What information do you have to do for civil high rise static pile corefilling? Which inspection bat

Updated on society 2024-02-26
5 answers
  1. Anonymous users2024-02-06

    Application Form for Pile Foundation Project Inspection.

    01 inspection and acceptance records of concealed steel cage engineering;

    02 Static pile engineering site acceptance record form;

    03 Reinforcement cage inspection batch quality acceptance record'

    04 Static pile inspection batch quality acceptance record.

    05 Concrete pouring order.

    06 Technical review records.

    5 2 Static pile pressing.

    Static piles include anchor piles and other non-impact piles.

    Before construction, the appearance and strength of the finished pile (the anchor hydrostatic finished pile is generally manufactured by the factory and transported to the site for stacking) should be inspected, and the welding rod or semi-finished sulfur cement should be used for the pile.

    There should be a product qualification certificate, or sent to the relevant departments for inspection, pressure gauges and anchor specifications for pile pressing.

    and quality should also be checked. Semi-finished sulfur cement should be made every 1 0 0k g a group of test pieces.

    3 pcs). In the process of pile pressing, the pressure, the verticality of the pile, the intermittent time of the pile, and the connection of the pile should be checked.

    Jointing quality and pressing depth. Important projects should be 10 probe for the joints of electric welded piles.

    Wound examination. Structures that are subjected to reaction forces should be observed.

    After the construction is completed, the bearing capacity of the pile and the quality of the pile should be inspected.

    The quality inspection standard of anchor static pile shall comply with the provisions of Table 5, 2, 5.

  2. Anonymous users2024-02-05

    2. Pile foundation design documents and construction sources.

    drawings, including construction drawings review records, design change notices; 3. Pile position measurement pay-off diagram, including project baseline review visa form; 4. Engineering geology and hydrogeological survey report; 5. Approved construction organization design or construction plan, including changes in implementation; 6. Static pile factory certificate and product manual; 7. Summary of pile pressing construction records, including pile number diagram, final pressure value, final pressure times, etc.; 8. Inspection data of pile materials used in construction sites, including sampling of the size and material of pile end plate and pile tip, sampling inspection of prestressed steel bars and spiral bars, specification and quality inspection of welding rods, joint weld acceptance records and other summary data; 9. Completion drawing of pile pressing project (measured deviation of pile position, position of pile repair and test pile, etc.); 10. Pile quality inspection report (pile top elevation, pile top plane position, verticality deviation test results, pile integrity test report, etc.); 11. Single pile bearing capacity test report; 12. Quality accident handling records; 13. Records of construction technical measures, technical summary materials, etc. The above content is sorted out according to the problems encountered by students in their actual work, for reference, if there are any problems, please communicate and correct them in time.

  3. Anonymous users2024-02-04

    Kiss! Hello, happy to answer your <>

    Refer to the "Technical Standard for Carrier Piles" (JGJ T135-2018) This standard is made with a general inspection batch. Carrier pile foundation refers to a structural form in which reinforced concrete piles are driven into the soil layer as a foundation to achieve the effect of increasing bearing capacity, stability and shear strength. In this kind of foundation, the inspection batch is a very important link to ensure the quality and safety of the pile foundation.

    Check the diameter, elevation, verticality, axis position and other dimensions of the pile. 2.Check the mixing ratio, slump, tung burning, strength and other properties of pile concrete.

    3.Check the diameter of the reinforcement of the pile body, the degree of the bending wheel, the depth of embedding, and the virtual layer of reinforcement protection. 4.

    Inspection of the size, position, inclination of the prefabricated hole in the pile top, etc. In the process of inspection and batching, it is necessary to implement it in strict accordance with the relevant specifications and standards according to the specific engineering situation to ensure that the indicators of the pile foundation meet the requirements. At the same time, for some special circumstances, corresponding tests and inspections are also required to ensure the safety and stability of the pile foundation.

    Hope mine can help you <>

    Do you have any other questions?

  4. Anonymous users2024-02-03

    Project Overview Table.

    Construction permits.

    Commencement report. As-built report.

    Construction logs. Engineering and technical documents submitted for review.

    Drawings will be reviewed and design will be disclosed.

    Design changes. Design change negotiation record (design change document).

    Construction organization design.

    Engineering Positioning Survey Records.

    Concealed Works Inspection Records.

    Intermediate check handover records.

    Static pile hammered pile construction record.

    Low strain test report.

    Static load test report.

    High strain test report.

    Other test reports such as horizontal deviation test report of engineering pile.

    Pipe pile certificate and inspection report.

    Welding electrode certificate.

    Pile foundation acceptance record form.

    Foundation and Foundation Division (Sub-Division) Quality Acceptance Record.

    Itemized Quality Acceptance Record Form.

    Engineering inspection batch quality inspection record form.

    Quality Supervision Opinion Sheet.

    Self-assessment report. Supervision evaluation report.

    Survey and design assessment report.

    Acceptance meeting minutes and sign-in sheets.

    Pile body sample drawing, pile location map.

    As-built drawings of the piles.

    Proofreading report.

  5. Anonymous users2024-02-02

    2. Pile foundation design documents and construction drawings, including construction drawings review records and design change notices;

    3. Pile position measurement pay-off diagram, including project baseline review visa form;

    4. Engineering geology and hydrogeological survey report;

    5. Approved.

    Construction organization design.

    or construction plans, including changes in implementation;

    6. Static pile factory certificate and product manual;

    7. Summary of pile pressing construction records, including pile number diagram, final pressure value, final pressure times, etc.;

    8. Inspection data of pile materials used in construction sites, including sampling of the size and material of pile end plate and pile tip, sampling inspection of prestressed steel bars and spiral bars, specification and quality inspection of welding rods, joint weld acceptance records and other summary data;

    9. Completion drawing of pile pressing project (measured deviation of pile position, position of pile repair and test pile, etc.);

    10. Pile quality inspection report (pile top elevation, pile top balance plane position, verticality deviation test results, pile integrity test report, etc.); Shengchang.

    11. Single pile bearing capacity test report; 12. Quality accident handling records; 13. Records of construction technical measures, technical summary materials, etc.

Related questions
16 answers2024-02-26

Civil construction, right? What civil engineer? It's too big. >>>More

13 answers2024-02-26

The steel structure swimming pool is good, which is the trend.

10 answers2024-02-26

On the second floor, the view is poor, the downstairs in and out of the car is noisy, the lighting and ventilation are relatively poor, the floor drain is easy to return to the smell, and the first two years are easy to return to the moisture, relatively speaking, it is cheap. >>>More

11 answers2024-02-26

Regarding the provisions on external wall insulation and fire protection, the external wall insulation must be made of Class A fireproof materials (in the past, it was stipulated that Class A materials should be used as fireproof isolation belts). What you're talking about is the construction step, and it has little to do with fire prevention. The construction method you mentioned is to make a thin plastering and insulation system, as well as curtain wall type and built-in mold type. >>>More

13 answers2024-02-26

Friends, you can only use the cable from the 5th floor to the bottom floor to charge the motorcycle, fix the socket on the bottom floor to put the position of the bicycle, in order to prevent others from stealing electricity, then add a switch on the 5th floor. The only other thing you can do is to take the battery of the dismantled motorcycle upstairs to charge it.