-
Information related to the cost of civilized construction measures: (1) The original and copy of the construction contract (stamped with the information of the acceptance of the construction unit, the construction unit and the completion acceptance data, and some regional quality supervision stations will have their own specific **,
-
The safety reporting information is not exactly the same in each region, but it is roughly as follows:
The following information shall be submitted to the construction project safety supervisor:
3. A copy of the general layout plan of the construction (the construction unit stamps the official seal);
4. Planning and construction of temporary facilities (construction unit, supervision unit, construction unit with official seal);
5. Construction site safety protection facilities erection (setting) plan (construction unit stamped with official seal);
6. Cost plan for safety measures (construction unit, supervision unit, construction unit with official seal);
7. Special safety construction organization design (plan, measures) (signed by the person in charge of the construction unit, the person in charge of the construction unit and the person in charge of the technical department, and the project director and stamped with the official seal of the construction unit, the supervision unit and the construction unit);
8. The original and copy of the accident injury insurance policy for workers in the construction enterprise (stamped with the official seal of the construction enterprise);
9. The family planning agreement registered and filed by the sub-district office where the project is located;
10. The plan for the establishment of night schools for employees, including the setting of the leading group, the allocation of teaching facilities and equipment, the teaching plan, the situation of teachers and the curriculum schedule, etc.;
11. The original and photocopy of the certificate of the person holding the certificate (indicating the name of the project and the location of the project, signed by the person and stamped with the official seal of the construction unit.) )。
1) The original and copy of the construction contract (stamped with the official seal of the construction unit and the construction unit);
2) the original and copy of the bidding ** book or the construction drawing budget (non-bidding project) when winning the bid; (stamped with the official seal of the construction unit).
3) The original certificate of the construction enterprise opening a separate account in the bank (provided when the separate account is activated for the first time) and a copy (stamped with the official seal of the construction unit);
4) Original and photocopy of bank statement or receipt (stamped with the official seal of the construction unit and the construction unit);
5) Original and copy of invoice (stamped with the official seal of the construction unit);
6) The original and copy of the notice of winning the bid (stamped with the official seal of the construction unit).
-
Hello, happy to answer your <>
The acceptance of the main structure is an important part of the construction project, which is mainly to inspect and evaluate the main structure of the building to ensure its construction quality and safety. The main acceptance content is as follows: prosthetic limb 1
Check whether the foundation of the building meets the design requirements, and whether there are problems such as settlement and deformation. 2.Check whether the construction of the main structure of the building conforms to the design drawings, specifications and standards, and whether there are quality problems.
3.Check whether the quality of the structural materials and components of the building meets the requirements, including the strength of the concrete, the quality of the reinforcement, etc. 4.
Check whether the various structural joints of the building are firm and reliable, whether there are cracks and deformations and other problems. 5.Check whether the load bearing capacity of the building meets the design requirements and whether there are problems such as overload.
6.Check whether the safety facilities of the building are complete, including fire fighting facilities, emergency evacuation facilities, etc. 7.
Check whether the construction process of the building meets safety standards and whether there are any risk factors. The above is the main content of the acceptance of the main structure, through the inspection and evaluation of the above content, it can ensure that the structural safety and quality of the building meet the requirements of the code.
-
The contents are as follows: 1. Check the variety, specification, quantity, location, anchorage and joint, lap length, thickness of the protective layer and rust and decontamination of the steel bar used for binding, and the replacement of steel bars and the treatment of beard tendons.
2. Inspection of prestressing engineering.
3. Inspection of steel structure engineering.
4. Perception and quality inspection of the appearance of the main branch project.
5. Inspect the welded joints and mechanical joints.
6. The quality of the construction process of structural concrete and load-bearing masonry.
7. The quality behavior of all parties involved in the construction of the project and the performance of the quality system.
8. The construction quality, structural quality and use function of the construction work surface, the factory certificate, test report, witness sampling and inspection data and structural entity test report of the main materials, structural parts and equipment related to the structural safety and use function.
