How many levels of wind are prohibited from hoisting operations Tower cranes can not operate above h

Updated on amusement 2024-03-16
11 answers
  1. Anonymous users2024-02-06

    Lifting operations are prohibited above level 5 wind.

    It is forbidden to operate the crane when the wind speed exceeds the conditions specified by the equipment manufacturer. If the manufacturer does not stipulate, it is forbidden to hoist the wind above level 5.

    The standard requires that high-altitude operations should be stopped in windy weather above level 5.

    Bad weather such as rain and snow.

    When working at height, there should be reliable anti-skid and cold-proof measures; If there is a strong wind above level 5 (inclusive), the lifting and hoisting operation of the large formwork should be stopped; The tower crane must be stopped in strong wind weather above level 6.

    The hoisting operation shall not be dismantled in the event of rain, snow, fog and wind greater than level 4.

    Safety specifications for hoisting operations.

    1. Designate personnel engaged in command and operation.

    2. Conduct safety inspection and confirmation of the lifting spreader to ensure that it is in good condition, such as: whether the hook safety buckle is effective, whether the wire rope is broken and stranded, and whether the U-ring is tripped.

    3. Confirm the implementation of safety measures and the hoisting environment.

    4. Check the safety status of the hoisting area, including the demarcation, identification, obstacles, warning area, etc. of the hoisting area.

    5. Wear personal protective equipment correctly; **In the event of a possible accident, take effective precautions and choose a safe escape route.

    The above content referenceEncyclopedia - Hoisting.

  2. Anonymous users2024-02-05

    It is forbidden to operate the crane when the wind speed exceeds the conditions specified by the equipment manufacturer. If the manufacturer does not stipulate, it is forbidden to hoist the wind above level 5.

  3. Anonymous users2024-02-04

    Lifting operations are prohibited above level 5 wind.

  4. Anonymous users2024-02-03

    Category 5 wind or above.

  5. Anonymous users2024-02-02

    Tower cranes are not allowed to be constructed above level 6 winds.

    According to the unified regulations of the tower crane tower base standard specification, when the wind exceeds level 4, the tower crane can work, but if the tower crane is in a non-working state, it should be parked downwind to ensure that the tower crane balance arm is not affected by the wind; When the wind force exceeds level 6, the tower crane should be stopped to avoid accidents in the balance arm.

    Tower crane insistence"Ten"Do not hang. After the operation is completed, the power should be cut off and the box should be locked, and the machinery should be done"Cross"Assignment work. The contents of the ten non-hanging are as follows:

    1) Diagonal hanging is not hoisting.

    2) Do not hang when overloaded.

    3) If the bulk is too full or the bundle is not firm, it will not be hung.

    4) The edge of the hanging object is not hung without protective measures.

    5), the person standing on the hanging object does not hang.

    Lu Jutong 6), the command signal is not clear.

    7) The components buried in the ground are not hoisted.

    8) If the safety device fails, it will not be hoisted.

    9) The light is dark and you can't see clearly.

    10) No hanging in strong winds above level 6.

  6. Anonymous users2024-02-01

    Strong winds above level 6 are not allowed to work, including level 6.

    The contactor power supply in the tower crane distribution box is loose, the terminal board wiring bolt is in poor contact, and the main contact of the contactor is poor; Poor ablation contact of the wiring bolt of the motor rotor and stator coil; The wear of brake pads of high-speed and low-speed motors exceeds the specified requirements; The gears of the gearbox are broken and the bolts of the fixing gears are loose; The phase loss protector does not work.

    The pitching luffing boom tower crane is not realized by the lifting arm of the crane boom, and its advantages are: it can give full play to the effective height of the boom, the mechanism is simple, and the disadvantage is that the minimum amplitude is limited to about 30% of the maximum amplitude, can not be completely close to the tower body, and the load is lifted together with the boom when luffing, and can not be luffed with load.

  7. Anonymous users2024-01-31

    In terms of safety regulations, strong winds above level 6 are not allowed to operate, including level 6. However, most project departments will not think too much for you, depending on their own grasp.

    You can't hurt others, and you can't hurt yourself. There is really no way to communicate with the project department, and the project manager knows the stakes.

