If there is a doubt during the operation, the operation should be stopped immediately and the sender

Updated on society 2024-05-13
10 answers
  1. Anonymous users2024-02-10

    During the operation, the operation should be stopped immediately if the guardian or the operator has doubts about the operation or finds abnormalities. It is not allowed to change the operation ticket without authorization, and it is not allowed to release the locking device at will, and it must be reported to the person in charge on duty or the dispatcher on duty immediately, and after the doubt or abnormality is cleared and eliminated, according to the situation, according to the following methods:

    1) If the doubt or abnormality is not a problem on or during the operation, and does not affect the safety of the system or other work, the operation can be continued with the permission of the person in charge of duty;

    2) If there is no error on the operation ticket, but other unsafe problems may occur, it should be executed according to the order of the person in charge of duty or the dispatcher on duty;

    3) If there is an error in the operation ticket itself, and the original ticket is stopped, the operation ticket should be filled in again according to the actual situation on site, and the operation should be carried out after review, simulation and other procedures;

    4) If an abnormality occurs due to improper operation or error, you should wait for the order of the person in charge of the shift or the dispatcher on duty.

  2. Anonymous users2024-02-09

    Right. If there is a doubt during the operation, the operation should be stopped immediately and the sender should be reported.

  3. Anonymous users2024-02-08

    Problems in operation:

    1.**It is not smooth, when ** reaches the key level, the long and short begin to compete, ** will be repeated up and down the key level, the second principle is to avoid ** repeatedly caused by one of the measures to constantly place orders and stop losses. But this doesn't completely solve the problem of key bit repetition.

    Because in the same cycle, the strength of a single root is always limited, even if a single root successfully breaks through and becomes a reality, there is no guarantee that the next ** will continue the direction of the previous one. This is what happened to me this morning:

    **When it's done, the support becomes a fact, go long. But the next ** will still break through the support and make the account lose money. After the current **breakout, the previous **effectiveness (support) decreases.

    Especially near the key level, this kind of repetition will happen many times, resulting in non-stop opening and closing positions, and consuming energy and money in vain. Therefore, a double cycle is introduced to solve the problem of key bit iteration.

    The greater the power of the **, the greater the possibility of a breakthrough becoming true. Find the key level of the 30min period, and then observe when the ** of 60min breaks through the key level of the 30min period. This method is equivalent to the treatment of overlapping ** in the entanglement theory, which can not only eliminate the meaningless **, but also increase the effectiveness of the processed **.

    This approach is to sacrifice flexibility to enhance effectiveness, as opposed to identifying key levels in large cycles and using small periods** to determine whether to break through. When the ** in the big cycle hits the key level of the big cycle, there is no doubt that the ** in the small cycle will continue to repeat at the key level of the big cycle, and this situation must not be opened in a hurry.

  4. Anonymous users2024-02-07

    When a question arises during the operation:

    1.The operation should be stopped immediately; And report to the on-duty dispatcher or the person in charge on duty, and then operate after clarifying the problem.

    2.It is not allowed to change the operation ticket without authorization.

    3.It is not allowed to release the locking device at will.

  5. Anonymous users2024-02-06

    When there is any doubt during the operation, the operation should be stopped immediately and reported to the dispatcher on duty or the person in charge of the mu on duty.

    Extended Materials

    1. Work safety

    Risk prevention: Stopping operations and reporting to superiors ensures that operations are not risked in case of doubt or uncertainty. This practice helps to prevent potential accidents and crashes and protects personal and property safety.

    Protect compliance: Timely reporting to superiors ensures operational compliance. If the operation in doubt or controversy is recognized and guided by the superior, it can avoid violating laws and regulations, policies or company rules and regulations, and ensure the legality and standardization of the work.

    2. Responsibility and efficiency

    Accountability: Timely reporting to superiors shows a sense of responsibility and initiative in the work. When a problem arises, reporting it to superiors in a timely manner can help hold them accountable and provide a strong basis for resolving them.