-
Legal analysis: 1. The sub-project of the main structure shall be completed in accordance with the design documents and meet the requirements of the construction quality acceptance specifications; 2. Quality assurance data, the quality of the main body responsible for participating in the construction is complete and meets the requirements (the data should be reported to the supervision department for review five days in advance); 3. The problems raised in the rectification notice must be fully processed and meet the requirements; 4. The cast-in-place concrete component reinforcement protective layer is qualified (if it needs to be processed, there should be a design verification order or treatment opinions, and the signature and seal are complete); 5. The construction site meets the safety production conditions of civilized construction, and the safety assessment in the decoration stage is qualified; 6. Door and window frames must be installed in place according to the design and specifications; 7. When the junction of different materials and the thickness of the plastering layer is 35mm, the measures to prevent cracking of the wall must all be set in place (add steel wire mesh, the width of each side is 100mm); 8. The lock ring in the junction box must be set in place; 9. In addition to the door opening, the floor with waterproof requirements must be all set up with a height of 120mm and a width of the same wall C20 concrete to turn over; 10. The thickness of the floor slab (each) must be fully measured, and inspected and approved by the supervising engineer to form a fully signed inspection record.
Legal basis: "Construction Law of the People's Republic of China" Article 61 The construction project delivered for completion and acceptance must meet the quality standards of the construction project set by the Planning Department, have complete engineering technical and economic information and signed project warranty, and have other completion conditions stipulated by the state. The construction project can only be delivered after the completion experience is qualified; If it has not been accepted or the acceptance is unqualified, it shall not be delivered.
-
First, the main structure acceptance inspection content:
1.Whether the size positioning of the beam and column plate is required by the design, what is its forming quality, whether there is a honeycomb surface, etc., and whether there are traces of repair, if so, the reason for the repair should be asked, and whether it has an impact on the structure.
2.Whether the embedded parts are accurately buried, whether the reinforcement is reserved, whether the rainwater pipe through the hole is accurate, whether the toilet and other equipment are retained as required, and whether the hole plate reinforcement of the rear seal is reserved.
3.Whether the mortar of the masonry project is full, whether the strength is enough (you can use a hand wrench), how is the lofting of the masonry, whether it is straight, whether the wall is flat, whether the structural column in the masonry is set up, whether the masonry under the frame beam is compact, whether the ring beam is set according to the requirements, and whether the thickness of the mortar screed layer on the wall is too thick.
4.Look at the settlement record of each layer, whether there is too much difference in settlement, the amount of settlement increased in each layer, and the settlement difference between each observation point, if the difference is too large, first increase the observation density.
Second, the materials to be prepared for the acceptance of the main structure:
Construction permits, planning permits.
Notice of Winning the Bid.
Safety and quality supervision and audit report.
Practitioner Qualification Examination Form.
Certificate of Qualification for Construction Drawing Review.
Engineering geological survey report.
Construction enterprise qualifications (including enterprise qualifications, business licenses, safety production licenses, and integrity manuals) in the state.
Letter of appointment from the project manager.
The management certificate (eight members) is best unified with the qualification review form of employees, such as the spring potato site is not good, the project manager must be unified.
Instrument test report. (level, Jingweiyi, tape measure 5m, 50m, compressive concrete test, impermeable concrete test, mortar test, slump barrel, tower ruler, oxygen, acetylene valve, scale, shake meter, etc.).
Construction organization design (must be approved by the company and supervision, signed and sealed).
Special programs (quality assurance system, security system, temporary electricity, etc.).
The post responsibility system of management personnel.
Standard maintenance room (according to the requirements of the layout of the sampling manual, and the required record sheet, temperature, humidity and test block records).
If the construction site has started and there are materials entering the site, do a good job of material testing and basic preparation of the 16 sheets, data b and d.
Generally speaking, most of the enterprises with "construction installation" in the name or business scope have the ability to install and construct steel structures. >>>More
What is intermediate acceptance, which side are you
Io is mostly made up of red-hot silicate rocks. Its surface is also very different from other stars in the solar system, which surprised scientists when they first came into contact with the data sent back by Voyager. They thought that the terrestrial bodies should be covered with large and small craters left by impacts, and then estimated the age of the planet's crust based on the "craters" left in the unit area. >>>More
The full name of HRB is Hot -Rolled Ribbed -Steel Bar.
The following number is the yield strength of the steel bar, for example, HRB500 refers to the hot-rolled ribbed steel bar, the yield strength is 500MPa, 335 is the yield strength of 335MPa, and 400 is 400MPa. >>>More
It's good enough, what else to change, just send it directly.