What are the time control points when bidding for projects? How to master?

Updated on Financial 2024-05-10
4 answers
  1. Anonymous users2024-02-10

    Bid opening time: The time of public bidding mentioned in the bidding document is generally shortly after the official bid closing, and the bidding of each bidding manufacturer is read out and a ** ranking is carried out, so that the bidders can understand their own situation and avoid black box operation. Tender validity:

    The validity period of the bidder's bid plan and ** is generally 90 days, which is left to the user to evaluate the bid, contract negotiation and contract execution, and within this validity period, the bidder's plan and ** must be guaranteed to be cashable.

    Validity period of bid bond: The validity period of bid bond is generally required to be within 20 days after the deadline for bidding.

  2. Anonymous users2024-02-09

    The bidding control price is the highest price limit announced in advance. The bid price will not be higher than it. The bottom of the bid is sealed and announced after the opening of the bid. It is not the maximum limit price. The bid price, the winning bid price, are likely to break through it.

    The bidding control price only plays the role of the highest price limit, and the bidder's ** should be lower than the price, and the bidding control price does not participate in the scoring, nor does it occupy the weight in the bid evaluation, just as a reference to the cost of specific construction projects. The bottom of the bid generally participates in the evaluation process of the bid evaluation, that is, the composite bid bottom A + B mode, occupies the weight in the bid evaluation process, so the bottom of the bid can affect which bidder wins the bid.

    When evaluating the bid, the bid shall not exceed the bidding control price, otherwise the bid will be scrapped. The bottom of the bid is the winning price expected by the bidder, and the closer the bid is to this, the easier it is to win the bid. When all the bids are too low or too high enough to be lower, the employer can announce that the bid is not responsible for the failure of the bid, but the situation that is too low is almost impossible in the project.

  3. Anonymous users2024-02-08

    If you bid, as long as you don't miss the time to bid, then look at the scoring criteria of the bid, and the bidding documents are the most important.

  4. Anonymous users2024-02-07

    <> there will be a lot of time points involved in the bidding and bidding activities, and these time points will better protect the principles of openness, fairness and justice in the bidding activities. Therefore, if a company wants to participate in the bidding for travel, it must first keep these times in mind.

    Each bidding project has to go through the process of bidding, bid evaluation, and bid opening, and each process has its corresponding time node, the most common time number is 20th, 15th, 10th, 5th, 3rd, 2nd, etc., today I will take you to sort it out.

    First, the bidding process.

    1. Prequalification documents: 5th, 2nd, 3rd, 3rd.

    2. Bidding documents: 5th, 10th, 3rd, 15th, 20th.

    2. Bidding. 1. The validity period of the bid shall be calculated from the date of submission of the tender documents.

    2. The validity period of the bid bond shall be consistent with the validity period of the bid.

    Third, open the bid evaluation.

    The bid opening time is the same time as the tender deadline.

    4. Winning the bid: 1) The winning candidate: the bid evaluation report will be publicized within 3 days, and the publicity period will be 3 days.

    2) Determine the winning bidder within 15 days to report to the supervision department.

    Signing: within 30 days of determining the winning bidder; The deposit + interest will be refunded within 5 days of signing the contract.

    The tenderer shall, at the latest, within 5 days after the signing of the contract with the town of spike noodles, return the bid deposit and bank deposit interest to the winning bidder and the unsuccessful bidder.

    5. Complaints and Handling.

    10 days of knowing or ought to have known;

    Decision on whether to accept the complaint: 3 working days.

    Written decision: 30 working days.

    Master the time node of each process and do the right thing at the right time, so that you can get twice the result with half the effort. Here's wishing you all the best of luck.

Related questions
9 answers2024-05-10

First, calculate the engineering quantity.

If the bill of quantities is provided in the project bidding documents, the engineering quantity should be checked before the bidding ** calculation. If the bill of quantities is not provided in the tender documents, the entire quantity must be calculated according to the drawings and summarized into a list of works. >>>More

8 answers2024-05-10

A proposed project is a project that wants to be built, or is in the process of being conceived. >>>More

11 answers2024-05-10

According to the provisions of the bidding law, it will take at least more than 20 days, but it is generally not compliant, and basically the general project is about 2 weeks.