Urgent need for the calculation formula of the wall, column, roof, etc. of the foundation in the pro

Updated on educate 2024-05-13
5 answers
  1. Anonymous users2024-02-10

    The general formula for calculating the engineering quantity of concrete strip foundation is:

    v=l×s (4-12)

    where v is the volume of the strip foundation (m3).

    l - strip foundation length (m), the outer wall is calculated according to the length of the center line, and the inner wall is calculated according to the net length of the foundation.

    s - strip foundation section area (m2).

    If the interior and exterior walls have a beam-type ribbon foundation, the T-joint part of its junction (the volume of the figure is calculated as follows:

    v = v1+v2

    v1=l with b h1

    v2= l h2 (2b+b) 6 (4-13).

    In the formula, V lap - T-joint lap volume (m3).

    v1 - (b) The lap volume of the H1 section in the figure (m3).

    v2 - (b) The lap volume of the H2 section in the figure (m3).

    If the interior and exterior walls are beamless belt foundations, v build = v2.

    Cast-in-place columns are reinforced concrete columns that are on-site formwork and poured in situ, such as frame columns and structural columns. The engineering quantity is calculated in cubic meters according to the cross-sectional size multiplied by the column height shown in the figure.

    Column sections are calculated according to the plane geometry of the size shown, and the common geometric sections are rectangular, circular, circular (hollow column) and I-shaped.

    Wherein, because the cross-sectional area of the structural column is calculated by the formula.

    Structural column cross-sectional area = d1d2+ (4-14).

    where d1 and d2 are the dimensions of the two directions of the structural column.

    n1, n2 - the number of edges snapped in the direction of d1 and d2.

    The height of the column shall be determined according to the following provisions:

    Cast-in-place concrete beams.

    Cast-in-place beams include foundation beams, general beams and ring beams. The engineering quantity is calculated by multiplying the section size shown in the figure by the beam length in cubic meters.

    The length of the beam shall be determined according to the following provisions:

    When the beam is handed over to the column, the beam length should be calculated according to the net distance between the columns;

    When the main beam is connected with the secondary beam, the length of the secondary beam is calculated to the side of the main beam. The volume of the beam head and beam pad extending into the wall is combined into the beam volume for calculation.

    In short, the length of a beam with a small cross-section is calculated to the side of a beam with a large cross-section.

    5) Cast-in-place concrete slab.

    The structural form of cast-in-place concrete slab can be divided into beam slab, beamless slab, slab, arch slab, etc. The engineering quantity is calculated by multiplying the area shown in the figure by the plate thickness in cubic meters.

    Cast-in-place slabsBeamed plate refers to a plate with beams, and the engineering quantity is calculated according to the sum of the volumes of beams and plates.

    The beamless plate refers to the plate without beams and directly supported by the column head, and its volume is calculated according to the sum of the volume of the plate and the column cap.

    Slab refers to a slab without columns and beams, and is directly rested on the load-bearing wall on all sides, and its engineering quantity is calculated according to the solid volume of the slab. When there are multiple types of plate connections, they should be divided by the center line of the wall, and the plate head protruding into the wall should be merged into the plate for calculation.

    When the cast-in-place eaves gutter is connected with the slab (including the roof panel and the floor slab), the outer wall is the dividing line, and when it is connected with the ring beam (including other beams), the outer edge line of the beam is the dividing line. Outside the edge of the exterior wall or outside the outer edge of the beam is the eaves gutter.

    If the concrete slab is poured composite high-strength thin hollow pipe, the engineering quantity should be deducted from the volume occupied by the pipe, and the composite high-strength thin hollow pipe should be included in the **. Lightweight materials are used to pour in the beamed slabs, and the lightweight materials should be included in the **.

  2. Anonymous users2024-02-09

    Wall columns. Plastering: Plastering is calculated according to the structural surface shown in the design drawing.

    Wall plastering and wall joints are calculated by area according to the size shown in the design drawing. Deducting the area of wall skirts, door and window openings and holes other than a single one, excluding the area of baseboards, mirror lines and the junction of walls and components, the side walls and top surfaces of door and window openings and holes are not increased. The side walls of attached wall columns, beams, buttresses and chimneys are incorporated into the corresponding wall area for calculation.

    1.The plastering area of the exterior wall is calculated according to the vertical projection area of the exterior wall.

