  1. Anonymous users2024-02-07

    This problem needs to be multifaceted, considering that your plan will be sent to the expert review meeting for demonstration in the future, and the county will eventually help the owner get the approval as soon as possible, from this point of view, each chapter is important.

    The first chapter, a comprehensive explanation or preface, don't think that it is simple, whether it is well written or not, experts can see it at a glance, and there may not be a big problem, but the organization is not clear, the writing is not smooth, and the logic is unreasonable, which will leave a bad impression on the expert, and the score will be reduced.

    The second chapter, the basis for compilation, I believe you will write well, mainly the classification of judicial interpretations of regulations, document number format, whether they are effectively cited, whether they are up to date, etc.

    Chapter 3, Project Overview, most people will copy from the main design, then it depends on the level of the main design. But no matter what, it is also necessary to clearly describe the characteristics of the project layout, land occupation, process, process, and reversal that disturb the landform and cause soil erosion, otherwise you will not be able to seal the mouth of the expert.

    Chapter 4, Overview of the Demonstration Area, Write a wide range of easy to write, it is not easy to go down to the "Demonstration Area". It depends on the professional skills.

    Chapter 5, the evaluation of water conservation of the main project, is difficult and important, which directly tests whether you are familiar with the construction of this project and the impact on water conservation.

    Chapter 6, the scope of responsibility for prevention and control, is relatively simple and rarely goes wrong, but it should not be careless. It must be combined with the project approval documents, not too much, and not too little. However, the problem is often that there is little demarcation, because a certain area has "done a water conservation plan before", "soil erosion is slight, and the vegetation is good", which interferes with thinking and causes a lack of principles.

    The team leader will hold you back.

    Chapter 7, Churn**, Simple, Always Problematic, But Never Problematic. Matter.

    Chapter 8, the design of measures, is more important and more difficult. Your highest level is to be able to "adapt to local conditions".

    Chapter 9, Monitoring Design, is applied in an off-the-shelf format, and then attention is paid to the focus areas and time periods of the project.

    Chapter 10, general estimate, the workload is larger, do a good job of excel formulas, apply.

    Chapter 11, safeguards, simple, clichés, but find a good template.

    Chapter 12, Conclusions and Recommendations, Conclusions is a summary, and specific points to be made are suggested.

  2. Anonymous users2024-02-06

    Summary. If the ground area exceeds 20,000 square meters or the amount of ground moved exceeds 50,000 cubic meters, the land use right holder shall submit the "Soil and Water Conservation Program Report" to the municipal water affairs department. If the ground area is less than 20,000 square meters and the amount of ground is less than 50,000 cubic meters, the land use right holder shall submit the "Soil and Water Conservation Program Report Form" to the district water affairs department.

    If the groundbreaking area exceeds 20,000 square meters or the groundbreaking volume exceeds 50,000 cubic meters, the land use right holder shall submit the "Soil and Water Conservation Program Report" to the municipal water affairs department. If the ground area is less than 20,000 square meters and the amount of ground is less than 50,000 cubic meters, the land use right holder shall submit the "Soil and Water Conservation Program Report Form" to the district water affairs department.

    Hope mine can help you

  3. Anonymous users2024-02-05

    According to the latest Soil and Water Conservation Law of the People's Republic of China

    25th in mountainous areas, hilly areas, sandstormy areas and other areas prone to soil erosion as determined by the soil and water conservation plan to carry out production and construction projects that may cause soil erosion, production and construction units shall prepare soil and water conservation programs.

    Report to the people's water administrative departments at or above the county level for examination and approval, and in accordance with the approved soil and water conservation plan, take measures to prevent and control soil erosion. If there is no ability to prepare a soil and water conservation plan, it shall be entrusted to an institution with the corresponding technical conditions.

  4. Anonymous users2024-02-04

    Legal analysis: The water protection plan is generally made before the start of the project. The water protection plan is only done once, but if the feasibility study or initial design changes greatly, and if the project scale or site selection changes, it is necessary to re-submit the water protection plan for approval.

    Legal basis: Provisions on the Administration of the Preparation and Approval of the Preparation and Submission of the Soil and Water Conservation Program for the Development and Construction of the Soil and Water Conservation Project》 Article 5 The preparation and reporting of the soil and water conservation program shall be responsible for the development and construction units or individuals. The specific preparation of soil and water conservation programs of units and personnel, should have the corresponding technical ability and professional level, and by the relevant industry organization to implement management, specific management measures by the industry and the organization to formulate.

  5. Anonymous users2024-02-03

    The water conservation plan is generally done before the start of the project. Generally, the water protection plan is only done once, but if the feasibility study or initial design changes greatly, and if the project scale or site selection changes, the water protection plan needs to be re-approved.