    Good luck with your work and stay safe.

    The above quote, thanks to the original.

  8. Anonymous users2024-01-30

    Legal analysis: the implementation of lifting and hoisting operations of the unit of the buried bush relevant personnel should verify the weather conditions at the construction site, outdoor operations encountered heavy snow, heavy rain, fog and wind above level 6, should not arrange hoisting operations.

    Legal basis: "Safety Code for Lifting and Hoisting Operations" Article 9 The relevant personnel of the implementation of the bending cherry lifting and hoisting operation unit should verify the weather conditions at the construction site, and the outdoor operation should not be arranged when encountering heavy snow, heavy rain, fog and strong winds above level 6.

  9. Anonymous users2024-01-29

    Legal analysis: It is forbidden to operate the crane when the wind speed exceeds the conditions specified by the equipment manufacturer. If the manufacturer does not stipulate, it is forbidden to hoist the wind above level 5.

    In windy weather above level 5, work at height should be stopped, and reliable anti-skid and cold-proof measures should be taken when working at height in bad weather such as rain and snow; If there is a strong wind above level 5 (inclusive), the lifting and hoisting operation of the large formwork should be stopped; The lifting operation of the tower crane must be stopped in strong wind weather above level 6, and the demolition operation shall not be carried out in case of rain, snow, fog and wind greater than level 4.

    Legal basis: Article 87 of the Civil Code of the People's Republic of China A legal person established for public welfare purposes or other non-profit purposes and does not distribute the profits obtained to investors, founders or members is a non-profit legal person. Non-profit legal persons include public institutions, social organizations, associations, and social service machines.

  10. Anonymous users2024-01-28

    Legal analysis: hoisting operations are prohibited above level 5 wind.

    It is forbidden to operate the crane when the wind speed exceeds the conditions specified by the equipment manufacturer. If the manufacturer does not stipulate, it is forbidden to hoist the wind above level 5.

    The standard requires that high-altitude operations should be stopped in windy weather above level 5, and reliable anti-skid and cold-proof measures should be taken when working at heights in bad weather such as rain and snow; If there is a strong wind above level 5 (inclusive), the lifting and hoisting operation of the large formwork should be stopped; The lifting operation of the tower crane must be stopped in strong wind weather above level 6, and the demolition operation shall not be carried out when it encounters rain, snow, fog weather and wind force greater than level 4.

    Legal basis: Article 2 of the Standardization Law of the People's Republic of China The standards (including standard samples) mentioned in this law refer to the technical requirements that need to be unified in the fields of agriculture, industry, service industry and social undertakings.

    Standards include national standards, industry standards, local standards, group standards, and enterprise standards. National standards are divided into mandatory standards and recommended standards, and industry standards and local standards are recommended standards.

    Mandatory standards must be enforced. The State encourages the adoption of recommended standards.

  11. Anonymous users2024-01-27

    Legal analysis: When the wind force is greater than level 4, it is strictly forbidden to suspend the operation.

    Legal basis: Work Safety Law of the People's Republic of China

    Article 20 Production and business operation entities shall have the safety production conditions stipulated in this Law and relevant laws, administrative regulations and national standards or industry standards; Those who do not have the conditions for safe production shall not engage in production and business activities.

    Article 41 Production and business operation units shall establish a hierarchical management and control system for safety risks, and adopt corresponding control measures in accordance with the classification of safety risks.

    Production and business operation entities shall establish, improve and implement a system for the investigation and management of hidden dangers of production safety accidents, and take technical and management measures to discover and eliminate potential accidents in a timely manner. The investigation and management of potential accidents shall be truthfully recorded, and the employees shall be notified through the workers' congress or the workers' congress, information bulletin boards, etc. Among them, the investigation and management of major accidents shall be reported to the departments responsible for the supervision and management of production safety and the workers' congress or the workers' congress in a timely manner.

    Local people at or above the county level at all levels are responsible for the supervision and management of production safety departments shall incorporate major accident hazards into the relevant information system, establish and improve the supervision system for the management of major accident hazards, and urge production and business operation units to eliminate major accident hazards.

Related questions