    2.The area of plastering of the façade skirt is calculated by multiplying its length by its height.

    3.The plastering area of the interior wall is calculated by multiplying the net length between the main walls by the height.

    1) If there is no wall skirt, the height is calculated from the ground of the indoor building to the bottom of the ceiling;

    2) If there is a wall skirt, the height is calculated from the top of the wall skirt to the bottom of the ceiling;

    3) If there is a suspended ceiling, its height shall be calculated according to the indoor ground or floor to the ceiling plus 100mm.

    4.The plastered surface of the interior wall skirt is calculated by multiplying the net length of the interior wall by the height.

    Independent cylinder plastering, according to the size shown in the design drawing, the perimeter of the column section multiplied by the height and the area is calculated.

    The plastering of the independent beam surface is calculated by multiplying the perimeter of the beam section by the length according to the size shown in the design drawing.

    The joints of independent columns and chimneys on the house are calculated by area according to the size shown in the design drawing.

    The plastering of railings and railings (including columns) shall be calculated according to the vertical projection area of their plastering.

    Plastering of sporadic projects, calculated in area according to the dimensions shown in the design drawing.

    Decorative plastering grids, caulking is calculated according to the decorative plastering area.

    Block surface layer: The block surface layer is calculated according to the exterior finish shown in the design drawing.

    The wall and skirt inlay blocks are calculated by area according to the size shown in the design drawing.

    Cylindrical inlay blocks are calculated in terms of area according to the dimensions shown in the design drawing.

    The beam surface is covered with blocks, calculated by area according to the size shown in the design drawing.

    Sporadic inlay blocks, calculated by area according to the dimensions shown in the design drawing.

    Hanging stickers, dry hanging block materials, according to the size of the design diagram to calculate the area.

    Sporadic decorative block inlays, calculated by area according to the dimensions shown in the design drawing.

    The finished stone cylindrical waist line, yin angle line, column cap, column pier, according to the outer surface of the brigade size to extend the meter.

    Dry-hung stone steel skeleton, calculated by mass according to the size shown in the design drawing.

    Wood decoration and other keels and base layers are calculated according to the size and area shown in the design drawing, deducting the area occupied by the openings of doors and windows and the holes above.

    Wall finishes are calculated by multiplying the net length of the wall by the clear height shown in the design diagram and the area. Deduction of the area occupied by door and window openings and more than one hole.

    Column (beam) finish, calculated by area according to the outer dimensions of the finish shown in the design drawing. The column cap and column pier are incorporated into the corresponding column finishing engineering quantity.

    The partition is calculated by area according to the outer dimensions of the frame shown in the diagram. deduct the area occupied by more than one hole; If the material of the bathroom door is the same as the partition, the area of the door is incorporated into the partition area.

    1.The stainless steel frame of the partition is calculated by the area of the frame.

    2.If there are reinforcing ribs in the all-glass partition, the engineering quantity of the ribbed glass will be incorporated into the partition.

  3. Anonymous users2024-02-08

    1. The plastering area of the wall and skirt shall be calculated according to the design size, and the area occupied by the door and window openings and the above holes shall be deducted, and the area of the baseboard, hanging mirror line and the junction between the wall and the component shall not be deducted, and the side wall and top surface of the door and window openings and holes shall not be increased. Attached wall columns, beams, buttresses, flues and other side walls and calculated within the corresponding wall area. Interior wall plastering has a suspended ceiling but not to the top, the height is calculated to the bottom surface of the ceiling plus 15cm

    2. The parapet wall (including flooding, brick picking) and the plastering on the inside of the railing (the area occupied by the lattice hole within the deduction) are calculated according to the projection area multiplied by the coefficient, and the parapet with the top pressure multiplied by the coefficient.

    3. The plastering area of balconies, awnings and horizontal sunshades shall be calculated according to the horizontal projection area, and the plastering length of the gutters and decorative lines shall be calculated according to the length of the center line of the eaves and decorative lines.

    4. The cylinder plastering is calculated by multiplying the perimeter of the column section by the height according to the size shown in the design drawing. Sporadic plastering is calculated in terms of area according to the dimensions shown in the design drawing.

    5. The wall, column and beam surface inlay block material is calculated according to the size shown in the design diagram and the actual paving area. Attached wall columns, beams and other side walls are incorporated into the corresponding wall area for calculation.

