Approval by the technical person in charge of the enterprise.
The project manager is responsible to the company manager and to the project department.
Responsible for the quality of the construction undertaken. Implement the company's quality policy.
and the goal of fully fulfilling the project contract. Participate in the contract review organized by the company's management office, and make contract disclosure to the project business personnel. Report to the company's business department to propose major changes to the contract review requirements, and be responsible for the implementation of the review.
Organize and formulate the progress of the project.
and labor, materials, construction machinery and equipment use plan, respectively, reported to the relevant functional departments of the company for review, approval of material procurement plan. According to the construction machinery and equipment use plan, organize the construction machinery to enter the site, arrange the personnel with the operation certificate to work, and establish a list of qualified operators.
-
Construction plan. It is first reported to the technical person in charge of the enterprise for approval, and then reported to the director for review; For special construction plans that exceed a certain scale, they can only be implemented after being approved by the expert group. That is, the technical person in charge of the enterprise will first approve it, and then report it to the director for review and then demonstrate.
Divisional Engineering. The degree of construction danger is divided into three categories: general construction risk, large construction risk, and major construction risk. The project management department should be based on the engineering characteristics of the project, combined with the unit project.
The characteristics of the middle division project define the degree of construction hazard.
Each project management department shall establish a branch project account with greater construction risk and major significance.
For dangerous branch projects, special safety construction plans should be prepared, including foundation pit support.
and dewatering engineering, earthwork excavation engineering, formwork engineering, lifting and hoisting engineering, scaffolding.
engineering, temporary power engineering, etc.
-
The general construction plan is first submitted to the technical person in charge of the enterprise for approval, and then submitted to the director for review; For special construction plans that exceed a certain scale, they can only be implemented after being approved by the expert group.
-
First approved by the technical person in charge of the enterprise, and then submitted to the director for review and certification.
-
It should be demonstrated first and then reported to the superintendent.
-
Construction enterprises shall organize an expert group of no less than 5 people to demonstrate and review the prepared special safety construction plan.
The expert group of the special construction plan for safety must submit a written demonstration and review report, and the construction enterprise shall improve it according to the demonstration and review report, and the technical person in charge of the construction enterprise and the chief engineer shall sign before it can be implemented.
The written demonstration and review report of the expert group shall be attached to the special safety construction plan, and in the implementation process, the construction enterprise shall organize the construction in strict accordance with the special safety plan.
Article 4 of the Measures for the Preparation of Special Construction Plans for the Safety of Dangerous Projects and the Review of Expert Demonstrations.
The special safety construction plan prepared by the professional engineering and technical personnel of the construction enterprise shall be reviewed by the professional and technical personnel of the technical department of the construction enterprise and the professional supervision engineer of the supervision unit, and shall be signed by the technical person in charge of the construction enterprise and the chief engineer of the supervision unit.
-
An expert review team is composed of an odd number of 7 or more people for water conservancy and an odd number of 5 or more people for municipal administration.
-
Article 9 The special plan for the sub-project with greater risk exceeding a certain scale shall be organized by the construction unit to convene an expert demonstration meeting. If the general construction contracting is implemented, the general construction contractor shall organize and convene experts.
Debate meeting. The following persons shall participate in expert debate meetings:
a) members of the expert group;
2) The person in charge of the project or the technical person in charge of the construction unit;
C) the supervision unit, the project director, the engineer and related personnel;
4) The person in charge of safety, the technical person in charge of the construction unit, the person in charge of the project, the technical person in charge of the project, the special program preparation personnel, and the full-time safety production management personnel of the project;
5) The technical person in charge of the project and related personnel of the survey and design unit.
Article 10: The members of the expert group shall be composed of 5 or more experts who meet the relevant professional requirements.
The personnel of all parties involved in the construction of the project shall not participate in the expert demonstration meeting as experts.
Article 11 The main content of expert argumentation:
1) Whether the content of the special plan is complete and feasible;
2) Whether the calculation and verification basis of the special plan conform to the relevant standards and specifications;
3) Whether the basic conditions for safe construction meet the actual situation on site.
