Which friend is the data clerk of the construction unit???

Updated on society 2024-04-20
9 answers
  1. Anonymous users2024-02-08

    The work of a data clerk is definitely not very easy to do at the beginning, because I don't know how to start, I only started to contact this area last year, I will tell you some of my experience, I hope to give you some help.

    1. The engineering data first needs to know the division of the quality acceptance of the construction project, which are the sub-projects, which are the sub-divisions, and which sub-divisions include the sub-projects, which is the content of the "Unified Standard for Construction Quality Acceptance of Construction Projects" GB50300-2001.

    After you are familiar with the above, you can understand how far the project has been carried out according to the actual project you are in, whether it is still under the construction of the main structure, or whether it has been carried out to the stage of building decoration and decoration. That is, what is the current situation of the project, then what kind of information needs to be prepared.

    2. After you know the first item, then you can first find the corresponding construction acceptance specification, and first look at what information is required to be done in the corresponding specification, for example: when the main structure is constructed, you need to find the "Concrete Structure Construction Engineering Quality Acceptance Specification", and then see which sub-project is carried out, whether it is a formwork sub-project or a steel bar sub-project, or a concrete sub-project, etc., and then look at the specific sub-project façade needs to do what construction records or concealed acceptance records.

    Note: In the process of completing the second information, you need to know that all materials entering the site need to have a certificate, product quality certification documents or inspection reports, especially pay attention to the materials that require the re-inspection of the site, and need to do witness sampling and re-inspection in time, such as steel bars, cement, bricks, steel connectors, etc.

    3. The next thing is to sort out the data for the acceptance of the project As mentioned in the first item, you know the division of the project, then you can start the acceptance of the completed project, that is, the filling of the inspection batch, and then after the completion of the entire sub-item, the sub-project acceptance will be carried out, and then it will be completed step by step.

    To add a note:

    1. Regarding the data inspection work Taking the project inspection as an example, the ** required is roughly as follows: 1) a project inspection form; 2) Construction records; 3) Concealed acceptance record (some processes do not have this, but most processes will have this, pay attention to the provisions in the specification); 4) Inspection record form (concrete, waterproofing and other processes have requirements, some processes do not have this, pay attention to the specification requirements); 5) Inspection batch project quality acceptance record form.

    2. The materials required for inspection are: 1) materials and equipment inspection form; 2) Material certificate, product quality certification documents and factory inspection report; 3) Witness the sampling re-inspection report (you need to re-inspect in accordance with the provisions of the corresponding construction quality acceptance specifications, pay attention to the requirements in the specifications).

  2. Anonymous users2024-02-07

    I'm a supervisor, and I know someone who works as a data clerk. It's the same as you, but he's already done a complete construction site, and now it's no problem to do the data.

    His way of playing is: make full use of the library. Then add the following construction technical information***. Slowly, I learned to ......Be patient.

  3. Anonymous users2024-02-06

    Leave an email to send you a complete set of information software.

  4. Anonymous users2024-02-05

    The main duties of a construction site data clerk are:

    1.Collection, sorting, filing, archiving and storage of engineering data.

    2.Collection, inspection and summary of various quality assurance materials in the construction process.

    3.Recording, sorting, countersigning, copying, and distribution of various meetings during construction.

    4.Sampling, inspection, result return, reporting, classification and storage of various test blocks and specimens in construction.

    5.Collection, transmission and feedback of various engineering information, and timely report to the leader if necessary.

    Collect, archive and sort out all kinds of information such as drawings, supporting facilities, budget and final accounts of various development projects.

    Arrange the sending and receiving of drawings and materials for construction projects.

    Collection of all kinds of technical books and magazines; Refine workflow documents, etc.

    Skills and competencies required of a data clerk on a construction site:

    1. Simple drawings will be seen such as architectural and structural drawings.

    2. The process of construction materials on the site must be known.

    3. The use of office software and the application of data procedures.

    4. Documents and materials should be sorted out, classified and filed in a timely manner for easy reference.

    5. The information that should be prepared for the acceptance of each project.

    Main business scope:

    Minute; materials for review; Construction application and report; visa application; As-built records, etc. The business covers the collection, collation and filing of all information related to construction projects. It can be said that it is a primary file management content.

    Things you need to do:

    Collect, archive and sort out various materials such as pre-licenses and contracts for each development project. Collect, archive and sort out all kinds of information such as drawings, supporting facilities, budget and final accounts of various development projects. Arrange the sending and receiving of drawings and materials for construction projects.

