Can terrazzo be soaked in water after it is laid? How long does terrazzo take to grind

Updated on home 2024-04-03
11 answers
  1. Anonymous users2024-02-07

    Terrazzo. It can be soaked in water after paving, because the surface can be waterproof after paving, and it is okay to soak in water for a short time, but it is not recommended to soak in water for a long time. Because of long-term immersion, the crevices will seep water.

  2. Anonymous users2024-02-06

    Hello friends, if your terrazzo is using a new polishing process, it can be soaked in water.

    1) The surface finish of terrazzo crystal treatment is high, which can reach 90 degrees of gloss and up to 102 degrees of gloss, which is equivalent to the quality of imported high-grade marble surface.

    2) The surface hard height is up to 5-7 grades, close to the surface of high hardness granite, and the wear resistance is good.

    3) Anti-permeability, waterproof and anti-fouling (the water seepage rate is less than that of oil resistance, weak acid resistance, alkali resistance, salt spray resistance, and the comprehensive performance of natural protection exceeds that of all current stone products.)

    4) The service life is up to 30 years, and the special formula and structural design ensure that the "high-gloss crystal terrazzo" plate is easy to cycle and repair after being put into use, and the maintenance and cleaning costs and sanitation management difficulties of the ground are greatly reduced.

    5) The terrazzo floor after the treatment of "terrazzo high-brightness treatment agent" is attached to the surface of the anti-permeable material, so the terrazzo does not regurgitate moisture, no longer has a permeable effect, and will not cause the ground to be wet and slippery, and a series of projects such as industrial plants and school education systems are preferred.

  3. Anonymous users2024-02-05

    Yes, soak and rinse and drain.

  4. Anonymous users2024-02-04

    After the terrazzo is dressed. Can you soak in water, when are you not afraid of water? You're just in the water for a while, and you don't always put it in the water.

  5. Anonymous users2024-02-03

    After the terrazzo is paved, it can be soaked in water, and it was originally used for soaking in water for stones.

  6. Anonymous users2024-02-02

    Within 24 hours after 6 hours.

    Spot-watered terrazzo, if the standard grade cement is used, the temperature is between 25 and 35 degrees, and the filling starts within 24 hours after 16 hours, which can be appropriately adjusted according to the different conditions and conditions of the construction site;

    And at least once a day, generally after filling the material after an interval of 72 to 84 hours can be ground (or depending on your actual construction site, generally in the cement solidification of about 7 to 8 percent, grinding will not appear a large number of stones collapse phenomenon).

    Traditional terrazzo has a huge market in China with its unique advantages such as low cost, arbitrary color parquet, and convenient construction, and there are as many as one billion square meters of terrazzo ground used in various buildings in urban and rural areas across the country.

  7. Anonymous users2024-02-01

    Watering terrazzo, if the standard grade cement is used, the temperature is between 25 and 35 degrees, generally in the filling 16 hours after 24 hours of watering maintenance (this can be appropriately adjusted according to the different conditions and conditions of the construction site), and at least once a day, generally after filling the material after the interval of 72 to 84 hours can be ground (or depending on your actual construction site, generally in the cement solidification of about 7 to 8 percent, grinding will not appear a large number of stone collapse phenomenon).

  8. Anonymous users2024-01-31

    Summary. Terrazzo is a commonly used decorative building material, and its main components are marble powder and cement. Terrazzo needs to be cured after construction to ensure its quality and performance.

    If the terrazzo is soaked in water the next day after laying the terrazzo, it may be caused by the following reasons:1Maintenance is not in place:

    Terrazzo needs to be cured after construction, and it is generally required to be cured for about 7-14 days. Failure to maintain proper humidity and temperature during curing, or failure to maintain it in a timely manner, can lead to inadequate hardening of the terrazzo surface, which can affect water absorption. 2.

    Material quality problems: The water absorption performance of terrazzo is related to the quality of its material. If the marble powder or cement used is of poor quality, or if it is not properly proportioned, it may lead to poor water absorption of terrazzo.

    3.Ground treatment problems: Before laying terrazzo, the quality of the ground treatment will also affect the water absorption performance of the terrazzo.

    If the ground is uneven, unclean, or has other problems, it can affect the water absorption of terrazzo. Therefore, if the terrazzo is soaked in water and does not absorb water the next day after paving, it is necessary to check the details of the construction process, find the specific cause and take corresponding measures to repair it.

    You've done a great job! Can you elaborate on that?

    Terrazzo is a commonly used decorative building material, and its main components are marble powder and cement. Terrazzo needs to be cured after construction to ensure its quality and performance. If the terrazzo is soaked in water the next day after laying the terrazzo, it may be caused by the following reasons:

    1.Maintenance is not in place: terrazzo needs to be maintained after construction, and it is generally required to be cured for about 7-14 days.