After the special plan is demonstrated, the expert group shall submit a demonstration report, put forward clear opinions on the content of the demonstration, and sign the demonstration report. The report serves as a guide for the revision and improvement of the special plan.
--Basis: -Ministry of Housing and Urban-Rural Development, "Measures for the Safety Management of Sub-projects with Greater Risks" [2009] No. 87 ---
-
Legal analysis: According to the law of Xianghao Buguan, the special construction plan of the sub-project with greater risk shall be reviewed and signed by the technical person in charge of the construction unit, stamped with the official seal of the unit, and reviewed and signed by the chief engineer and stamped with the seal of professional guidance before it can be implemented.
Legal basis: "Regulations on the Safety Management of Sub-projects with Greater Risk".
Article 10 The construction unit shall organize engineering and technical personnel to prepare a special construction plan before the construction of a critical project. In the case of general construction contracting, the special construction plan shall be organized and prepared by the general construction contractor. If the critical project is subcontracted, the special construction plan may be organized and prepared by the relevant professional subcontracting unit.
Article 11 The special construction plan shall be reviewed and signed by the technical person in charge of the construction unit, stamped with the official seal of the unit, and reviewed and signed by the chief engineer and stamped with the practice seal before it can be implemented.
If a critical project is subcontracted and the subcontractor prepares a special construction plan, the special construction plan shall be jointly reviewed and signed by the technical person in charge of the general contractor and the technical person in charge of the subcontractor and stamped with the official seal of the unit.
-
Content from user: Yang Yanxiu.
1. Deep foundation pit engineering (1) Earthwork excavation, support and dewatering engineering of foundation pit (groove) with an excavation depth of more than 5m (including 5m). (2) Although the excavation depth does not exceed 5m, the geological conditions, the surrounding environment and the underground pipeline are complex, or the earthwork excavation, support and dewatering engineering of the foundation pit (groove) that affects the safety of adjacent buildings (structures). 2. Formwork engineering and support system (1) Tool-type formwork engineering:
Including sliding form, climbing formwork, flying form engineering. (2) Concrete formwork support project: erection height of 8m and above; erection span of 18m and above; The total construction load is 15kn m2 and above; Concentrated line loads of 20 kN m and more.
3) Load-bearing support system: It is used for full-hall support systems such as steel structure installation, and bears a single-point centralized load of more than 700kg. 3. Lifting and hoisting and installation and dismantling engineering (1) Lifting and hoisting projects that use unconventional lifting equipment and methods, and a single lifting weight of 100kn and above.
2) Lifting equipment installation projects with a lifting capacity of 300kn and above; Dismantling of lifting equipment with a height of 200m and above. 4. Scaffolding engineering (1) Erection of floor-mounted steel pipe scaffolding projects with a height of 50m and above. (2) Lifting height of 150m and above, attached integral and sliced lifting scaffolding projects.
3) Cantilevered scaffolding project with a frame height of 20m and above. 5. Demolition and blasting projects (1) Demolition and demolition projects. (2) Wharves, bridges, viaducts, chimneys, water towers or special constructions that are easy to cause toxic and harmful gas (liquid) or dust diffusion, flammable and explosive accidents in the process of demolition
In terms of style, we can abide by rules and disciplines, unite colleagues, be pragmatic and realistic, optimistic and motivated, always maintain a rigorous and serious work attitude and meticulous work style, be diligent and hardworking. hair in life.
-
Deep foundation pits, high formwork, underground excavation works, cantilever scaffolding, manual digging piles, etc.
-
Refer to the measures for the management of sub-projects with greater risk.
-
The current thermal insulation also needs to be demonstrated by experts.
