The difference between construction methods and construction technical schemes

Updated on society 2024-05-10
13 answers
  1. Anonymous users2024-02-10

    Construction organization design, this focus is on the organization, including the organizational structure of the project department, the basic construction technology, etc., it should be said that it is the overall and approximate general construction design.

    The construction plan is a construction method and method prepared for a certain division, sub-project, and even each process.

    The construction technical disclosure, to be more direct, is the technical disclosure to the construction team before the construction work begins, which is generally to inform the key points, difficulties and links that should be paid special attention to in the work.

    Hand typing, hope to help you, hope. Satisfied.

  2. Anonymous users2024-02-09

    Construction method refers to the method used in the construction of a building. Depending on the construction method, buildings can be divided into the following three types:

    1. Cast-in-place, masonry buildings.

    2. Prefabricated and prefabricated buildings.

    3. Part of cast-in-situ masonry, part of the prefabricated building.

    Construction plan. It is determined on a project-by-project basis, and some projects are simple and have a short duration that does not require the development of complex plans. Including organizational plan, personnel composition plan, and technical plan.

    In addition, according to the size of the project, there are on-site security plans, logistics support plans, etc.

  3. Anonymous users2024-02-08

    Construction method: It is to organize the construction method that will be used in the construction process to recommend a series of scientific methods.

    Construction plan: It is mainly to organize the entire construction process in the form of organization and management.

  4. Anonymous users2024-02-07

    Do the math how much it will cost you to renovate your home

    1. It is not the same, because the content introduced in the construction method is what method is used by the construction personnel to carry out each construction process, and the content introduced in the construction process is the fierce sale of a series of construction processes according to what construction sequence the construction personnel are, so it can be seen that the construction process contains the construction method, and the content of the construction process will be more comprehensive and detailed than the construction method.

    2. The construction process will make a specific specification of all the construction processes of the construction project, and the construction steps of each construction process and the matters of the notice and destruction will also be clearly marked, so that the construction project can be built more beautiful and smooth.

    3. In order to let the construction personnel know more clearly how to carry out the construction, the construction method is generally required to be handed over to the construction personnel, and the supervision and management personnel need to understand the construction process in detail, so that the supervision and management personnel can better arrange, manage and supervise each construction project, so as to ensure the construction efficiency and construction quality, and avoid delaying the construction period.

    4. When we carry out construction, we must coordinate each construction part with each other, and do an overall construction concept, and also need to develop a detailed construction step for each construction part.

    Enter the area and get the decoration for free**].

    Enter the area and get the decoration for free**].

  5. Anonymous users2024-02-06

    The construction process refers to the specific specifications of a certain project and the pipelines of those systems sold by the bureau. These processes are to make the project look more beautiful and smoother after completion. The construction method is to carry out ** with your friends before construction to see which method is more practical.

    These two types are in order in the acceptance stage, and the effect is not the same. Every construction site will have these two procedures, which is also a very important phenomenon. <>

    Not only are the two definitions different, but they also serve different roles. The role of the construction process is to influence each other between different systems and reduce some gaps. For example, when installing the line, the line will be connected very flat, and there will be no other differences.

    The construction method refers to what kind of method should be used to construct each house, and these things should be substantially investigated according to the actual situation. For different solutions, others give different definitions, so the role is naturally different. <>

    Engineering technology is a very important process, if there is no standardized construction and guide to the Tong Qi teasing guide is likely to be different. Everyone wants to be able to do their own work well, so it's important to do this guide. The construction method was also finally obtained after repeated trials, and it is not necessary to move if you want to.

    In the process of construction, we must control all aspects of conditions and behaviors, so as to ensure quality. <>

    In general, when constructing, I need to coordinate each part with each other and carry out an overall concept. If the scope of application is relatively large, it is definitely not possible to use the construction process, only the construction method. Construction workers are more knowledgeable about this aspect because they are often exposed to this type of thing.

    You must see what kind of process you want to do and whether it will have an impact on the whole.

  6. Anonymous users2024-02-05

    1. Define different side heads. The construction process is to do the specific specification of a certain project, such as the pipeline in the strong current system, the requirements: horizontal and vertical, the line should be along the edge of the corner.

    The construction process refers to the sequence of the main stages from the acceptance of the construction task to the delivery and acceptance. 2 is the role is different. For example, the weak current line needs to be separated from the weak current line by more than 30 cm, so as to avoid the interference of the weak current transmission cable by the strong electromagnetic field, resulting in the destruction of the front-end or back-end equipment function.

  7. Anonymous users2024-02-04

    It is not the same, the general construction method is based on the original drawings to complete the pure construction process or method, and then the first command method is optimized, the relevant specification system is manufactured, and a complete technology is formed, which is called the construction process.

  8. Anonymous users2024-02-03

    It is different, and the construction method has been determined before the decoration of the world. And it can't be changed. The construction process is generally changeable, and you can also choose according to your own interests.

  9. Anonymous users2024-02-02

    It's not the same; There are so many differences between different concepts, different standards, different service levels, different contents, and different writing formats.

  10. Anonymous users2024-02-01

    [Legal Analysis]: Engineering construction is to construct the project according to the requirements of the construction project design documents. Before the construction of the project, there must be a project construction plan. Includes:

    First, the type of project construction plan:

    1. Civilized construction plan; 2. Safety construction plan; 3. Formwork construction plan; 4. Scaffolding construction plan; 5. Construction plan of three treasures and four mouths; 6. Temporary electricity construction plan; 7. Construction plan for high-altitude work; 8. Tower crane installation and dismantling construction plan; 9. Multi-tower operation anti-collision construction plan; 10. Emergency plan; 11. Construction plan for winter rainy season; 12. Assessment and prevention measures for major hazards; 13. Construction organization design; 14. Building energy-saving scheme; 15. a hanging basket construction plan; 16. Tower crane hoisting scheme.

