After the announcement of the winning bid, the relationship with the start date Why is the announcem

Updated on society 2024-06-18
8 answers
  1. Anonymous users2024-02-12

    The date of the announcement of the winning bid has nothing to do with the date of commencement of construction, and are two different concepts.

    After the project is won the bid, it is generally carried out for three days after the winning of the bid, and the notice of winning the bid can be issued after the publicity is completed without objection, and the winning bidder is issued with a notice of winning the bid after the confirmation of the winning bid in the project, and the winning bidder is notified at the same time, and the contract is signed with the winning bidder within 3o working days.

    According to Article 56 of the Measures for Bidding and Bidding for the Construction of Engineering Construction Projects issued by Order No. 30 of the Seven Ministries and Commissions, "after the bid evaluation committee submits a written bid evaluation report, the tenderer shall generally determine the winning bidder within 15 days, but shall be determined at the latest 30 working days before the end of the bidding validity period." "Article 62 provides:

    The tenderer and the winning bidder shall, within 30 days from the date of issuance of the notice of winning the bid, enter into a written contract in accordance with the bidding documents and the bidding documents of the winning bidder. ”

    When the written contract is concluded, then the winning bidder shall handle the construction permit in accordance with the relevant requirements, and the project leader can start construction on the date of holding the groundbreaking ceremony, so the date of the winning bid announcement is not the date of the project commencement, and only after the project is won can the project be implemented after the commencement of construction.

  2. Anonymous users2024-02-11

    Because there is a publicity period during the bidding period, after the publicity, after receiving the notice of winning the bid, the construction contract must be signed, according to the procedure, the construction permit can be declared, and the construction permit can only be started after getting the construction permit.

  3. Anonymous users2024-02-10

    The date of winning the bid and the date of commencement of construction are two different things.

    After the issuance of the notice of winning the bid, it means that the bidding procedure is over, and then the construction contract will be signed, and the construction contract will be submitted for construction after the construction contract is signed, and the supervising engineer will decide when to issue the construction order according to whether the site conditions are met, otherwise it will cause claims.

  4. Anonymous users2024-02-09

    After the bid is announced, it is necessary to sign a contract, go through the construction permit and other related procedures before starting construction.

  5. Anonymous users2024-02-08

    The publicity period after winning the bid is generally 3 days. The law stipulates that for projects that must be tendered in accordance with the law, the tenderer shall publicize the winning candidate within 3 days from the date of receipt of the bid evaluation report, and the publicity period shall not be less than 3 days. If the bidder or other interested parties have any objection to the bid evaluation results of the project that must be tendered in accordance with the law, it shall be raised during the publicity period of the winning candidate.

    [Legal basis].Article 54 of the Regulations for the Implementation of the Tendering and Bidding Law.

    For projects that must be tendered in accordance with the Verification Law, the tenderer shall publicize the winning candidate within 3 days from the date of receipt of the bid evaluation report, and the publicity period shall not be less than 3 days.

    If the bidder or other interested parties have any objection to the evaluation of the bidding results of the project that must be tendered in accordance with the law, it shall be raised during the publicity period of the winning candidate. The tenderee shall reply within 3 days from the date of receipt of the objection; Before replying, bidding and bidding activities shall be suspended.

  6. Anonymous users2024-02-07

    According to the provisions of China's ** Procurement Law, the bid winning results shall be reviewed by the bid evaluation committeeWithin 10 working daysPublicity. At the same time, the winning bidder also needs to carry out filing and other procedures during the publicity period to ensure the normal performance of the tomb-building contract.

  7. Anonymous users2024-02-06

    Legal analysis: not less than 3 days. The tenderee shall, within three days from the date of receipt of the bid evaluation report, publicize the winning candidate, and the publicity period shall not be less than three days.

    Legal basis: Measures for bidding and bidding for construction projects Article 56 After the bid evaluation committee completes the bid evaluation, it shall submit a written bid evaluation report to the tenderee. The bid evaluation report shall be signed by all members of the bid evaluation committee.

    For projects that must be tendered in accordance with the law, the tendering rubber burying person shall publicize the winning candidate within three days from the date of receipt of the bid evaluation report, and the publicity period shall not be less than three days.

    The notice of winning the bid shall be issued by the tenderee.

  8. Anonymous users2024-02-05

    Legal analysis: more than 3 days. Bidding project, the tenderer shall be in receipt of the bid evaluation report results within three days of the announcement of the winning candidates, and published in the public for more than 3 days, in the publicity period to accept the objections of other bidders or interested parties, after receiving the objection the tenderer shall reply within 3 days, and before the reply temporarily stop the bidding activities.

    Legal basis: "Regulations on the Implementation of the Tendering and Bidding Law of the People's Republic of China" Article 54 of the project that must be tendered in accordance with the law, the tenderer shall publicize the winning candidate within three days from the date of receipt of the bid evaluation report, and the publicity period shall not be less than three days. If the bidder or other interested funnel has any objection to the evaluation results of the project that must be tendered in accordance with the law, it shall be raised during the publicity period of the winning candidate.

    The tenderer shall reply within three days from the date of receipt of the objection; Before replying, bidding and bidding activities shall be suspended.

Related questions
8 answers2024-06-18

1. Legal basis.

1. Article 54 of the Regulations for the Implementation of the Tendering and Bidding Law of the People's Republic of China shall be tendered in accordance with the law, and the tenderer shall publicize the winning candidate within 3 days from the date of receipt of the bid evaluation report, and the publicity period shall not be less than 3 days. >>>More

4 answers2024-06-18

1. Look at the bidding time.

2. Look at the bidding parameters and scoring criteria. >>>More

9 answers2024-06-18

"Publicity" means public display. According to the Interim Regulations on the Disclosure of Enterprise Information. >>>More

10 answers2024-06-18

1.Under normal circumstances, public institutions can go to work about a month after the completion of the political examination. Public institution recruitment examination to go through the written test, interview, physical examination, political examination, inspection and other processes, the political examination needs the unit to send more than 3 staff to the candidate's household registration for information verification, if the candidate's immediate or collateral relatives have a criminal record, the political examination is not passed, but the vast majority of them are no problem, the political examination through the publicity period can wait for the unit to notify the work. >>>More

4 answers2024-06-18

Cannot win the bid. Implementing Regulations

Article 42 bidders have any of the following circumstances, it belongs to the bidding and bidding law Article 33 of the provisions of the other ways of fraud: >>>More