1. Enter, tear down the wall, build the wall.
2. Bathroom, kitchen floor for 24-hour closed water test (the developer needs to complete this task).
3. Drill the trunking, hydropower transformation and acceptance.
4. Concealed hydropower renovation project of buried trunking, and waterproof engineering began to be done without leakage in the closed water experiment.
5. Bathroom and kitchen are attached to the wall magnetic sheet.
6. Carpentry entry, hanging ceiling, gypsum corners.
7. Cover the door and the window. Make a wooden cabinet frame.
8. Synchronous production of various wooden doors, modeling doors and flat pressing.
9. The wooden panel is brushed with dustproof paint (clear oil).
10. The window sill marble countertop is leveled and laid.
11. Wood veneer paste, line production and fine installation.
12. Wall base treatment, grinding and leveling.
13, household goods, stickers (protective edges) are pasted at the seams of the door.
14. The wall oil ici is at least three times.
15. Furniture paint into the field, nail holes, paint.
16. Treat corners, lay floor tiles, solid wood or laminate wood flooring, waterproof marble strips, baseboards.
17. Installation and debugging of lamps, sanitary ware, handles, and door locks.
18. Clean up and sanitize, repair the floor tiles, and withdraw from the site.
19. Preliminary acceptance within the decoration company.
20。The three-party appointment time is formally accepted and delivered to the owner.
-
1.Preliminary drawing design.
2.The main body of the house is demolished, the wall is demolished, and the wall is built.
3.Trunking of the line, reconstruction of the hydropower jurisdictional line.
4.Carpentry, hanging ceilings, gypsum angles, etc.
5.Veneer bricks, bathrooms, kitchens with wall magnets.
6.Paint the walls, fix the nail holes, paint.
7.Kitchen hygienic ceilings.
8.Cabinets, door installations.
9.room and other wooden doors installed.
10.Flooring is installed and installed.
11.Cover wallpaper (optional).
12.Radiator mounting.
13.Switch socket installation.
14.Lighting installation.
15.Hardware sanitary ware installation.
16.Curtains and rods are installed.
17.Cleaning and cleaning.
18.Furniture comes in.
19.Placement and installation of household appliances.
20.Home accessories.
-
First, the preliminary design.
To decorate a house, the first thing is to start with the design, the designer has a detailed understanding of your entire family situation and the house type, and their own ideas and opinions should be clearly communicated with the designer to avoid some unnecessary troubles in the later stage. In addition, after the design is out, it should be checked, and the unsatisfactory places should be adjusted in time.
Second, the main body of demolition and reform.
At the beginning of this step, even if the construction stage is officially entered, the main demolition and modification should be carried out in accordance with the design plan, and the framework of the construction site should be built first. The main body demolition and renovation package Dongqing wheel includes wall demolition, wall building, shoveling wall skin, etc.
3. Hydropower transformation.
Hydropower renovation is the most important step in the decoration process, and many houses in life will have hidden dangers left by hydropower projects that are not up to standard. Therefore, this part of the construction must be careful to avoid unnecessary troubles in the later stage.
4. Carpentry engineering.
Carpentry is a complex process, of course, carpentry can also be handled as a key part of the main modification, and there is no conflict with the hydropower transformation, and sometimes there will even be some cooperation. Carpentry is the type of work to complete various wooden works in the house, and the labor cost accounts for 40-60% of the entire decoration labor cost.
5. Masonry engineering.
Masonry engineering is the tile step that everyone is more concerned about, as well as the wall, the ground, the area of waterproof engineering, etc., the poor construction quality of this project is also directly related to the appearance of the decoration, and the waterproof quality is directly related to the quality of life after moving in.
6. Painting works.
When it comes to the painting project, it generally marks the end of the hard decoration part, which mainly includes wall surface treatment, batch scraping putty, grinding, brushing latex paint, etc. The painting project is a face-saving project, but if it is not done well, there will be various troubles in the later period, such as wall cracking, paint peeling, etc.
