You can clean it first, water the hole after cleaning, and then apply mortar or concrete.
-
Chiseling. We need to chisel out some of the particularly low strength concrete on the surface of the honeycomb surface. This is done all the way down to the dense part of the inside. In fact, to put it bluntly, the concrete with unqualified strength is chiseled first, and then chiseled all the way to the part with qualified strength.
Clean and water to moisten. After we have chiseled off some of the floating concrete on the surface, we have to clean up some of the crumbled concrete and rinse it with a water hose. Make sure the area is wet. Patching can only be done after that.
3.Mend. Fine stone concrete is used to fill the holes.
The so-called fine stone concrete is to use fine stone concrete that is more than one grade higher than our concrete load-bearing beam to repair the parts we chiseled. The conventional method is to take concrete with a high grade and then seal the part.
-
If this happens, we can take appropriate treatment methods, such as smearing or grouting the hole, and watering the hole while walking along the river to keep the hole moist.
-
Dear, slow burial Hello, I am glad to answer for you: how to remedy the cavity in the load-bearing beam of the self-built house? Answer: Hello, dear, the concrete beam reinforcement should pay attention to the main reinforcement, the payment reinforcement, the stirrups, the diagonal tendons, and the erection disturbance of the answering ribs, the most important of which is the main reinforcement.
When the lintel is designed, the diameter of the main reinforcement is generally not less than 20mm, and it is distributed about 50mm away from the lower skin of the beam (25-50mm of the protective layer). If the beam height is more than 500mm and the middle of the beam height is selected at the position of the drilling air hole, the main reinforcement of the lower layer will not be damaged, that is, there are steel fragments drilled out of the reinforcement and stirrups will not have a big impact, and the air hole can be used safely by blocking the air hole with cement. If a hole is punched in the lower layer of the beam height and the main reinforcement within the protective layer is destroyed, the consequences are serious, and there is only one remedy:
Peace and joy!
-
There is only one way, and it looks very simple, and that is to fill in the hole.
After the hole in this beam, there is no potential safety hazard at all for us to fill it, because although it produces a hole, it is a whole in other places, and it is poured with reinforced concrete, and the force that should be played has been played, and the remedy is just to make yourself psychologically comfortable and look good. There is no effect on the load-bearing.
However, although this remedy is only filled, it cannot be sloppy when filling, because of the particularity of cement, resulting in the two not being poured at the same time, it is easy to produce an unfavorable situation of combination.
Therefore, when we remedy, we should rinse the cavity surface well, rinse some ash and slag, and then rinse the cavity surface well, it must be wet, and the two cannot be combined at all when it is dry, and the things that are made up will shrink directly, or it will fall off.
-
1. The first step is to remove the concrete with cavities or non-compactness, and remove it to the dense part;
2. The second part will be cleaned of the removal surface, and the following interface agent can be brushed if conditions are possible 3, and the high-grade fine stone concrete (preferably reinforced with vibration-free high-strength concrete) is poured and compacted 4, and attention should be paid to maintenance.
-
The first step is to remove loose stones and concrete from the holes.
The second step is to clean it with water.
The third step is to fill it with concrete of a higher strength grade.
For example, if you are now C25, you can fill it with concrete with C30 strength grade, and if the hole is small, you can also fill it with high-strength cement mortar.
Generally speaking, only those who have deposited the housing provident fund can apply for a housing provident fund loan, even if it is a rural household registration, as long as their unit pays the housing provident fund, then they can apply for a housing provident fund loan. The conditions for applying for a housing provident fund loan are: 1. The borrower must have a permanent urban residence or valid residence status in the city; 2. Push forward from the date of application, and pay the housing provident fund in full for more than 12 consecutive months (only one person is allowed to take out a loan if both husband and wife have paid the provident fund); 3. There are contracts (agreements) and related materials for purchasing, building and overhauling self-occupied houses in accordance with the law; 4. Have a certain proportion of self-raised funds. >>>More
If the rural house does not have a property ownership certificate, it should be handled in a timely manner. According to the provisions of the "Housing Registration Measures", the following materials shall be submitted when applying for the initial registration of house ownership due to the legal construction of a house: >>>More
The five elements of self-built house design mainly include kitchen design, living room design, bathroom design, bedroom design and sloping roof design. >>>More
All localities have a set of standards for the homesteads used in rural homesteads that are in line with the actual local people's conditions, and in accordance with the standards, the homesteads for rural housing applications are examined and approved. The standard area of each household base is 80-120 square meters, and each village committee shall determine the standard of homestead area of the village according to the village plan and the actual land use of the village. Generally speaking, the total land area of a 1-2 person farmer household shall not exceed 95 square meters; The total land area of a rural household with 3 or more persons shall not exceed 125 square meters; The total land area of the original site shall not exceed 140 square meters, of which the building area shall be determined according to the planning of the specific plot and related technologies, and the specific standards announced by the local ** department shall prevail. >>>More
It is decided on a case-by-case basis. If the rural house is built in the middle of a house and the height is not prominent, there is no need to set up a separate direct lightning strike facility, and only need to install a lightning arrester or surge protector at the power inlet of the house to avoid lightning and high voltage along the power line into the house equipment. >>>More