Survey at which stage of the project the tender is

Updated on Financial 2024-06-30
13 answers
  1. Anonymous users2024-02-12

    The survey and bidding are carried out during the preparatory stage of the project. The whole procedure of the project is as follows: 1. Handle two certificates and one book

    Site selection opinions, land use planning permits, engineering planning permits; 2. Handle the EIA report and apply for the approval of the environmental assessment; 3. Apply for pre-examination of construction land and obtain approval; 4. Prepare a feasibility study report.

    5. Apply for feasibility study report.

    Review and project approval; 6. Prepare the design task book, prepare the geological survey report (and organize the review), the construction plan design and the preliminary design and organize the design review; 7. Apply for approval of construction plan; 8. Prepare design budget estimates and declare budget estimates for review (commonly known as financial evaluation); 9. Construction drawing design, organization of construction drawing review (including fire protection, lightning protection and other individual approval procedures), preparation of budget and subject matter (bidding control price.

    10. Apply for bidding for the record; 11. Carry out project bidding (including goods bidding and supervision bidding); 12. Sign construction, supervision, and goods procurement contracts, and declare the contract to the relevant agencies for the record; 13. Apply for construction planning permits.

    Public greening construction filing, construction project quality supervision and administrative supervision declaration (including white ants.

    Prevention and control, new wall materials, bulk cement, construction waste disposal, fixed fees, civil air defense fees, etc.), commencement procedures (to obtain a construction permit.

    14. Measuring the elevation of the control point of the construction site; Organize the construction party, the supervision party, and the design party to hold a technical disclosure meeting and a construction disclosure meeting; 15. Issue a notice of commencement of construction (if it is necessary to apply for approval, an application report for commencement of construction shall be prepared and submitted to the Construction Bureau for a commencement order); 16. Apply for land certificate; 17. Project management of the owner (throughout the whole process of the project); 18. Organize the completion acceptance and prepare the final account report; 19. Data archiving; 20. Handle real estate registration. 21. Project handover.

  2. Anonymous users2024-02-11

    From the start-up stage to the current covering all disciplines, including housing construction, municipal infrastructure, highways, water conservancy, at present, 3,201 bidding projects (bid sections) have been implemented bills of quantities bidding. Practice has proved that the amount of engineering.

  3. Anonymous users2024-02-10

    1.Complete the preparation of the project survey and design plan, after the preparation is completed, report to the tenderer, the report content should include the technical content of the project survey and design, the total economic investment amount, the text of the report, etc., and put forward the proposal of the right and reasonable. 2.

    Prepare project survey and design bidding documents, including the basic situation of the project, bidding requirements, bidding documents preparation requirements, bidder qualification requirements, bidding documents delivery requirements, etc. 3.Select the bidder, after research, determine the bidder who meets the requirements of the tenderer, Chang cover and sign the bidding agreement.

    4.Hold a bid opening meeting for bidding documents, conduct a public review of the bidding documents, and determine the final winning bidder according to the bidder's bidding documents and technical indicators. 5.

    After signing the project survey and design contract, the winning bidder shall actively perform the contract, organize the project survey and design work, and complete the project survey and design work in accordance with the time specified in the contract.

  4. Anonymous users2024-02-09

    Site surveys are part of the preparation requirements of the project. Construction engineering survey is a very important stage in construction, its task is to determine whether the geological conditions and natural environment of the construction project site are suitable for engineering construction, and its results provide the required engineering geology and hydrogeological data for the design and construction of single buildings, and also provide various technical services for the construction of the whole process.

    Such as foundation scheme demonstration, engineering monitoring, etc. Engineering survey work should be undertaken by the survey unit with corresponding qualifications, and work according to certain procedures and requirements, general engineering survey can be divided into three stages according to the work requirements: feasibility study survey, preliminary survey and detailed survey.

    Site survey is a bidding process that bidders must go through. In accordance with international practice, the bidder's first order is generally considered to be prepared on the basis of on-site inspection, once the first order is proposed, the bidder has no right to modify the bid, adjust the first or put forward compensation and other requirements because the site survey is not thorough, the situation is not well understood or the factors are not fully considered.

  5. Anonymous users2024-02-08

    The construction project that must be tendered refers to the construction project that has reached the statutory scope and scale and must be contracted through bidding. No unit or individual may divide the project that must be tendered in accordance with the law into parts or avoid the bidding in any other way.

    Article 3 of the Tendering and Bidding Law stipulates the scope of bidding: the following engineering construction projects within the territory of the People's Republic of China, including the survey, design, construction, supervision and procurement of important equipment and materials related to the construction of the project, shall be tendered: (1) large-scale infrastructure, public utilities and other projects related to social public interests and public safety; (2) Projects that use all or part of state-owned funds for investment or state financing; (3) Projects that use loans and aid funds from international organizations or foreign countries.

    The specific scope and scale standards of the project shall be formulated by the Huifan Development Planning Department in conjunction with the relevant departments and submitted for approval. If the law or the scope of other projects that must be tendered have provisions, follow those provisions.

    Article 49 of the Tendering and Bidding Law stipulates the legal liability for non-bidding and circumvention of bidding: if the project that must be tendered is not tendered, the project that must be tendered is reduced to zero or the bidding is avoided in any other way, it shall be ordered to make corrections within a time limit, and a fine of not less than 5/10000 but not more than 10/1000 of the contract amount of the project may be imposed; For projects that use all or part of state-owned funds, the implementation of the project or the allocation of funds may be suspended; The person in charge who is directly responsible for the unit and other personnel who are directly responsible for Shiliang shall be punished in accordance with law.

  6. Anonymous users2024-02-07

    Legal Analysis:1Tender** contract (if please**); 2.