    Collection of all kinds of technical books and magazines; Refine workflow documents.

    The data clerk is responsible for information documents such as:

    Organize and keep management documents, notices, relevant technical documents, construction technical standards, process standards, construction specifications, atlases, construction drawings, construction organization design, project quality plans, etc.

    The information formed in the construction process such as: construction technology disclosure, project contact form, change visa form, project negotiation records, meeting minutes, process checklist, equipment installation checklist, commissioning records, engineering hidden (pre)inspection records, design changes collation, preservation and archiving. Preparation of data, processing of texts such as project pre-settlements.

    At present, the data clerk of the construction site is generally served by the civil engineering students of colleges and universities, and the data clerk on the construction site.

    In order to learn the important infrastructure drawings and find them as quickly as possible when needed, it is necessary to learn to read the drawings and recognize the types of drawings.

    To learn to fold drawings and classify them, the most important thing is to learn to read the drawings first, which is very laborious. Have a certain understanding of CAD, and know the most basic icons and drawing methods.

    It's much easier to learn by asking experienced technicians than by working hard yourself. At the same time, there are many jobs and documents that you need to sign directly with the engineer and supervisor in charge, and the superior headquarters and the ** department ask for information to investigate.

  5. Anonymous users2024-02-04

    1. Gray soil foundation, sand and gravel foundation, geosynthetics foundation, fly ash foundation, strong compaction foundation, grouting foundation, preloaded foundation, the strength or bearing capacity of the foundation should be inspected, each unit of the project should not be less than 3 points, more than 1000m2 of the project, every 100m2 should have at least 1 point, more than 3000m2 of the project, every 300 m2 should have at least 1 point, each independent foundation should have at least 1 point, the foundation groove should have 1 point every 20 extension meters.

    2. Cement soil mixing pile composite foundation, high-pressure jet grouting pile composite foundation, sand pile foundation, vibro pile composite foundation, soil and ash compacted pile composite foundation, cement fly ash gravel pile composite foundation and tamped cement soil pile composite foundation, bearing capacity inspection, the number is the total, not less than 3, and the number of single pile strength inspection is the total, not less than 3.

    3. The gray soil foundation has a mix ratio and a layered backfill compaction coefficient detection.

    4. The sand and gravel cushion has a mix ratio and a layered backfill compaction coefficient detection.

    5. There is a test report for lime, and there is a test on the particle size of lime and the organic matter content of the coating.

    6. There is a retest report for sand and gravel cushion and sand and gravel, and there are tests for sand and gravel, organic matter content, mud content, particle size, etc., and the cement and soil mixing pile bearing is 90d test piece.

    7. Fly ash foundation, fly ash has a retest report, fly ash particle size, alumina and silica content, burning vector and other detection.

    8. There must be 1 group of specimens for every 50 m3 poured pile, and 1 group of specimens for each pile less than 50 m3.

    9. A set of specimens (3 pieces) should be made every 100kg of semi-finished sulfur cement semi-finished products of static pile.

    10. The finished pile has a product certificate.

    11. The backfill has a mix ratio, layered backfill compaction coefficient detection, and the thickness of the filling uses a diesel tamping machine with a layered thickness of 200 250mm. In winter, the thickness of the backfill should be reduced by 20% to 50% compared with room temperature.

    12. Each layer of backfill should be concealed, and each layer should be divided into inspection batches for acceptance.

    GB50203-2002 Code for Acceptance of Construction Quality of Masonry Engineering

    1. The stability and strength of the cement shall be re-checked. Cement inspection and batch regulations: according to the annual production capacity of the cement plant.

    l More than 1,200,000 tons, no more than 1200t as a number;

    l 600,000 1,200,000t, numbered with no more than 1,000t;

    l 300,000 600,000t, numbered with no more than 600t;

    l 100,000 300,000 tons, numbered with no more than 400 tons;

    l Less than 100,000t, no more than 200t as a number;

    2. For mixed mortar above m5, the mud content of the sand should not exceed 5%.

    3. The mortar mixed with organic plasticizer should have a masonry type inspection report. (Plasticizer: such as microfoam, which is made of rosin, alkali and boiling with water, and its lubricating effect).

    4. For masonry mortar of various types and strength grades of masonry with mortar test blocks not exceeding 250 m3, each mixer shall be sampled at least once; at the mouth of the mortar mixer.