    Resource utilization efficiency: Stopping operations and reporting to superiors can avoid wasting resources. When there is a doubt, continuing to operate may lead to unnecessary loss of time, manpower and materials, and timely reporting to the superior can avoid this situation and improve work efficiency and resource utilization.

    3. Mutual assistance, cooperation and communication

    Collaboration and learning: Reporting to superiors in a timely manner can promote collaboration and learning among teams. When in doubt, by asking and reporting to your superiors, you can get guidance and help from their experience and knowledge, and improve your work skills and professional level.

    Two-way communication and feedback: Stopping operations and reporting to superiors is a positive way to communicate. This behavior helps to establish a good communication mechanism and feedback mechanism, so that each member of the team can keep abreast of the progress of the work and the problems encountered, and solve and improve together.

    In case of any doubt during operation, the operation should be stopped immediately and reported to the superior, in order to ensure the safety, responsibility and efficiency of the work. Stopping operations avoids potential risks and violations, and protects work and personal safety. Timely group key Hu can report to the superior can be proactive and responsible for the work, improve work efficiency and resource utilization efficiency.

    In addition, timely reporting can promote collaboration and learning among teams, and establish good communication and feedback mechanisms. Through the above measures, the smooth progress of the work can be ensured, and strong support and basis for problem solving can be provided.

  6. Anonymous users2024-02-05

    If there is any doubt in the operation, you can follow the correct steps to operate, and then correct the operation ticket to the vertical star.

    Power system operation ticket: the safety regulations for the operation of the reverse gate and the work of electrical equipment occupy an important position, and the organizational and technical measures for the operation of the reverse gate and ensure the safety are the core. The reverse operation stipulates the requirements and procedures of the attendant in the process of performing the operation in Yutan.

    Organizational measures to ensure security define the requirements and procedures during the execution of work tickets. The technical measures to ensure safety are the technical measures that must be taken to ensure the safe work of the staff on site, and these technical measures are completed by the personnel on duty through the reverse operation.

    Introduction to Operation Tickets:

    Operation ticket: refers to the written basis for electrical operation in the power system, including dispatching instruction ticket and substation operation ticket.

    The operation ticket is the main measure to prevent misoperation (mis-pulling, mis-closing, pulling with load, closing the isolation switch, closing with ground wire, etc.).

    The operation ticket must be filled out on the basis of an order or permit. There are two forms of orders: written orders and oral orders, and written orders are work tickets; Verbal orders can be given by the person in charge of electrical work to the personnel on duty, or they can be issued (recorded) in a ** manner.

    Must have a dual name (device name and number) and record at the same time; The operation unit shall carefully recite the order of the person in charge on duty, and after confirming that it is correct, record the accepted operation tasks and orders in the operation record; If there is a recording device but does not use it, and the consequences are caused, the assignee shall be responsible for the accident. Then what.

  7. Anonymous users2024-02-04

    Answer]: cThe deficit examined in this question is the safety operation procedure. Safety operation procedures are the procedures and precautions that employees must comply with in the process of operating machines, pin bridges, destroying equipment, adjusting instruments and meters, and other operations.

  8. Anonymous users2024-02-03

    1. Circuit breaker: cut off the circuit under conditions (such as: short circuit, overload, overvoltage, etc., of course, it can also be manual).

    2. Isolation switch: a switch with obvious visible disconnection and dull Li bright spots. (Purpose: To provide psychological comfort to electricians when overhauling the line).

    3. Load switch: It can be loaded with rated load to disconnect the closed circuit.

    4 Switches: On or Off.

    5. Knife switch: named after the shape, the mechanical structure is similar to the knife (the knife switch is mostly an isolation switch, and it can also be operated with a small load.)

    6. Disturbance sensitive ground switch: It should be a short-circuit protection specially set up for the overhaul of the rear section of the wide line (purpose, in case the line suddenly calls, to achieve the purpose of grounding short circuit and tripping. Generally, it is strictly forbidden to set up switches on PE lines.