    Determine the preliminary plan for awarding contracts (open bidding, invitation to bid, competitive bidding, direct bidding, etc.); 3.Preparation of tender notices; 4.Review by the Bidding Office (project registration, entry of the contract awarding plan, review announcement and release, etc.); 5.

    Bidder registration; 6.The bidder submits prequalification materials; 7.Pre-qualification (shortlisted if qualified, shortlisted by lottery, shortlisted by scoring, etc.); 8.

    Bidding documents (**preparation, tenderer review, bidding office approval, bidder purchase); 9.On-site survey, questioning, and answering questions; 10.Publish the limit price; 11.

    bid opening, bid evaluation and calibration; 12.Publicity of winning the bid; 13.Issuance of a notice of winning the bid; 14.

    Signing a contract; 15.Bidding for the record, contract for the record.

    Legal basis: "Measures for Bidding and Bidding for Survey and Design of Engineering Construction Projects" Article 15 The tenderer shall prepare the bidding documents according to the characteristics and needs of the bidding project. Survey and design bidding documents shall include the following:

    A) Bidding instructions;

    B) the format of the tender documents and the main contract terms;

    3) The description of the project, including the financial situation;

    4) The scope of survey and design, the progress, stage and depth requirements of survey and design;

    5) Survey and design basic information;

    6) the method of payment of survey and design fees, whether the unsuccessful bidder is compensated and the compensation standard;

    7) Bidding requirements;

    8) the criteria for the qualification of bidders;

    9) bid evaluation criteria and methods;

    10) Validity period of bidding. The validity period of the bid is the validity period of the bid documents specified in the bidding documents, which is calculated from the deadline for submitting the bid documents. The fee for the bidding documents should be limited to compensation for the cost of preparation and printing, and the tenderer shall not seek benefits through the bidding documents.

  7. Anonymous users2024-02-06

    On-site investigation is to have a detailed understanding of the site, electricity, water supply, transportation, and surrounding environment before construction, and to have a detailed reference for your own machinery, temporary facilities, and construction plans.

    The bidder surveys the site mainly to see the following aspects:

    1. The on-site traffic situation, the size of the site, whether it is unconventional, the need to increase the cost in this regard, and whether there is any impact on the entry and vertical transportation of the material yard.

    2. The amount of on-site precipitation (if it is in the field) and the required precipitation equipment.

    3. Whether the surrounding buildings or places have an impact on the construction, whether measures are taken to reduce noise and prevent dust.

    4. Whether temporary housing, accommodation and office space can be erected on site.

    5. If it is a fine decoration or installation project, it depends on the completion of the civil engineering, whether there is anything inconsistent with the construction drawings, such as whether the wall can bear the load and wait.

    In a word, it is to fully understand the on-site situation and consider the influencing factors for the first and future construction.

  8. Anonymous users2024-02-05

    Have a detailed understanding of the site, electricity, water supply, transportation, and surrounding environment, and have a detailed reference for your own machinery, temporary facilities, and construction plans.

  9. Anonymous users2024-02-04

    The three links and one level of the site, the local material ** situation. Whether the topography matches the drawings. Key considerations of factors that have an impact on bidding**.

  10. Anonymous users2024-02-03

    It should be surveyed whether the five links and one level are consistent with the bidding documents.

  11. Anonymous users2024-02-02

    Surrounding environment, on-site conditions, distance from bordering buildings, on-site water and electricity, etc.

  12. Anonymous users2024-02-01

    Answer]: a, c

    1. The opening of bids for engineering survey and design bidding shall be made public at the same time as the deadline for submitting bidding documents determined in the bidding documents.

    2. The bid opening shall be presided over by the tenderer and all bidders shall be invited to participate.

    3. When opening the bid, the sealing of the bidding documents should be checked first, and then the bid should be opened in public in accordance with the prescribed bid opening order, and the name of the bidding project, the name of the bidder, the submission of the bid deposit, the bidding **, the person in charge of the project, the service period of the survey and the design and other contents.

    4. If electronic bidding is adopted, the bidder will decrypt the submitted electronic bidding documents through the electronic bidding and bidding trading platform, publish the above content of Yu Yan, and record it.

    5. If the bidder has any objection to the bid opening, it shall be raised at the bid opening site, and the tenderer shall reply on the spot and make a record.

  13. Anonymous users2024-01-31

    Answer]: a, b, c, e

    This question examines the bidding process of engineering survey and design. The main links of engineering survey and design bidding are: issuing a tender notice or issuing an invitation to bid; The bidder is prequalified and rushes to Li Hao; Preparation and sale of tender documents; Organize site surveys, etc.

    Option D: Preparation and sale of tender documents is part of the tender stage.

Related questions
7 answers2024-06-30

1. Infrastructure projects related to social public interests and public safety. >>>More

5 answers2024-06-30

The quantity of projects, goods and services estimated by the tenderer in the bidding documents shall meet the standard that the general contractor cannot determine. >>>More

9 answers2024-06-30

In addition to the funds**, the bidding scope and scale standards of engineering construction projects are stipulated. >>>More

11 answers2024-06-30

As an innovative bidding method, electronic bidding is the product of the combination of traditional bidding and modern information technology, and is a major reform of the traditional bidding method. Electronic bidding and bidding is to further standardize bidding activities, to promote the healthy development of the whole industry of the inevitable trend, electronic bidding system construction can focus on Beijing Zhulong, as a professional intelligent bidding procurement construction and operation service provider, has been for China Merchants Group, Dongfeng Consulting and other central enterprises, state-owned enterprises to provide efficient, safe and advanced electronic bidding procurement system. >>>More

8 answers2024-06-30

Whether the tentative pricing project needs a second bidding depends on the conditions that do not belong to the second bidding, and the specific conditions are as follows: >>>More