  6. Anonymous users2024-02-03

    1. First of all, you have to have a little foundation in architecture, at least you have to read the construction drawings!

    You can take a look at "Housing Architecture", "Civil Engineering Drawing", the book "Information Clerk" in the architecture bookstore.

    2. It is best to go to the front line and actually contact it, and it is easier to understand the theory and practice.

    3. When you go to the construction site, you can find the completion materials made by the predecessors, and do it while learning.

    4. After a complete experience of engineering, basically most people will do it. p The construction data clerk mainly does: record the relevant tests during construction, submit the test of the building materials used in the construction, record the acceptance of the construction process, record the concealed acceptance, and make the overall acceptance conclusion of important engineering parts.

    In fact, many of these things are filled in the regulations, and then find the construction, supervision and other units to confirm the signature, seal, and complete one process after another.

    In fact, the data clerk is a record of the entire building from the beginning of the construction procedures to the completion of construction, completion acceptance, data sorting and handing over to the urban construction archives and the construction unit for archiving.

  7. Anonymous users2024-02-02

    Keep the items, send things, and watch the boss's arrangement.

  8. Anonymous users2024-02-01

    Summary. Thank you for your patience and happy to answer for you. It is good for the construction unit to be a data clerk, if you hold a learning attitude to do a data clerk, you will have a great harvest, but it is only an expedient measure to do a data clerk on the construction site, and it can not be used as a career direction in the future.

    How about the construction unit as a data clerk.

    I hope the above can help you, I wish you a happy life, if you are satisfied with the answer, please kiss and give a thumbs up at the end of the session, thank you, <>

    Your thumbs up are the greatest affirmation of me) <>

    Thank you for your patience and happy to answer for you. It is good for the construction unit to be a data clerk, if you hold a learning attitude to do a data clerk, you will have a great harvest, but it is only an expedient measure to do a data clerk on the construction site, and it can not be used as a career direction in the future.

  9. Anonymous users2024-01-31

    The information clerk on the construction site is mainly responsible for the following tasks:

    1.Responsible for the collation, archiving and management of engineering data and documents, including construction drawings, engineering plans, foot-round preparation materials, contract agreements, and records of the construction site of the mausoleum.

    2.Responsible for the compilation, cavity change and archiving of the bill of quantities, including the statistics, measurement, calculation and verification of the engineering quantity.

    3.Responsible for the preparation and submission of relevant records and reports for safety monitoring and quality assurance, including safety production records, quality inspection reports, project acceptance reports, etc.

    4.Responsible for the monitoring and recording of project progress, including progress control, timing and tracking of construction sites, project nodes, and project stages.

    5.Responsible for the sorting, preservation and archiving of engineering files, including the archiving and management of on-site data, reports, engineering certification materials and other materials.

    6.Responsible for the update and maintenance of engineering data, to ensure the accuracy, completeness and reliability of all data in the construction process.

    7.Assist in handling administrative matters and work coordination on the site, including customer communication, material procurement, coordination arrangements, etc.

Related questions
10 answers2024-04-20

1. The material of the dancing wood floor.

The wooden floor of the dance is too slippery, and the performers are easy to fall, and they are too astringent and do not use the dance steps. Create a moderately moist dance wood floor for dancers. In terms of material, high-quality solid wood flooring is selected, and the surface of the floor has undergone special and delicate treatment, as long as the pier cloth is gently wiped. >>>More

5 answers2024-04-20

Pay attention to these points when losing hair, one is to cut your hair short immediately, which can reduce the friction area of external forces and avoid hair loss. The second is to change to a neutral shampoo or not to use shampoo, but to add a spoonful of vinegar to the water when shampooing, which is conducive to hair fixation. The third is to use your fingers to massage your head every day, don't use a comb, because the hair roots are already unstable and easy to comb out. >>>More

13 answers2024-04-20

Personally, I think that the choice of copy trading and business is not based on personal preference. It depends on your own level and where you are in your career, as well as the products you make. Let's say you're making a consumer product, and you're trained to try to start with your business because it's easy to get started. >>>More

18 answers2024-04-20

I'm ready to pass it on to you. The Internet speed is a bit slow, wait a minute, there are many students who use the school Internet now.

5 answers2024-04-20

Regardless of the benefits, as long as you treat each other sincerely, it is the best...Remember, people don't make friends for the sake of profit! Friendship is the most valuable