What is the difference between the construction organization design and the construction plan?

Updated on society 2024-03-21
5 answers
  1. Anonymous users2024-02-07

    The connection and difference between the construction organization design and the construction plan:

    The construction organization design is the basic technical and economic document for the construction enterprise to guide the preparation and organization of a proposed project, and is a comprehensive planning arrangement made in terms of personnel, finance, materials, time, space, technology and organization for the construction preparation of the proposed project (single project or unit project) and the entire construction process; The construction plan is the analysis of a certain construction technology and construction method in the unit project or the division (sub-item) project, and the labor, materials, machinery costs and construction period consumed in the construction implementation process are selected through technical and economic analysis under the condition of reasonable organization, from which the feasible and optimal construction technology and method are selected. For some construction difficulties and key divisions and sub-projects, special construction plans are often prepared.

    The connection between the two (1) the relationship between the whole and the part: the construction organization design is the whole, and the construction plan is the part; The construction plan is an indispensable part of the construction organization design of the project, and the construction plan that is separated from the construction organization design has no guiding significance and cannot guide the construction. (2) The relationship between the guide and the coached:

    The preparation of the construction plan must be carried out under the overall planning and overall deployment of the construction organization design; The construction plan is always prepared and implemented under the guidance of the construction organization design.

    The difference between the two (1) the purpose of preparation is different: the construction organization design is the selection method of manpower and material resources in the construction, the careful arrangement of time and space layout, etc., and the construction plan is clarified according to the requirements of all aspects; The construction plan is to prepare a specific construction technology and method of a certain part to ensure the quality requirements and safe and civilized construction requirements. (2) The content of the preparation is different:

    The object of the construction organization design is the project as a whole. It involves all aspects of engineering construction, including the division of project institutions, the selection of construction plans, the construction sequence, the optimal allocation and the saving of various production factors, etc.; The object of the preparation of the construction plan is usually the division and sub-project. The content of the preparation includes the engineering concept, the key points in the construction, the selection of construction methods and specific construction methods, etc.

    3) The focus is different: the construction organization design focuses on the plan, and the construction plan focuses on the implementation.

  2. Anonymous users2024-02-06

    The construction organization design is the planning or preparation plan of the overall construction procedure, which can also be called the overall arrangement, including a series of descriptions such as project overview, construction period, preparation of machinery and equipment, personnel arrangement, specific construction details, safety measures, etc.;

    The construction plan only refers to the description of a single or multiple construction processes, steps and practices, and the two cannot be confused.

    1. In accordance with the construction contract (model text) (GF-2013-0201):

    Part II General Terms:

    The content of the construction organization design.

    1) Construction plan.

    2) Floor plan of the construction site.

    3) Construction schedule and guarantee measures.

    4) Labor & Materials** Program.

    5) Selection of construction machinery and equipment.

    6) Quality assurance system and measures.

    7) Safe production and civilized construction measures.

    8) Environmental protection and cost control measures.

    9) Other contents agreed by the parties to the contract.

    2. The construction plan is the implementation plan specified according to a construction project. It includes organizational plan (the composition of each functional organization, their respective responsibilities, mutual relationships, etc.), personnel composition plan (project leader, head of each agency, person in charge of each specialty, etc.), technical plan (schedule, key technical plan, major construction step plan, etc.), safety plan (overall safety requirements, construction risk factor analysis, safety measures, safety plan for major construction steps, etc.), material plan (material process, inspection process, temporary (urgent) material procurement process, etc.), In addition, according to the size of the project, there are on-site security programs, logistics support programs, and so on.

    The construction plan is determined according to the project, and some projects are simple and have a short construction period that does not require the development of complex plans.

