-
Elevation, space point, building line.
-
Hello dear, the following engineering survey results should be inspected by the project supervision agency, including the potato plane control survey results, elevation control survey results, scale topographic map, line survey results, pipeline survey results, deformation measurement results, construction survey results and underwater topographic survey results. Engineering Surveying Technology is a very comprehensive major, which has high requirements for surveying and mathematics (such as adjustment, least squares, etc.), and with the development of science and technology, this major has put forward new requirements for English and computer technology. The purpose is to cultivate high-skilled talents who master the basic theories and basic skills of surveying and can be engaged in the front-line work of various engineering surveying and cadastral surveying production, management and service.
In addition to obtaining an academic certificate, students must also obtain at least one vocational skills appraisal certificate issued by the Guokulu family when they graduate. , dear hello, I hope the answer can help you.
-
Answer]: a, b, c, d
The test point involved in this question is the main work of survey quality management of the engineering supervision unit. The main work of the survey quality management of the project supervision unit: (1) Assist the construction unit in preparing the engineering survey task book and selecting the engineering survey unit, and assist in signing the engineering survey contract; (2) Review the survey plan submitted by the survey unit, put forward the review opinions, and report to the construction unit.
When the survey plan is changed, it should be re-examined according to the original procedure; (3) Check the qualifications of the operators in the main positions of the survey site and the indoor test, and the verification of the equipment and instrument measurement; (4) Inspect the implementation of the survey plan by the survey unit, and conduct on-site inspection of the exploration and testing of important points; (5) Review the survey results report submitted by the survey unit, and if necessary, organize expert demonstration or expert review for the survey results report at each stage, and submit the survey results evaluation report to the construction unit, and at the same time participate in the acceptance of the survey results.
-
What is the most critical in the management of building construction survey technical data?
The original measurement data, original observation data and memorization items must be filled in in strict accordance with the content and format of the survey regulations, and the on-site records are clear and complete, and shall not be supplemented afterwards. The notebook must be filled in with the page number, indicating the date, start and end time, location, measurement items, observer, recorder, weather conditions and equipment used. 2. The measurement and calculation results and charts must be clearly marked, the calculation process must be clear and signed.
Incomplete measurement data that has not been reviewed, calculated and signed by Hail Fiber shall not be used. The measurement handover book must be filled in with the project name, measurement date, handover time, handover content, handover unit, and signed by the person in charge of both parties. After the measurement results are handed over, the receiving unit shall re-test and check the results data and on-site piles, and report the problems in time so that they can be dealt with in a timely manner.
-
Answer]: b, c, e
Exam questions answer early grinding case] BCE
Test Question Analysis] The focus of this question is "progress control work procedures in the design stage". The main task of progress control in the construction engineering design stage is drawing control, that is, by taking effective measures to enable the engineering designer to complete the design work of each stage of the preliminary design model, technical design, construction drawing design and so on, and submit the corresponding design drawings and instructions. To this end, the supervising engineer should review the design unit's schedule of each professional drawing plan, land code bucket and in the process of design implementation, track and check the implementation of these plans, regularly compare the actual progress with the planned schedule, and then correct or revise the schedule.
If it is found that the progress is delayed, the supervising engineer shall urge the design unit to take effective measures to speed up the progress. Therefore, the correct answer to this question is BCE.
-
Answer]: a, c, d
The knowledge points assessed in this question are the content of supervision work methods and measures in the construction project supervision planning content. Units related to construction projects mainly include: units within the construction project system; Outside the construction engineering system, the unit is oak.
Among them, the units in the construction engineering system mainly include the owner, the design unit, the construction unit, the material and equipment unit, and the fund provider.
The following monthly report format and sample text are available for your reference: Project Name Construction Unit Design Unit Construction Unit Project Overview of the Month Column reinforcement welding, binding, formwork installation and concrete pouring on the first floor of the second floor Structural beams, plate formwork installation, steel bar installation and concrete pouring on the second floor of the 22nd floor Column reinforcement welding, binding, column formwork installation and concrete pouring on the second floor of the third floor structural beam, plate formwork production and installation, steel installation and concrete pouring and smashing; 5. Installation of external scaffolding, derrick and safety net. The completion of the project image progress of this month The welding, binding, formwork installation and concrete pouring of the first floor of the building were all completed on March 18 The installation of the two-story structural beam, plate formwork, reinforcement installation and concrete pouring on the second floor of the 22nd floor were all completed on March 28 The welding, binding, column formwork installation and concrete pouring of the second floor of the 22nd floor were all completed on March 31 The production and installation of the three-story structural beam and plate formwork, the installation of steel bars and the concrete pouring were all completed on March 28; 1. In the process of electroslag pressure welding of frame column reinforcement, some parts of the welding ladle are uneven, the welding slag is not knocked off and the appearance quality is poor; 2. In the process of making and installing beams and floor slabs, some of the main reinforcement anchorage length is not enough, the position deviation and the thickness of the protective layer is not enough, and the non-standard erection of the load-bearing frame has been stopped in time; 4. The template installation is not in place, and there is slurry leakage. >>>More
The work of the hydropower supervisor is to verify the original materials such as the quality inspection report of the incoming raw materials and the construction measurement results report, inspect the use of the contractor's construction materials, components and engineering equipment, and make on-site records, check and record the on-site construction procedures, construction methods, etc., and inspect and count the daily work; Verify the results of engineering measurement and verify the qualifications of personnel in key positions; Inspect and supervise the construction safety and environmental protection measures at the project site, report to the supervising engineer in a timely manner if any abnormalities are found, check the contractor's construction log and laboratory records, and verify the original situation of the contractor's quality assessment.
1. Concrete reinforcement: Concrete reinforcement of the house is convenient for construction, saving money and time. >>>More
International express delivery is generally for personal belongings to declare entry, and the requirements are as follows: >>>More
Off-campus training institutions must go through the "School Running Permit" approved by the county-level education department, and then apply for a registration certificate or "Business License" from the relevant department according to the type to which they belong. If a branch or training center is established across counties, it is necessary to go to the county-level education department where the branch or training site is located to complete the approval procedures. >>>More