    1. Change of EIA agency.

    The procedures for changing the EIA are as follows: 1. Make an application report to the competent environmental protection bureau, and the local ** seal is required; 2. A copy of the name approval notice of the industrial and commercial bureau; 3. Copy of real estate certificate and land certificate; 4. A copy of the lease agreement; 5. Find an EIA unit to do an EIA. If the construction unit fails to submit the environmental impact report or report form of the construction project for approval in accordance with the law, or fails to re-submit for approval or re-review the environmental impact report or report form in accordance with relevant laws and regulations, and starts construction without authorization, the competent department of ecology and environment at or above the county level shall order the construction to be stopped.

    2. What policies does Chengjiang County adopt in Yuxi to protect and govern Fuxian Lake?

    The people of Yuxi City have set up a management agency for Fuxian Lake to implement unified protection and management of Fuxian Lake, and perform the following main responsibilities:

    1) Publicize and implement relevant laws and regulations;

    2) Organize the preparation of the overall plan for the protection and development and utilization of Fuxian Lake, and formulate the annual dispatch plan for the water volume of Fuxian Lake, which shall be reviewed by the people of Yuxi City and implemented after approval by the provincial people;

    3) Formulate measures for the protection and management of Fuxian Lake, and implement them after being approved by the people of Yuxi City;

    4) Implement the annual water intake control plan, manage the Haikou control gate and the river control gate, implement the water intake permit system in the Fuxian Lake first-class protection area, issue water intake permits, and collect water resource fees;

    5) Formulate the fishery development plan and fishing control plan of Fuxian Lake, stipulate the fishing methods and net specifications, register and inspect fishing vessels, issue fishing licenses and fishing licenses, and levy fishery resource multiplication and protection fees;

    6) Issuing permits for non-motorized boats to enter the lake, and being responsible for water safety management;

    7) Organize scientific research on the protection, management, development and utilization of Fuxian Lake;

    8) Cooperate with the competent department of environmental protection to establish a water quality monitoring and early warning system for Fuxian Lake;

    9) Set up boundary tunghong piles and signs in the first-class protection area of Fuxian Lake;

    10) In the Fuxian Lake first-class protection area, the exercise of some administrative punishment rights of the departments of water and lead shed, environmental protection, fishery administration, water transport and maritime affairs, etc., the implementation plan shall be drawn up by the people of Yuxi City and submitted to the provincial people for approval.

    The Fuxian Lake Management Agency, which was established by the people of Yuxi City in Yanhu County, undertakes the specific work of the protection and management of Fuxian Lake in accordance with their respective responsibilities.

  6. Anonymous users2024-02-02

    Hello dear, happy to answer for you; What is the answer to the requirements for the preparation of the water protection plan; Feasibility study stage: According to the provisions of the "Regulations on the Preparation and Approval of Soil and Water Conservation Plans for Development and Construction Projects" and the feasibility study report of Dachang for construction projects, prepare the report of soil and water conservation plans. The soil and water conservation programme report should include the following main points; 1.

    The scope of responsibility of the construction project area and its surrounding environment. 2.Current status of soil erosion and soil and water conservation in the demonstration area.

    3.The amount of waste solids discharged in production and construction and the possible soil erosion and its hazards. 4.

    Soil erosion prevention and control primary selection program. 5.Soil and Water Conservation Investment Book Imitation Estimates.

    Preparation requirements for the preliminary design stage: According to the report of the soil and water conservation plan (feasibility study stage) approved by the water administrative department, the preliminary design of the soil erosion prevention and control project shall be carried out.

  7. Anonymous users2024-02-01

    1. What is a soil and water conservation program?

    In order to prevent soil erosion during the construction of the project, the state.

    The Ministry of Water Resources and the State Environmental Protection Administration have issued the "Measures for the Management of Soil and Water Conservation Programs for Development and Construction Projects", which is suitable for all development and construction units that may cause soil erosion.

    and individuals, soil and water conservation programmes must be prepared.

    1. For the approval system project, the feasibility study report is submitted.

    Complete the approval procedures for soil and water conservation plans;

    2. For approval-based projects, complete the approval procedures for soil and water conservation plans before submitting the project application report;

    3. For record-filing projects, the approval procedures for soil and water conservation plans shall be completed after going through the filing procedures and before the project starts.

    2. Determination of the category of soil and water conservation programs.

    The Soil and Water Conservation Programme is divided into a Soil and Water Conservation Programme Report Form and a Soil and Water Conservation Programme Report Form.

    1. Where the development and construction projects covering an area of more than 15 acres or the total amount of excavation and filling is more than 10,000 cubic meters, a report on the soil and water conservation plan shall be compiled;

    2. Other development and construction projects shall prepare and submit a report form for soil and water conservation programs.

    The content and format of the soil and water conservation program report and the soil and water conservation program report form shall comply with the technical specifications for the soil and water conservation program of development and construction projects and relevant provisions.