-
In fact, the approval process for the demonstration and approval of the special construction plan prepared by the over-scale dangerous project is actually written in the document, see the notice on the implementation of the "Regulations on the Safety Management of Dangerous Sub-project Projects" in the "Five, Zhihongmo on the modification of the special construction plan" in the "Five, Zhihongmo on the modification of the special construction plan" ......The construction unit shall make revisions in accordance with the expert opinions, and perform the relevant review and review procedures before implementing the ....... On the other hand, if you think about it, no matter which unit approves it, it is signed and sealed by the technical person in charge of the unit, and it will be shameful.
-
According to the notice of the "Measures for the Safety Management of Dangerous Sub-projects" (Jianzhi [2009] No. 87), deep foundation pit engineering, underground excavation engineering, tall formwork engineering, 30m and above high-altitude work projects, large rivers, deep-water operations in large rivers, urban housing demolition and blasting and other large-scale earth and rock blasting projects need expert demonstration.
Pioneer Posture Exhibition InformationFirst, the construction scheduleEach construction unit according to their own company's construction experience to complete the bidding documents of the project required time, such as our company won the bid, our company intends to complete the bidding documents within 50 days of the project content. (See schedule for details).
2. Construction schedule managementThe entire schedule, including the first and last of the complete set of construction drawings provided by Party A, the entry time of materials and tools, and the deployment of labor, and the completion of each sub-project are carried out around this overall goal. In order to ensure this goal, a top-down planning system is formed, from the overall cherry potato to the details.
-
If the special construction plan for a dangerous project that exceeds a certain number of regulations is concluded as "passed" after expert argumentation, the construction unit may refer to the expert opinions to modify and improve it on its own; If the conclusion is "adopted after revision", the expert opinion should clarify the specific content of the amendment, and the construction unit shall revise it in accordance with the expert opinion, and perform the relevant review and review procedures before it can be implemented, and the modification shall be informed to the expert in a timely manner.
Legal basis: Notice of the General Office of the Ministry of Housing and Urban-Rural Development on Issues Concerning the Implementation of the Regulations on the Safety Management of Dangerous Sub-projects
3. About the participants of the expert demonstration meeting.
Participants in the expert demonstration meeting of the special construction plan of the critical project exceeding a certain scale shall include:
a) Experts; 2) The person in charge of the project of the construction unit;
3) The technical person in charge of the project and related personnel of the relevant survey and design units;
4) The technical person in charge of the general contractor and the subcontractor or the professional and technical personnel authorized to appoint it, the project leader, the project technical leader, the special construction plan preparation personnel, the full-time safety production management personnel of the project and related personnel;
5) Supervision unit project total macro pure mu supervision engineer and professional supervision engineer.
Fourth, on the content of expert arguments.
For special construction plans for critical projects exceeding a certain scale, the main contents of expert argumentation shall include:
1) Whether the content of the special construction plan is complete and feasible;
B) the special construction plan calculation and verification basis, construction drawings in line with the relevant standards and specifications;
3) Whether the special construction plan meets the actual situation of the site and can ensure the safety of construction.
5. Modification of the special construction plan.
If the special construction plan for a critical project exceeding a certain scale is concluded to be "passed" after expert argumentation, the construction unit may revise and improve it by itself with reference to expert opinions; If the conclusion is "adopted after revision", the expert opinion should clarify the specific content of the amendment, and the construction unit shall revise it in accordance with the expert opinion, and perform the relevant review and review procedures before it can be implemented, and the modification shall be informed to the expert in a timely manner. Trouser call.
Construction organization design of the dredging project of the Junheyong section of the Shijing River in Baiyun District, Guangzhou. >>>More
Emergency plan, special construction plan 370
Decoration Engineering Special Construction Organization Design 314 >>>More
First, the general situation of the project.
XX Bay Bridge and XX River Bridge, starting station number: K22+, ending station number: K23+, XX Bay Bridge bridge length, 9 30m structural continuous T beam. >>>More
Construction organization design, this focus is on the organization, including the organizational structure of the project department, the basic construction technology, etc., it should be said that it is the overall and approximate general construction design. >>>More
Cantilevered discharge platform.
Design size: steel platform length, width 2m, primary and secondary beams are made of 16 I-beams. >>>More