  3. Anonymous users2024-02-05

    Summary. Hello! The differences between the construction plan and the construction organization design are as follows:

    1. The preparation of different purposes of the construction organization design is a strategic deployment of the project, and it is a programmatic document for the overall situation of the project. It is required to be scientific and instructive, highlighting the word "organization"; The construction plan is based on the construction organization design of a division, the construction method of the sub-project and the preparation of the specific construction technology, it will be the division and sub-project of the people, materials, machines and processes for detailed deployment, to ensure the quality requirements and safe and civilized construction requirements, should be feasible, pertinent, in line with the construction specifications, standards. 2. The object of the preparation of the construction organization design is the project as a whole, which can be a construction project or a unit project.

    3. Focus on different construction organization design, focus on decision-making, and emphasize overall planning; The construction plan focuses on implementation, pays attention to operability, emphasizes easy to understand, and is convenient for guiding local construction. 4. The starting point is different, and the construction organization design is a documented reflection of the will of the decision-maker from the perspective of the project decision-making level. It reflects more the principle of scheme determination, and how to determine the construction method through multi-scheme comparison.

    5. The preparation and approval are different.

    Hello! The difference between the construction plan and the construction organization design is as follows: 1. The construction organization design is a strategic deployment of a project and a programmatic document for the overall situation of the project.

    It is required to be scientific and instructive, highlighting the word "organization"; The construction plan is based on the construction organization design of a division, the construction method of the sub-project and the preparation of the construction technology with Kai jujube and body, it will be the division and sub-project of the man, material, machine and process for detailed deployment, to ensure the quality requirements and safety and civilized construction requirements, should be feasible, pertinent, in line with the construction specifications, standards. 2. The object of the preparation of the construction organization design is the project as a whole, which can be a construction project or a unit project. 3. Focus on different construction organization design, focus on decision-making, and emphasize overall planning; The construction plan focuses on implementation, pays attention to operability, emphasizes easy to understand, and is convenient for guiding local construction.

    4. The starting point is different, and the construction organization design is a documented reflection of the will of the decision-maker from the perspective of the project decision-making level. It reflects more the principle of scheme determination, and how to determine the construction method through multi-scheme comparison. 5. The preparation and approval are different.

    The general design of the construction organization and the construction organization design of the unit shall be presided over by the project manager, with the participation of the relevant departments of the project management department, and the technical person in charge of the project shall organize the relevant personnel to complete the preparation of its text; The construction organization design shall be submitted to the chief engineer at the next higher level or the professional and technical person in charge authorized by the chief engineer for approval. In principle, the construction plan of the sub-project shall be prepared by the project manager department and approved by the technical person in charge of the Qiao Zhaoye project; The construction plan of the key and difficult division (sub-item) shall be approved by the technical department of the enterprise; The construction organization design (construction plan) of the project undertaken by the professional company shall be approved by the person in charge of the professional company's technical awareness. Hello, the above is yes, you can refer to it, I hope it will help you I wish you a happy life! 

  4. Anonymous users2024-02-04

    Summary. Hello, the difference between construction organization design, construction organization plan, and construction organization plan: 1. The role is different.

    Construction organization design is the strategic deployment of a project, which is the executive management of the project manager; The scheme is a specific construction process prepared according to the construction organization design of the construction method of a sub-project.

    2. The focus is different.

    The construction organization design focuses on decision-making, and the plan focuses on implementation.

    3. The starting point is different.

    From the perspective of the project decision-making level, the construction organization design is a documented reflection of the will of the decision-maker.

    From the perspective of the project management, the plan is a refinement of the construction method, which reflects how to implement, how to ensure quality, and how to control safety.

    4. The compilation principles are different.

    The construction organization design can be based on the reasonable, feasible, safe, economical, advanced and other aspects as the basis for the preparation to ensure the accuracy, advancement, mass, seriousness and practicality of the construction organization design.

    5. The content of the compilation is different.

    The object of the construction organization design is the project as a whole, which can be a construction project or building group, or a unit project.

    What is the difference between construction organization design, construction organization plan, and construction organization plan?