    The keel is hung on the stone surface layer, the base and the surface layer are set of quotas, and the skeleton engineering quantity of the base layer is calculated according to the weight of the corresponding quota.

    6. The area of the base and surface layer of the wall finish is calculated according to the net length of the size shown in the design diagram multiplied by the net height, deducting the area occupied by the door and window openings and each of the above holes; The quantity of the additional layer is calculated according to the corresponding increase part.

    7. The finishing area of the column and beam is calculated according to the peripheral finishing area shown in the figure.

    8. The engineering quantity of plastering, inlay blocks and finishes of column piers and column piers (except marble, granite column piers and column caps) is incorporated into the corresponding columns for calculation, and each column pier and column cap is added to the labor: plastering increases man-days: inlay blocks increase man-days; Finishes increase man-days.

    9. The partition is calculated according to the size shown in the design drawing and the area occupied by the outer area of the frame, deducting the opening of the door and window and the area occupied by each of the above holes. If the material of the bath side door is the same as the partition, the area of the door is incorporated into the partition area.

    10. The surface layer and base layer of the curtain wall are listed separately, and the area of the curtain wall is calculated according to the size shown in the design diagram with the peripheral area, and the base layer is calculated by weight. The ribbed part of the all-glass curtain wall is incorporated into the curtain wall area for calculation.

  4. Anonymous users2024-02-07

    3. Schematic diagram of all a project a) Floor plan b) 1-1 Section drawing KJ-I: column 400 mm 400 mm, beam 400 600 mm [solution] (1) Quota engineering quantity:

    Exterior wall volume: v outside = (net length between frames net height between frames - area of doors and windows) wall thickness = (

    Apply the base quota 4-11.

    Interior wall volume: V inside = (net length between frames, net height between frames - area of doors and windows) wall thickness =

    Apply the base quota 4-11.

    2) The calculation method of the list quantity is the same as the fixed quantity quantity. The calculation of the quantity of the list is shown in the table.

    Table List Quantity Calculation Table.

    Serial number item code.

    The name of the project. Description of the characteristics of the project.

    Unit of measure. Quantity 1

    Solid brick walls. Exterior wall, wall thickness 365mm, wall height.

    m359 . 74

    Solid brick walls. Exterior wall, wall thickness 365mm, wall height.

    m327 . 04

  5. Anonymous users2024-02-06

    The net length of the interior wall is multiplied by the wall floor height multiplied by the wall thickness, and the exterior wall is multiplied by the wall height multiplied by the wall thickness according to the center line, and the area of doors and windows and openings larger than the square is multiplied by the wall thickness!

Related questions
10 answers2024-05-13

If you meet this application condition, you can.

A) all citizens of the People's Republic of China, law-abiding and have one of the following conditions, can apply for the cost engineer qualification examination: >>>More

3 answers2024-05-13

Cost Engineer I.

It refers to the professional and technical personnel who have passed the national unified examination, obtained the "Cost Engineer Qualification Certificate" and have been registered, and are engaged in cost business activities in construction projects. Cost engineer refers to the engineering economic professionals who are qualified by the state and licensed to practice after registration, and who are specifically designated, entrusted or hired by a department or a unit, and are responsible for and assist in the valuation, pricing and management of project costs, so as to safeguard their legitimate rights and interests. The state implements the cost engineer qualification system in the field of engineering cost. >>>More

10 answers2024-05-13

If you research, cheat, all kinds of cheating. Khan, not for the research, it is recommended to do a few years of construction staff and then come, you have done 5 years of construction cost is not as good as 2 years of construction back to do 3 years of cost, the master is mixed out of construction, or the site and the construction site of the cost staff, first learn to understand the drawings, CAD ah to be proficient, and then start to read, the basic knowledge has been seen, to cope with the exam, the pricing is carefully watched, and the quota should be seen carefully, to see the level of knowing so-and-so on such and such a page, and then it is practical, It is difficult for you to imagine if you have not done the construction site, such as the difference between the dry hanging keel and the curtain wall keel, even if you look at it, it is estimated that it is difficult to understand. The 16+4 in the quota plastering makes you unable to understand the meaning, or you can't notice the word at all. >>>More

8 answers2024-05-13

The difference between list pricing and fixed pricing.

1. The pricing basis is different. >>>More

14 answers2024-05-13

Let me tell you: how much it costs to build a project needs to be calculated. This is the cost of the project. >>>More