If you do a simple decoration by Mao Peifang, the construction period should be tight, and it should be done in more than a month.
Give you a renovation process, and you can do the math yourself to see how far your project can go.
-
See what kind of house you are? What is the decoration like?
-
This needs to be done on a case-by-case basis.
-
Home decoration usually takes months, depending on the size of your home, and the complexity of the decoration, if you order more materials, the time may be longer, (it is recommended to order the materials to be ordered in advance, such as doors, cabinets, lamps, etc.).
-
In fact, how long the decoration depends on the area of the house, the arrangement of decoration personnel, etc., and there is no unified time, just take 100 square meters as an example
Under normal circumstances, the normal decoration of about 100 square meters, the construction period is 40-60 days, and the details should be followed by the on-site decoration project and engineering quantity;
1. First of all, hydropower and bricklayers, it takes 20 25 days, of which 1 2 days for demolition and renovation projects, 4 10 days for hydropower projects, 3 7 days for waterproof projects, about 10 days for bricklayers, and 1 day for the acceptance of concealed projects;
2. At the same time, the carpenter needs 15 to 20 days for the wood production of the frame, and it takes 5 to 10 days for the finish and closing;
3. After that, it takes 10 to 15 days for the oilman to enter the site, including wood for primer, wood for topcoat, wall scraping putty and latex paint;
4. It takes 4 to 6 days to install wooden doors, floors, cabinets, switches, sockets, lamps, sanitary ware and hardware at the end.
Among them, wooden doors, cabinets, and furniture are generally customized, and the production and transportation cycle is about 30 days, so it should be set in advance and the quantity is good, so as not to delay the later progress.
-
The fastest is about 3 months, after the decoration of the new house, first test the indoor formaldehyde content, if the formaldehyde exceeds the standard, you can choose some formaldehyde removal products appropriately, but do not be deceived by those dazzling advertisements on the market, the following are several commonly used methods to remove formaldehyde, you can refer to the reference, I hope to help you.
1.Open all doors and windows to promote air circulation, so that harmful gases can be discharged to the outside through the flow of air, which is simple and effective. However, this method should be used to maintain ventilation for a long time, and a large fan can also be used to enhance the wind and assist in ventilation.
In this cycle, forced ventilation for a month, the odor in the room will be greatly reduced. For some movable furniture, try to place vents so that odors can be discharged directly to the outside.
4.Plants such as green plants, aloe vera, cacti, pothos and other plants have a certain absorption capacity for formaldehyde, and can slowly consume the surrounding formaldehyde through photosynthesis. Because it is a plant, it is very safe and does not produce other harmful effects.
However, it should be noted that the absorption of formaldehyde by plants is limited and can only be used as one of the comprehensive treatment methods to remove formaldehyde.
5.The fresh air system is similar to the ventilation method of removing formaldehyde, but there is no need to open the window when in use, and the air delivered to the room is filtered, and it is also used when it exceeds the standard.
-
How soon can the house be renovated; The time to renovate a new house (about 100 square meters) also needs to be renovated, because the decoration time is determined according to the grade.
If it is simple and simple, it only needs to be completed in 25-30 days.
If it is a normal renovation, it generally takes 40-50 days.
If it is finely decorated, it generally takes 70-90 days to complete.
If it is a luxury renovation, it will take 100-120 days.
So it depends on what you decorate to decide whether it is time.
-
If the integrated panel decoration is used, it will be completed in 3-5 days.
-
Many owners will choose a renovation company to decorate the house after receiving the house. Many owners are anxious to move in, so they are more concerned about how long it will take to renovate their house. So how long does it take to renovate a house in general? Next, I will briefly introduce it to you.
1. Under normal circumstances, it takes about 45 days from the beginning to the end of the renovation of the house. House decoration is usually divided into three parts: early, middle and late. For example, in the early stage, the owner chooses the decoration company, and determines the decoration plan, it will take about 10-15 days, if the owner chooses the half-package mode, you also need to choose the main decoration materials during this time.