    3. Soil and water conservation program preparation units.

    The compilation and reporting of the soil and water conservation plan shall be the responsibility of the development and construction unit or individual. The specific preparation of soil and water conservation programs of units and personnel, should have the corresponding technical ability and professional level, and by the relevant industry organization implementation management, specific management measures by the industry organization.

    4. Review of soil and water conservation programs.

    Soil and water conservation programmes must be reviewed and approved by the competent water administration. Before the review and approval, it must be reviewed by the expert technical review meeting organized by the water administrative department, and after the expert technical review meeting, the water administrative department can issue the approval document of the soil and water conservation plan.

    5. Conditions for examination and approval of soil and water conservation program reports.

    1. Comply with relevant laws, regulations, rules and normative documents.

    Stipulate; 2. Comply with the technical specifications and standards of soil and water conservation of the country and industry such as the Technical Specifications for Soil and Water Conservation Programs of Development and Construction Projects;

    3. The scope of responsibility for soil erosion prevention and control is clear;

    4. The soil erosion prevention and control measures are reasonable and effective, coordinated with the surrounding environment, and reach the depth of the main engineering design;

    5. The basis for the preparation of soil and water conservation investment estimates is reliable, the methods are reasonable, and the results are correct;

    6. The content and methods of soil and water conservation monitoring are appropriate.

    6. Fees for soil and water conservation programs.

    In order to standardize the billing work such as the preparation and consultation of soil and water conservation programs for development and construction projects, and promote the healthy development of soil and water conservation work in development and construction projects, combined with the relevant provisions of the Regulations and Quotas for the Preparation of Estimates (Estimates) for Soil and Water Conservation Projects (No. 67 [2003] of the Ministry of Water Resources) and the Administrative Measures for the Acceptance of Soil and Water Conservation Facilities for Development and Construction Projects (Order No. 16 of the Ministry of Water Resources), the preparation of soil and water conservation programs, soil and water conservation supervision, and the preparation of soil and water conservation programs, soil and water conservation supervision, and soil and water conservation supervision of development and construction projects are Soil and water conservation facilities acceptance technical assessment report preparation and soil and water conservation technical documents technical documentation technical consulting services to provide guidance;

  8. Anonymous users2024-01-31

    According to the latest Soil and Water Conservation Law of the People's Republic of China

    Article 25 In mountainous areas, hilly areas, wind-blown sand areas and soil and water conservation regulations.

    The establishment of other areas identified as prone to soil erosion may result in soil and water.

    Lost production and construction projects, production and construction units.

    Soil and water conservation methods should be prepared.

    case, reported to the people's water administrative departments at or above the county level for examination and approval, and in accordance with the approval.

    Quasi-soil and water conservation programmes.

    Soil erosion prevention and control measures should be taken. There is no can.

    Efforts to prepare soil and water conservation programs, should be entrusted with the corresponding technical conditions of the agency. Weave.

  9. Anonymous users2024-01-30

    As long as the project is related to the groundbreaking, a water conservation plan must be prepared.

  10. Anonymous users2024-01-29

    The original Soil and Water Conservation Law, 1991-2011, derived from the ministerial regulations - Order No. 5 of the Ministry of Water Resources, stipulates that if the area of disturbed land is more than 1 hectare requisitioned for development and construction projects, a "Report on Soil and Water Conservation Plan" must be prepared; If it is less than 1 hectare, a report form shall be prepared.

    The new soil and water conservation law has not yet been implemented, and the new regulations derived from it have not yet come out, and it is rumored that the report will be adjusted to cover an area of more than 5 hectares.

  11. Anonymous users2024-01-28

    The application conditions say that fifteen years of work experience can be exempted from one course, right? As long as you meet the exemption conditions, it's OK, and you can have relevant supporting materials, which shouldn't be a problem.

  12. Anonymous users2024-01-27

    1. As long as the production and construction project involves the excavation of the earth, the soil and water conservation plan needs to be done.

    2. Determine whether to make a water protection report or a report form according to the earthwork book or floor area.

    3. Before the start of construction, it is necessary to get the approval of water protection. Generally, the brief inspection of the water protection party is only done once, but if there is a large change in the feasibility study and initial design, such as a change in the project scale, state order or site selection, then the water protection plan needs to be re-submitted for approval, and it needs to be redone.

Related questions
10 answers2024-04-17

The basic genres of writing can be divided into: poetry, prose, essays, and screenplays. Because I have read the works of many famous Chinese and foreign artists, I am interested in **. >>>More

13 answers2024-04-17

01 Go to bed early and wake up early to decompress yourself. >>>More

8 answers2024-04-17

Trust each other and operate together.

24 answers2024-04-17

What is the most important treasure in life? Some say wealth, fame, power, status, health, time, etc. If conditions allow, I don't think there are too many of the above. >>>More

3 answers2024-04-17

Writing is one of the most basic abilities, it can record what we want to say in the form of articles, and after artistic processing, the ideas expressed are richer and more interesting. >>>More