Under what circumstances will the workshop be renovated to go through the EIA procedures?

Updated on society 2024-08-12
4 answers
  1. Anonymous users2024-02-16

    Projects that have already been approved for EIA need to be re-submitted for EIA approval when there are changes.

    Scale: 1Increased production capacity.

    Construction site: 2project relocation; Adjustments in the vicinity of the original site (including changes in the general layout) have resulted in the addition of environmentally sensitive points within the protective distance of the atmospheric environment.

    Production process: 3Feedstock changes lead to new pollutant items or increased emissions.

    4.New process equipment or production process changes due to changes in auxiliary materials or products, resulting in new pollutant items or increased pollutant emissions.

    5.New pollutant items or pollutant emissions increase due to fuel changes.

    Handle the environmental impact assessment to find Shenyang Qingcheng ecological and environmental protection.

    Environmental protection measures:

    6.Changes in wastewater and waste gas treatment processes or treatment scales, resulting in new pollutant items or increased pollutant emissions (except for the change of fugitive emissions of waste gas to organized emissions).

    7.The height of the exhaust cylinder at the main discharge port is reduced by 10% or more.

    8.new wastewater outlets; Wastewater discharge is diverted to irrigation or land use, or from indirect discharge to direct discharge; Adverse environmental impacts are exacerbated by changes in the location of direct outlets.

    9.The increase in the type or amount of solid waste and the insufficient self-disposal capacity, or the change of solid waste disposal method from outsourcing to self-disposal, or the change of self-disposal method, resulting in the aggravation of adverse environmental impacts.

  2. Anonymous users2024-02-15

    Expansion of production, major changes in equipment, new pollution, etc.

  3. Anonymous users2024-02-14

    Legal Analysis:1If you only need the EIA report form, the enterprise can fill it out independently, and there is basically no cost; Preparation of an EIA report if required.

    The EPA will recommend several qualified assessment agencies to help complete the preparation of the report and the work of the EIA, and the selection of the EIA agency will incur costs.

    2.The cost of choosing an EIA agency to sign a contract generally depends on the amount of investment.

    3.The EIA agency comes to inspect the site, and the company provides all the information and details required in the EIA (production process).

    Details of various raw materials used, annual consumption, storage methods, waste disposal methods, raw material composition, etc. In addition, whether there is noise and how to solve it; Is there industrial wastewater and how to deal with it; Whether there is any exhaust gas harmful gas and how to deal with it; Whether there is waste residue and how to deal with it; how to deal with various industrial wastes, etc.; )。

    4.According to the various equipment, raw materials and auxiliary materials used in the project, the EIA agency shall prepare the specific content of the air environment testing around the project location before the start of construction (such as noise, odor concentration, and non-methane total hydrocarbons).

    VOCs, etc.), testing frequency (testing for a few days, testing several times a day, etc.), testing points (several testing points are set up around the factory), and the enterprise takes the testing content issued by the EIA agency to the environmental monitoring station or third-party testing agency.

    Request a test. 5.After getting the test report, hand it over to the EIA agency.

    6.Take the ** lookup form from the EIA agency.

    Go to nearby residents' homes and surrounding enterprises and institutions.

    To conduct a household survey, the EIA agency will have certain requirements for the number of survey copies, and the survey results can be returned to the EIA agency.

    7.If hazardous waste will be generated in the production process, a contract should be signed with the corresponding environmental protection treatment enterprise.

    8.The commissioned EIA agency prepares the EIA report; Carry out project information publicity (newspaper, Internet); Organize expert review meetings; revise the EIA report based on expert opinions; The revised EIA report shall be submitted to the Municipal Assessment Center, and the Assessment Center shall issue a technical assessment report; The environmental protection bureau of the district will approve it, and finally the environmental protection bureau will issue an approval document, and the project can be developed and constructed.

    9.Started construction and put the project into production.

    10.After the project is in normal production, apply for environmental protection acceptance at the environmental monitoring station in the district.

    11.After passing the acceptance, the entire EIA process is over, and if the acceptance is unqualified, it will be rectified again until it is qualified.

  4. Anonymous users2024-02-13

    Legal analysis: After the environmental impact assessment document of the construction project is approved, if there is a "major change" in the nature, scale, location, production process adopted or measures to prevent pollution and ecological damage of the construction project, the construction unit shall re-submit the environmental impact assessment document of the construction project for approval.

    Legal basis: Article 24, Paragraph 1 of the Environmental Impact Assessment Law of the People's Republic of China After the environmental impact assessment document of the construction project is approved, if there is a "major change" in the nature, scale, location, production technology adopted or measures to prevent pollution and prevent ecological damage of the construction project, the construction unit shall re-submit the environmental impact assessment document of the construction project for approval.

Related questions
20 answers2024-08-12

Lin is flammable in the following situations:

1.Temperature: The ignition point of the lin is low, generally around 40 degrees, and if it is hot in summer, it may spontaneously combust when placed in the sun. >>>More

4 answers2024-08-12

Under what circumstances can the property be frozenPersonal property is personal property, but sometimes the court can freeze the property. >>>More

5 answers2024-08-12

The crime of bigamy refers to the act of marrying another person while the perpetrator has a spouse, or marrying another person knowing that he or she has a spouse. >>>More

17 answers2024-08-12

The service attitude of the takeaway guy last time was really bad. >>>More

5 answers2024-08-12

What do you call it in Chinese? ”

what(h)wɔt] >>>More