What kind of work should the construction unit do on the construction site?

Updated on society 2024-02-13
10 answers
  1. Anonymous users2024-02-06

    The constructor is the technical organization and management personnel at the grassroots level. The main work content is to go deep into the construction site under the leadership of the project manager.

    Assist in construction supervision, review the quantity of the project together with the construction team, provide the specifications, models and arrival dates of the materials required on the construction site, do a good job in the acceptance visa and management of on-site materials, and timely carry out the concealed project.

    Carry out acceptance and quantity visa, assist the project manager to do a good job in the data collection, storage and archiving of the project, and have important responsibilities for the progress and cost of on-site construction.

    The job of the constructor is to solve the construction organization design at the construction site.

    The relationship with the site, the organization of things in the design depends on the construction staff to supervise, measure, write the construction log, report the construction progress, quality, deal with the site problems, and is the liaison between the engineering headquarters and the construction team.

  2. Anonymous users2024-02-05

    In fact, in the actual work, although this is a position, there is still a lot of work, and it is also very exercised.

  3. Anonymous users2024-02-04

    The job responsibilities of the on-site applicator are:

    1. Participate in the calculation of materials, the delivery of materials and the acceptance of materials entering the site for all civil engineering projects;

  4. Anonymous users2024-02-03

    Constructors are generally required to work on site.

  5. Anonymous users2024-02-02

    Construction chores and manual work.

  6. Anonymous users2024-02-01

    What are the general departments on the construction site? I have seen the project department on the construction site, but I don't know what other departments there are, and what is the relationship?

    The construction unit of the project is generally divided into five departments and one room, mainly the engineering technology department, the safety and quality department, the material and equipment department, the economic management department, the finance department and the general office. The main responsibility of the engineering and technical defense department is to construct according to the drawings, according to the blueprint, and to build the content of the blueprint planning under the requirements of the relevant specifications, mainly to provide technical support. Most of the working time is on the front-line construction site, so it can be said that it is the hardest worker.

    The safety and quality department is mainly responsible for safety production and quality problems in the construction process, supervising and inspecting and correcting various safety problems and safety hazards existing in the on-site construction, and also needs to control the construction quality of the project. The material set up is responsible for the materials and equipment required for the construction of the project, and the materials and equipment are completed in a timely manner with quality and quantity according to the material demand plan issued by the Engineering and Technology Department. The economic management department is also called the planning and contract department, the commercial department, etc., in some units, and is mainly responsible for the owner's inspection and valuation (according to the amount of work completed on the site to ask the owner's unit for money), labor bidding (to find workers working on the site), labor inspection and valuation of labor units (according to the amount of work done by workers), as well as the calculation of economic indicators such as costs and benefits.

    The responsibilities of the finance department are similar to those of other corporate finance departments, mainly controlling income and expenditure in accordance with relevant rules and regulations, verifying whether payment procedures are perfect and compliant, etc. The general office can be said to be an internal department, which is in charge of the clothing, food, housing and transportation of the project, including the unified procurement of work clothes, the purchase of chefs and ingredients, the leasing of office and accommodation places of the project department, the management of bus scheduling, etc., and is also responsible for sending and receiving official documents and purchasing office supplies.

  7. Anonymous users2024-01-31

    1.Before construction, the construction personnel shall organize to be familiar with the design documents, drawings and materials, check whether they are complete, whether there are omissions, errors or contradictions, and if there are errors, correct and correct the design unit in a timely manner, and make records. 2.

    In the process of studying the design drawings and data, it is necessary to check them according to the actual situation on the site and, if necessary, conduct supplementary surveys to facilitate the preparation. 3.Work with Party A to find out the underground pipes and ground structures of the original bucket, so that protective measures can be taken during the construction process to avoid accidents.

    4.Do a good job in the testing of raw materials, asphalt concrete and mortar ratio, and report to the supervision engineer for approval. 5.

    Before construction, the calibration of measuring instruments such as calibrators, laser theodolites, and steel rulers should be carried out. 6.Inspect and review the piling, road control points, stormwater and sewage pipes and control points delivered by the construction unit.

