test results, if these four values are within the normal range, there are no symptoms, and there is generally no problem.
According to household equipment, electrical appliances and furnishings, choose C TV. >>>More