2. Next, the construction team will decorate the house. Often, it is the plumber and the wooden. Hydropower renovation generally takes about 4-7 days; It takes about 15 days for carpentry to make ceilings, cabinets and other products; After the renovation is completed, the bricklayer can start laying the tiles, and the tiling of the entire house will continue until the 30th day; After the carpentry is finished, the painter starts painting the walls, etc., which usually lasts about two or three days before the renovation is completed.
In the last two or three days, the decoration company will successively install hardware pendants, doors, sanitary ware and other products.
3. The time of house decoration is also related to the area of the house, the project of decoration rectification, and the style of decoration. If we decorate the house, or the structure of the house is more complex, such as a duplex house, it usually takes more than 3 months to decorate it. If we only partially rectify and decorate, the speed of construction is still relatively fast.
How long does it take to renovate the house, you can consult the decoration company or the construction team.
When choosing a decoration company, you can first consult the information such as how long it will take to complete the decoration, and you can indicate the method of postponement in the decoration contract.
-
About a month and a half:
7 days: The first step of decoration is generally to seal the balcony, when there is a need to seal the balcony, you need to seal the balcony first, only after the balcony is sealed can you pave the floor heating and tiles. When sealing the balcony, the time to make the window depends on the material you choose, the local processing is generally about a week, if it is a large profile, the time it generally takes is about a month and a half;
7 days: the next is to change the water and electricity, generally 89 square meters of the house to change the water and electricity can be done in 5 days, it takes time to groove in the wall, if there are more changes to the time, the time will be relatively longer. The time to lay floor heating is generally done in one day;
4-6 days: backfill floor heating 89 square houses can generally be backfilled in half a day, after backfilling, it is generally necessary to let the concrete completely condense, generally takes about 4-6 days, this depends on the temperature, the higher the temperature, the shorter the time required, the current season in the north generally takes about 4 days, the weather is too hot when the travel Zheng hand needs to be sprinkled in time to prevent concrete cracking;
5 days: After 6 days, the ground can be waterproofed after drying, it takes half a day to do waterproofing, it needs to be dried for 48 hours after it is done, and then it takes 48 hours to do the closed water test, and after 48 hours, the waterproofing will be successful when the downstairs does not leak;
7 days: tiling, the fastest cong banquet here for a month, the slowest two months can basically be tiled, 89 square houses generally need a week to paste, water pipes, tiles on the wall need to be paved for a long time, the speed of tiling the ground is very fast, at this time we must pay attention to whether the bricks that need to be cut are enough, when you need to ** in advance ** do not delay the master's time;
1 day: caulking is very fast, all caulking can be done in one day, if it is a beautiful sewing, it is necessary to clean all the sanitation before it can be done;
After pasting the bricks, the customized cabinet, the door can determine the size before entering the factory to place an order, so we must control the time of each step, so that we can dismantle the suspicion as smoothly as possible when decorating.
-
The length of time it takes to renovate a house is affected by many factors, and generally speaking, the renovation of an ordinary house generally takes three to six months.
1. Layout before decoration: Before the decoration, the decoration plan should be finalized, and the whole process will take more than ten days from the selection of the decoration company to the final confirmation, mainly in the preliminary preparations.
In this step, it is necessary to do a good job in the layout of decoration materials and water and electricity, so as to facilitate the later decoration.
2. Arrangement during the decoration period: In the later stage of decoration, it is mainly construction, such as water and electricity, such as carpentry, such as decoration, which takes a week, and the carpenter has to do the ceiling, background wall, and even the wardrobe on site, according to the progress, it generally takes half a month. After the completion of the hydropower project, the bricklayers began to lay the floor tiles, first the kitchen and bathroom, then the common areas, a process that took more than half a month; After the carpentry is done, the workers will enter the construction site to putty and paint the walls, and the whole project will take about 30 to 50 days.
During this time, owners can go to the mall to buy their favorite furniture and get ready to enter the interior.