    7.In order to ensure the reliability of the control network, the protective piles must be completed. The main control point (or guard post) is to be secured and maintained until the end of the project.

    In order to prevent errors, at least two sets of important markers, such as the main control point, are checked against each other, and the Tanzhen grinding line is measured and checked. 8.Construct a network of temporary horizontal points, set up a point every 100 meters according to the horizontal point set provided by the construction unit.

    9.The measurement results can only be used after the calculation of the actual measurement results of the domestic industry, and the measurement results must meet the requirements of the design and measurement standards, and be submitted to the supervision unit for review and approval. 10.

    Understand the impact of construction on units along the route, as well as the impact of vehicular traffic, so that you can make a scheduling plan. 11.Depending on the design scheme, which new materials, new technologies and new machines need to be studied in advance.

  8. Anonymous users2024-01-30

    Summary. Good afternoon, dear<>

    I've seen your question on my side, and I'm trying to sort out the answer, typing the main points, please wait a moment

    What are the units at the construction site where the staff often appears?

    Good afternoon, dear<>

    I've seen your question on my side, and I'm trying to sort out the answer, typing the main points, please wait a moment

    Dear <>

    We'll be happy to answer for you. There are developers and municipal supervision departments on the construction site. The staff showed up often.

    The construction site refers to the construction activities such as housing construction, civil engineering, equipment installation, pipeline laying and other construction activities of industrial and civil projects, and the construction site occupied by the approval and the place where human beings carry out safe production and civilized work and construction, including all areas where construction work can be carried out on land, sea and air. The project manager is fully responsible for the on-site management of the construction process, I hope the above will be helpful to you If you are satisfied with me, please give a thumbs up <>

  9. Anonymous users2024-01-29

    What are the units where construction workers can be employed?

    Construction units, construction units, supervision units, etc. Constructor is a fundamental position in the construction industry, and there is no doubt about its importance. This position has great employment prospects.

    It is safe to say that in the next few decades, as long as there are urban construction and renovation projects, the construction workers will make a big difference in the construction of the project.

    The constructor is mainly engaged in the direct command of the construction work on the front line of the site, assists in the construction supervision, fully coordinates and manages the on-site resources, and promotes the construction process. Constructor is a necessary profession for every engineering project, and the demand for it is particularly large, and he can develop into a project manager in the future, with a good employment prospect. But being a construction worker is undoubtedly the hardest, the most tiring, the internship salary at the beginning is not high at about 3000 to 6000, if the later development is good, after a few years of precipitation on the project manager, the annual salary of hundreds of thousands are available.

  10. Anonymous users2024-01-28

    Scope of project contracting.

    The first phase of the start of the district club and the surrounding earthwork (backfill to the back of the area, the distance within the area is calculated by 1 km), the bamboo roots, tree heads and construction waste in the earthwork excavation need to be transported to the designated area of the pit (the distance is calculated by 2 kilometers), the earthwork compaction compaction must reach more than 90%, the thickness of the layer is less than 50 cm, the earthwork compaction compaction must be tested by the relevant departments after the main can carry out the next process, the earthwork category according to the geological survey report according to the three types of soil calculation.

    1. The excavation of earth and stone, the total amount of excavated earth and stone is about 150,000 cubic meters (including 10,000 cubic meters of bamboo roots, tree heads and construction waste), and the excavation scope and slope setting of earth and stone are carried out according to the series of design drawings or related documents provided by Party A.

    2. The total amount of rolling earthwork is about 140,000 cubic meters, and the rolling machinery used is 18 tons of vibrating roller, layered rolling, and the thickness of each layer of rolling compaction does not exceed 50 cm, and the earthwork compaction coefficient after rolling is: 90%. About 10,000 cubic meters of bamboo roots, tree heads and construction waste were transported to the designated area of the pit.

Related questions
7 answers2024-02-13

The basis for the preparation of the design of the construction organization generally includes the following parts: >>>More