    Hello, I am the special guest professional respondent of the change: Linda teacher <>

    I've seen your message and I'm sorting out the answers, and I'll reply to your <> within 3 to 5 minutes

    Hello, the difference between construction organization design, construction organization plan and construction organization plan: 1. Different roles Construction organization design is a strategic deployment of a project, and it is the project manager to implement the management; The scheme is a specific construction process prepared according to the construction organization design of the construction method of a sub-project. 2. The organizational design of the collapse construction focuses on decision-making, and the plan focuses on implementation.

    3. The starting point is different, and the construction organization design is a documented reflection of the will of the decision-maker from the perspective of the decision-making level of the Songji project; From the perspective of the project management, the plan is a refinement of the construction method, which reflects how to implement, how to ensure quality, and how to control safety. 4. The preparation principle of different construction organization design can be based on reasonable, feasible, safe, economical, advanced and other aspects to ensure the accuracy, advancement, mass, seriousness and practice of the construction organization design. 5. The object of the preparation of the construction organization design is the whole project, which can be a construction project or building group, or a unit project.

    I hope mine can help you and I wish you a happy life, thank you! <>

    You can also click on my ruined old man's avatar to pay attention to the slim rise. Feel free to contact us. <>

  5. Anonymous users2024-02-03

    Summary. Hello dear, happy to answer your <>

    What is the difference between construction organization design and construction plan is that 1. Different roles Construction organization design is a strategic deployment of a project, which is the implementation and management of the project manager; The scheme is a specific construction process prepared according to the construction organization design of the construction method of a sub-project. 2. Focus on different construction organization design, focus on decision-making, and focus on implementation of the plan. 3. The starting point is different, and the construction organization design is a documented reflection of the will of the decision-maker from the perspective of the project decision-making level; From the perspective of the project management, the plan is a refinement of the construction method, which reflects how to implement, how to ensure quality, and how to control safety.

    What is the difference between construction organization design and construction plan.

    Hello dear, happy to answer your <>

    What is the difference between construction organization design and construction plan is that 1. Different roles Construction organization design is a strategic deployment of a project, which is the implementation and management of the project manager; The scheme is a specific construction process prepared according to the construction organization hiking design and the construction method of a certain sub-project. 2. Focus on different construction organization design, focus on decision-making, and focus on implementation of the plan. 3. The starting point is different, and the construction organization design is a documented reflection of the will of the decision-maker from the perspective of the project decision-making level; From the perspective of the project management team, the plan is a detailed description of the construction method, which reflects how to implement, how to ensure quality, and how to control safety.

    What you need to be equipped with. 2) A leading group for the winter construction emergency plan should be established. 3) Carry out a winter construction inspection

    In the early stage of winter construction, members of the winter construction emergency and inspection team will collectively dispatch to conduct a major inspection of the project, including: a) the overwintering maintenance of sensitive slag under construction, slow construction and suspended construction projects. b) Winter insulation of temporary buildings, facilities and machinery for production and living.

    c) Implementation of construction specifications, procedures and measures. d) The availability of construction materials, machinery and facilities in winter. e) If the inspection does not meet the requirements, report to the relevant departments in a timely manner to solve it as soon as possible or issue the corresponding team to rectify it within a time limit.

    Penalties shall be imposed for those who cause accidents due to dereliction of duty. In addition, after each heavy snowfall, the work site and roads and bridges should be quietly cleaned first. The water leakage should be repaired in time.

Related questions
6 answers2024-03-21

It generally includes the following contents: engineering pay-off, earthwork excavation, concrete pouring, steel bar binding, formwork installation, brick wall masonry, steel (wood) structure manufacturing and installation, stone paving and other decoration, sketches and furniture placement; Terrain arrangement, seedling planting, etc.

3 answers2024-03-21

There is a forum for the University of Architecture Hall, so go find it.

1 answers2024-03-21

The basic way of flow construction.

First, wait for the rhythm of the flow of construction. >>>More

6 answers2024-03-21

The preparation procedure for the general design of the construction organization is as follows:1. Collect and be familiar with the relevant materials and drawings required for the general design of the construction organization, and investigate and study the characteristics and construction conditions of the project; >>>More

6 answers2024-03-21

If you have it in the books, find it yourself.