    Second, the content of the project construction plan:

    1. Preparation basis, principle 2, preparation scope 3, project overview 4, overall layout and construction period arrangement 5, construction technical scheme 6, construction period guarantee measures 7, quality objectives, guarantee system and guarantee measures 8, safety production objectives and guarantee measures 9, emergency rescue plan 10, seasonal, winter construction guarantee measures 11, environmental protection measures 12, civilized construction requirements 13, and Party A, supervision, design coordination.

    Legal basis]: Construction Law of the People's Republic of China

    Article 49 For decoration projects involving changes in the main body of the building and load-bearing structure, the construction unit shall entrust the original design unit or the design unit with corresponding qualifications to propose a design plan before construction; If there is no design plan, no construction shall be allowed.

    Article 52 The quality of survey, design and construction of construction projects must meet the requirements of the relevant national safety standards for construction projects, and the specific management measures shall be prescribed by the state.

    When the national standards for the safety of construction projects cannot meet the requirements of ensuring construction safety, they shall be revised in a timely manner.

    Article 53 The State shall implement a quality system certification system for units engaged in construction activities. Units engaged in construction activities may, in accordance with the principle of voluntariness, apply for quality system certification from the first-class product quality supervision and management department or the certification body recognized by the department authorized by the first-class product quality supervision and management department. If it is certified, the certification body will issue a quality system certification certificate.

    Article 54 The construction unit shall not, for any reason, require the architectural design unit or the construction enterprise to violate the laws, administrative regulations and construction project quality and safety standards in the course of engineering design or construction operations, and reduce the quality of the project.

    Architectural design units and construction enterprises shall refuse the construction unit's request to reduce the quality of the project in violation of the provisions of the preceding paragraph.

  11. Anonymous users2024-01-31

    The contents of the construction technical scheme are as follows:

    1. Basis and principle of preparation.

    2. Scope of preparation.

    3. Project overview.

    4. Overall layout and construction schedule.

    5. Construction technical scheme.

    6. Construction period guarantee measures.

    7. Quality objectives, assurance system and assurance measures.

    8. Safety production objectives and guarantee measures.

    9. Emergency rescue plan. Filial piety.

    10. Construction guarantee measures in summer and winter.

    11. Environmental protection measures.

    12. Civilized construction requirements.

    13. Coordination with Party A, supervision and design.

    Technical preparation for construction:

    1. Carefully study the construction drawings, understand the design intent, cooperate with the owner to draw the construction drawings, eliminate the problems of errors, omissions, bumps, and shortages, and solve the contradiction between the construction technology and the construction process.

    2. When compiling the construction organization design, it is necessary to take into account the comprehensiveness, highlight the key points of smart rent, and take the construction drawings, construction specifications, quality standards, and operating procedures as the guiding documents for organizing the construction.

    3. Calculate the engineering quantity of the sub-project, dredge the material channel, analyze the labor force and technical strength, establish the construction technology management organization, and organize the quality and safety system and construction plan. <>

  12. Anonymous users2024-01-30

    1. The relationship between the whole and the part.

    The construction technical scheme is the whole, the construction technical scheme is to design the whole project from the perspective of science and technology, and the construction scheme is partial, which is a part of the scheme designed from the practical application.

    2. The relationship between the guide and the mentored.

    The construction plan must be designed and arranged under the guidance of the construction technical plan, and must not violate the requirements of the construction technical plan, but only supplement and refine the implementation of the project.

    Third, the focus is different.

    The construction technical plan is the comprehensive design of the decision-maker for the whole project manpower, material resources, time, quality, cost and plan, and is the basis for the implementation and progress of the entire project. The implementer of the construction plan is only responsible for the refinement of a branch project.

  13. Anonymous users2024-01-29

    1. Basis and principle of preparation.

    2. Scope of preparation.

    3. Project overview.

    4. The overall layout and construction period are covered with acacia rows.

    5. Construction technical scheme.

    6. Construction period guarantee measures.

    7. Quality objectives, guarantee system and guarantee measures.

    8. Safety production objectives and guarantee measures.

    9. Emergency rescue plan slippery rules.

    10. Seasonal and winter construction guarantee measures.

    11. Environmental protection measures.

    12. Civilized construction requirements.

Related questions
3 answers2024-05-10

Abstract:Treating soft foundation with pine pile is a foundation treatment method that is easy to obtain, low cost and easy to construct. Pine piles are suitable for working in environments below the groundwater table, and are suitable for projects with shallow thickness of soft soil foundations. >>>More

5 answers2024-05-10

The connection and difference between the construction organization design and the construction plan: >>>More

7 answers2024-05-10

1) Organizational safeguard measures.

1. Mobilize a team with rich construction experience, and select excellent technicians and high-quality management personnel to participate in the construction. >>>More

2 answers2024-05-10

Before the bracket is erected, check the bowl buckle rod in advance, and shall not use digging, bending, corrosion, etc., as well as components with damage and obvious defects, and the bowl buckle or pin must use a special pin. Bowl fasteners must be inspected one by one before entering the site to see if they meet the quality requirements and design requirements. >>>More

3 answers2024-05-10

When it comes to the underwater pile foundation construction process, at this stage, what is the basic situation of the construction enterprises carrying out the construction of the water pile foundation? What is the basic overview? The following is the relevant content of Zhongda Consulting to sort out the relevant water pile foundation construction, and the basic situation is as follows: >>>More