    Failure to maintain proper humidity and temperature during curing, or failure to maintain it in a timely manner, can lead to inadequate hardening of the terrazzo surface, which can affect water absorption. 2.Material quality issues:

    The water absorption properties of terrazzo are related to the quality of its material. If the marble powder or cement used is of poor quality, or if it is not properly proportioned, it may lead to poor water absorption of terrazzo. 3.

    Ground leakage treatment problem back to the bench: Before laying terrazzo, the quality of ground treatment will also affect the water absorption performance of terrazzo. If the ground is uneven, unclean, or has other problems, it can affect the water absorption of terrazzo.

    Therefore, if the terrazzo is not soaked in water the next day after paving, it is necessary to check the details of the construction process, find the specific cause and take corresponding measures to repair it.

  9. Anonymous users2024-01-30

    Summary. If you have a baby at home, you can directly choose to pave a crawling mat suitable for the baby to crawl, but when choosing a crawling mat, we must pay attention to the environmental protection of the product, if the product is not environmentally friendly, it will affect the baby's health. If you choose to lay a wooden floor, you can directly pave it, and you don't need to play the keel in advance, if you choose to lay a rubber floor, you can also directly pave it, and the construction is very simple and convenient.

    If there is a baby's talk at home, you can directly choose to pave the crawling mat suitable for the baby's crawling, but when choosing the crawling mat, we must pay attention to the environmental protection of the product, if the product is not environmentally friendly, it will affect the baby's health. If you choose to lay a wooden floor, you can directly pave it, and the nuclear chain does not need to play the keel in advance, if you choose to lay a rubber floor, you can also directly pave it, the construction is very simple and convenient.

    What is the specific paving on the terrazzo ground, you can choose according to the interior decoration style, your own preferences and economic ability, because the wooden floor is more expensive, but the decoration effect is better, and the rubber floor is cheaper, but the decoration effect is worse.

  10. Anonymous users2024-01-29

    It is recommended that it is very necessary to clean the ground before carrying out terrazzo. When terrazzo work, the ground must be clean and level to ensure that the terrazzo surface is smooth and even.

    Washing the floor with clean water removes contaminants such as dust, dirt, fibers, and other impurities. If the floor is not cleaned, these contaminants may impede the adhesion of the terrazzo coating to the ground and cause blistering or other defects in the terrazzo coating.

    Make sure the ground is completely dry before proceeding with terrazzo work. If the surface is not dry, air may be caught under the terrazzo during the coating process, resulting in a coating that is not tight enough and prone to problems.

    Therefore, in order to ensure the quality and durability of the final result, we strongly recommend cleaning the ground before performing terrazzo in Can Tai to ensure that the surface of the ground is sufficiently flat, clean and suitable for coating terrazzo material.

  11. Anonymous users2024-01-28

    What to prepare before making terrazzo? The things prepared before making terrazzo are mainly materials and mechanical equipment;

    One material: cement, grinding stone aggregate, sand, lattice strips, mineral fuels, etc.

    2. Machinery and equipment: terrazzo machine, drum (diameter is generally 200 250mm, about 600 700mm long, concrete or iron), wooden trowel, brush, iron dustpan, ruler, trolley, flat shovel, 5mm aperture sieve, oil stone (specifications according to coarse, medium and fine), rubber water pipes, large and small buckets, brooms, wire brushes, ironware, etc.

Related questions
4 answers2024-04-03

Advantages of terrazzo flooring:

1. Good wear resistance, crushed stone is added to the terrazzo floor as aggregate, which has good wear resistance; >>>More

16 answers2024-04-03

Terrazzo is made of cement, after adding stone ballast of different colors and different particle sizes, pouring cement stone slurry of a certain thickness, and making an artificial stone pavement and ground with a design pattern after surface grouting, fine grinding, waxing and other processes; According to the preparation method, terrazzo is divided into two categories: ordinary terrazzo surface layer and art terrazzo surface layer; According to the production process, it is divided into two types: prefabricated terrazzo (artificial stone) and cast-in-place terrazzo. >>>More

8 answers2024-04-03

How to polish the old terrazzo floor quickly, how to clean the terrazzo floor >>>More

10 answers2024-04-03

Terrazzo waxing you can only last for a while. After that, wax is required. In addition, it is slippery after waxing, and it is easy to fall. Crystallization is more expensive than waxing, but it lasts a little longer. >>>More

7 answers2024-04-03

The advantage is that it is more beautiful, and the disadvantage is that it is not good to look after a long time.