    7. The sequence of power failure: first open and then the main gate, and isolate the current load. Electricity transmission is the opposite. First the main switch and then the switch, first the isolation switch and then the load switch.

  9. Anonymous users2024-02-02

    (1) The load current suddenly exceeds the specified value or the phase is confirmed to be out of phase operation;

    2) Sudden high temperature or smoke from the motor or switch;

    3) The motor or other equipment is rubbed due to loose parts, making noise or sparks;

    4) Serious failure of mechanical load or endangerment of electrical safety.

  10. Anonymous users2024-02-01

    For better use of electrical energy. Prevent electric shock accidents. Some safety measures must be taken:

    1. All kinds of electrical equipment. Longqi is a mobile electrical equipment. A system of regular and periodic inspections should be established.

    If a malfunction is found or it does not comply with the rules regarding remorse. It should be dealt with in a timely manner. 2. When using various electrical equipment.

    The operating system should be strictly observed. The three-pin plug should not be changed to a two-pin plug without authorization. Do not insert the wire head directly into the socket to use electricity.

    3. Try not to work with electricity. This is especially true in hazardous locations, such as where the workplace is cramped. There are conductors with a voltage of 250V or more around the working place.

    It is forbidden to work with electricity. If it is necessary to work with electricity. Necessary safety measures should be taken, such as standing on rubber felt or wearing insulated rubber boots.

    Other nearby conductors or grounding areas should be covered with rubber cloth. And it needs to be supervised by a special person and so on. 4. The external power plug of household appliances with metal shell generally uses a three-pin plug.

    One of them is a grounding wire. At present, most residential houses do not have protective grounding wires. Therefore, it is not possible to touch the ground wire.

    If a buried water pipe is used as a grounding body. It is necessary to ensure that the water pipes above ground have a good electrical connection. The middle must be in good contact.

    There can be no non-conductive joints such as plastic. It is also forbidden to use flammable and explosive gas pipelines such as gas pipelines as grounding bodies or grounding wires. In addition, it should be noted that the phase zero of the household appliance plug should be consistent with the phase zero line in the socket.

    The specified connection method of the socket is: look at the socket. The ground wire above.

    The center line on the left. The phase wire on the right. 5. Static electricity may cause harm.

    In severe cases, it can cause ** and fire. It can be as light as an electric shock. Cause the consequences of Yan Ya.

    To eliminate static electricity, the first step is to limit the generation or accumulation of electrostatic charges as much as possible. Method: Good grounding.

    to eliminate the accumulation of electrostatic verutotic charges. Increase the humidity of the air around the equipment to more than 70% relative humidity. Electrostatic charge escapes.

    Measures for neutralization with ionization. Install the discharge needle where the charge is most strongly formed. Neutralize the charge.

    Eliminate static electricity. We use a production process that prevents the generation of static electricity. Such as reducing friction.

    Prevent the liquid from shaking. Prevent dust from flying, etc. Substances with good conductivity are incorporated into low-conductivity substances.

    6. When conditions permit. Reliable leakage protectors are also available. 7. It is strictly forbidden to use the earth as a neutral line.

    That is, it is strictly forbidden to use three lines and one place. Two-line, one-place or one-line, one-place system.

Related questions
15 answers2024-05-13

I feel very shameless when I was beaten, and I hope to do something to save my face, right? That's a great idea! >>>More

9 answers2024-05-13

The Interpretation of Accounting Standards for Business Enterprises (2008) stipulates that the inventory of the surplus shall be recorded at its replacement cost, and shall be accounted for through the account of "property loss and excess to be disposed of", and the management expenses of the current period shall be written off after approval according to the management authority. ”

18 answers2024-05-13

After the conflict occurs in the relationship, it must be solved in time, and at this time, we must stand on the other party's position and think about the problem, and we must give the other party a step, so that the contradiction can be resolved.

16 answers2024-05-13

Brake failure during driving can be said to be the most terrifying accident, a little carelessness may lead to the tragedy of car crash and death, what to do if you encounter sudden brake failure? >>>More