7. Finished product installation.
This step is to install various furniture and household appliances, such as switch and socket installation, lamp installation, hardware and sanitary ware installation, curtain installation, household appliance installation, etc.
-
The general order of renovation is as follows:
1. Demolition and reconstruction of the main body.
The main demolition and renovation is the first project in the decoration, mainly including wall demolition, wall building, shoveling wall skin, dismantling heating, replacing plastic steel windows and so on. The garbage after demolition and modification should be cleaned out in time to ensure the cleanliness of the room and make it more convenient for future construction.
2. Renovation of waterway circuits.
Before the water and electricity renovation, the cabinet designer should come to the door to make the first measurement, help determine the exact location of switches, lamps, basins, bathtubs, washing machines, etc., and formulate a renovation plan. It is also best to send someone to design the location of the power supply and interface according to the model you choose. The air conditioner and its power supply should be placed on the wall at the head of the bed as much as possible to avoid the situation where the air conditioner is blowing directly at people.
3. Paste wallpaper.
After the wall paint is painted, the oiler will brush the base paint in the place where the wallpaper needs to be pasted, and it can generally dry the next day, and then you can paste the wallpaper.
4. Install the socket panel.
The socket panel can be installed in about half a day, and it should be noted that the socket is best bought with a switch function, especially in the kitchen, so that the rice cooker and microwave oven can be plugged and unplugged from the power supply, and it can be controlled with a switch.
5. Install cabinets.
The cabinet is a matching project, and the range hood, stove and sink should be purchased in advance, and it is best to send it on the same day and install it together with the cabinet.
6. Install the finished door.
The finished door should be installed before the floor, mainly because of the complex steps of installing the door, hinges, door locks, door stoppers, door frames, etc., there are many tools used.
7. Install hardware.
It is recommended that before installing the floor, the drying rack, curtain rod, lamps, sanitary ware, bathroom and other fragmented items with a lot of ash scattered during installation are installed, if the procedure is reversed, it is likely to cause wear and tear to the floor.
8. Install the floor.
Before installing the floor, it must be leveled, and the ground must be cleaned, and it must not be cleaned with water. It is better not to cut the floor in the house, but to cut it in the hallway, so that you can clean the hallway at the end.
-
Under normal circumstances, the construction sequence of the decoration project is: building structure transformation, water and electricity wiring, waterproof engineering, tile paving, carpentry production, wood painting, wall finishing, floor paving, water and electricity installation, equipment installation, pollution control, sanitation and cleaning, auspicious day occupancy. The construction sequence of each type of work in home decoration is:
Bricklayer, Plumber, Plasterer, Carpenter, Painter, Plumber, Equipment Installer, Pollution Control Worker, Cleaner. When formulating specific construction procedures, attention should usually be paid to basic principles such as overall arrangement, finished product protection, and safety and environmental protection.
Customary procedures during construction——
1) Civil renovation stage.
Enter, tear down the wall, build the wall;
Customized doors, cabinets, bath cabinets, furniture, radiators, etc. for initial measurement and design;
chiseling trunking, hydropower transformation;
Concealed hydropower renovation project of buried trunking;
Do waterproof engineering, and do a 24-hour closed water test on the bathroom (kitchen) floor;
Bathrooms and kitchens are attached to walls and floor tiles;
Custom-made doors, cabinets, bath cabinets, furniture, etc. are measured.
2) Grassroots treatment stage.
carpentry entry, hanging ceiling, gypsum line;
Wrap door covers, window covers, and make wooden cabinet frames (except for custom-made);
Synchronous production of various wooden doors and modeling doors (except for custom-made);
Wooden panels brushed with dustproof paint (clear oil);
window sill marble countertop leveling;
Wood veneer pasting, line making and fine installation;
wall base treatment, grinding, leveling;
Furniture, doors and windows are pasted with stickers (protective edges) on the seams.
3) Detailing stage.