3. Later layout of decoration: after the completion of the building, only the installation is required, curtain rods, hardware accessories, etc.; In addition, doors, cabinets, furniture, etc. will also be carried out one after another; Coupled with the soft decoration at home, some simple design drawings can be done in one day and completed in seven to ten days.
During this time, the owners can check to see if there is any furniture and what is wrong, and when the renovation is completed, everything will be perfect.
If you want to shorten the construction period and move in early, you must plan in advance, arrange the progress of the entire project, step by step, and then send the materials to the construction site, one link after another, to ensure the quality and quality of the project.
A few suggestions on shortening the construction period: 1. Decoration is a very complex process, and each link should be reasonably used, such as when decorating the pipeline, it is necessary to inform the next staff in advance, so that they can enter the room in these days, so as to better decorate.
2. When renovating hydropower and electricity, it is necessary to inform the tiling workers in advance, and prepare tiles and other materials in advance. Otherwise, the materials will not arrive, so you will have to wait.
3. Hydropower renovation is a very troublesome work, especially if you are not satisfied with the existing house structure, you need to redesign, and there are too many hydropower transformations, which will delay time.
4. The protection of the finished product is also very important, after completion, it is necessary to protect the finished product, such as furniture, do not damage the wall, otherwise it will be redecorated and the construction period will be delayed!
5. In order to shorten the decoration cycle, another very important requirement is not to demolish the decoration plan of the house over and over again, and to implement it in accordance with the original design drawings, otherwise it will affect the progress and cause the employees to be unable to arrive on time.
The above is the relevant content of how long it takes to stop the mu for house decoration, I believe everyone has an understanding of these contents, and I hope to bring you some help.
-
Half a month like this!
Many decoration owners will ask when they go to the decoration company to do decoration, "I don't know how long your decoration company will help me decorate the house" In fact, for such a question, the decoration company is impossible to give a true time, and will give an approximate vague time, such as about three months and so on, but can it really be completed within three months in the decoration? In fact, there are still many factors that will affect how much time it takes to decorate a new house, so let's analyze how much time it takes to decorate in a new house.
When the front process is almost carried out, you can start the installation process of household appliances, and the installation time takes about a week, after all, there are many household appliances at home that need to be installed, such as air conditioners, range hoods, stoves and lamps and lanterns, because there are more things to be installed, so the installation time will be longer, and when installing, you also need to pay attention to harmony and comfort, so when installing, It has to be done step by step, and in the process of installation, you also have to pay attention to whether some tools that are often used are blocked, such as whether the position of the gas valve will be blocked when installing the stove.
-
1. It generally takes 80 days to renovate a house.
2. Because it is necessary to prepare the decoration design and materials in advance before the house decoration, the time of the construction stage is relatively long, usually one and a half months.
3. In addition, there are some finishing touches in the later stage, so the decoration is estimated to be 80 days.
It will take years to improve academic qualifications and obtain certificates at the earliest. >>>More
1.The black bow must be able to make money. Level 10 Arrow Rain must be placed at the back of the small tower (from your own side) and after the first mob (archer) in front of the dragon farm comes out. >>>More
The shortest time I've ever seen from marriage to divorce is five months. >>>More
Patenting process.
The procedure for applying for a patent is simple, and you only need to apply once to know it. First of all, from the national intellectual property online **patent application** and the version of the patent document (description, claims, abstract of the specification, request for fee reduction, request), fill in the ** and write the patent application documents can be applied to the patent office. If you know how to write patent documents, you can write documents by yourself and file a patent application with the patent office; Inventors who are not sure about writing documents and do not know how to apply for a patent can entrust a patent ** agency to apply for a patent. >>>More
Aries is an adventurous sign, and sometimes love is not necessarily about pursuing a good ending, and such a love will make him or her forget it very quickly. Of course, the love that he (her) puts into him (her) will also hurt him (her). But he or she won't be knocked out because of this. >>>More