Paint the wall at least three times, first two times;
Furniture paint entry, nail holes, paint;
treatment of corners, laying floor tiles, doorway stones;
Flooring and underfloor to prevent formaldehyde, mold, and germ contamination of the floor;
Custom-made doors, cabinets, bath cabinets, furniture, radiators, etc.;
installation and commissioning of lamps, switches, sockets, sanitary ware, handles, door locks, pendants, etc.;
The last pass of wall paint;
Cleaning and sanitation, floor tile repair, and withdrawal;
Preliminary acceptance within the decoration company;
The three-party appointment time is formally accepted and delivered to the owner.
-
1.Choose coatings with excellent performance.
When choosing coatings, we should be clear about what requirements we want to achieve when choosing coatings, such as water resistance, high gloss, don't blindly choose, there is also a big gap in the types of water-based coatings.
Shuaike chemical interior wall coating resin.
2. Estimate the dosage before buying paint.
Many consumers do not estimate the amount of paint used in advance, for fear of buying less paint, and always buy more when purchasing. This may cause a waste of materials, increase the cost of home improvement, and at the same time, the accumulation of too much paint will also have a certain impact on construction safety. Therefore, it is recommended that consumers must look at the area of the construction area before construction, so as to estimate the amount of materials purchased.
3. The construction preparation process needs to be done well.
Water-based building exterior wall paint resin.
Paint dripping will stain the furniture during construction, so paste color separation paper at the junction of doors, window frames and furniture before painting to protect it from dripping paint that is difficult to clean.
4. Wall paint construction tips.
Different tools will bring different effects, for example, the roller brush is divided into two kinds of thickness, and the bristles are also different from wool and chemical fiber, and the painting effect of different brushes varies greatly.
-
Decoration process is divided into: oilman, carpenter, bricklayer, plumber.
-
The decoration process is generally to change the plumbing and electricity first, including the adjustment of the position and layout of the kitchen and bathroom water pipes, and then it is necessary to pave the floor tiles and wall tiles, and then the ceiling of the house includes the living room, bedroom, study, dining room, kitchen and bathroom and the ceiling of the balcony, and then the door and mouth of the wall are painted, and the last step is to install lighting.
-
Hello: There are ten major processes in general construction:
1: Plastering works.
2: Lightweight partition.
3: Veneer engineering.
4: Coating engineering.
5: Suspended ceiling engineering.
6: Laminating and soft package engineering.
7: Door and window engineering.
8: Detailing.
9: Building ground engineering.
10: Curtain wall engineering.
-
Walls, floors, doors and windows, ceilings, partition walls, coatings (interior and exterior walls), details, etc.
-
Plastering, hanging ceilings, wallpaper, wall cloth, hard packing, soft packing, ceiling modeling, waterproofing, marble wet paste, dry hanging, tile paving, wall mounting, etc.
Annealing is generally arranged after the manufacture of the blank. >>>More
Common home decoration styles include modern simplicity, Chinese style, European style, pastoral style, Mediterranean style, etc., there are more people who choose modern simplicity, and it is better to design.
Steamed vegetables. The main ingredients are fresh meat, soy products, vegetables, seafood, mushrooms, lotus root slices, potatoes, lettuce, winter melon, and mushrooms. >>>More
1. The principle of satisfying spiritual requirements:
People's requirements for the spiritual aspect of catering cultural space are developed with the development of society, and the psychological activities of customers are ever-changing, difficult to grasp, and the personalized and diversified consumption trend makes the catering cultural space integrate strong cultural personality and taste. Whether the development of the catering industry is successful, the focus of its competition is to grasp the psychological activities of customers, and use cultural taste to impress the hearts of consumers. >>>More
Front desk design steps: first understand the customer's needs, grasp the customer's purpose, and the customer's business direction, according to the customer's business aspects, determine the interface color tone and layout. Secondly, according to these needs, refer to the same type of **, find a certain law of bending and renting from the same type of **, and then use ps to design a rough home page interface. >>>More