Procedures for applying for transformers for construction electricity, and what procedures are requi

Updated on Financial 2024-03-20
6 answers
  1. Anonymous users2024-02-07

    Now the declaration in the electricity service hall (fill in the form - you declare the transformer capacity, load type, etc.), - and then wait for approval, the following documents need to be provided:

    Users who apply for high-voltage new installation (capacity increase) need to provide the following information:

    General customers: business license, tax registration certificate, state-owned land use certificate, legal person ID card within the validity period.

    Copies of power of attorney, ID card of the authorized person, organization code, etc., and account opening permit.

    A copy of the approval document of the electrical engineering project. Geographical location map and floor plan of the electricity consumption area. Electricity load (including terminal planning).

    The necessity of security power and dual power supply. Main product varieties, output and production shifts. The main production equipment and production processes allow interruptions in the power supply time.

    Floor area, floor area and planned completion period. Provide the "Construction Land Planning Permit".

    Construction Project Planning Permit

    or "Opinion on Site Selection of Construction Projects". Households with increased capacity are required to provide a copy of the electricity bill of the previous month.

    Work Safety License".

    Work Safety Supervision Bureau), "Project License" (***.

    "EIA Report" (mainly produced by high-risk users).

    Special customers: In addition to the above information, the following information is also required.

    1) Coal enterprises provide: mine manager safety qualification certificate, mining license.

    Copies of coal production license, safety production license, power supply notice issued by the relevant competent department, etc.

    3) Polluting enterprises are required to provide relevant certificates issued by environmental protection authorities.

    4) Petroleum and chemical industry need to provide relevant certificates issued by the fire department.

    Please refer to the Customer Service Guide for details.

    Account name: the name on the user's official seal, and the invoice name must be consistent with the name on the seal.

    The term is half a year).

    Industry classification: According to the business license, fill in the industry to which the unit belongs, such as construction, manufacturing, etc.

    Nature of load: general or significant load.

    Production shifts: 1 shift (8 hours a day), 2 shifts (16 hours shifts (24 hours).

    Electricity use: production, infrastructure, office electricity or others (the purpose must be specified).

    If there is more than one transformer, the list of powered equipment carried by each transformer shall be written separately, and the capacity of each transformer shall not exceed (if there is a coefficient of simultaneous use, it shall be indicated). However, the total capacity of the powered equipment shall not be too low, such as applying for a 315kVA transformer, if the capacity is less than 250kw, our unit has the right to approve the user to install a 250kVA transformer, not 315kVA. The customer name of the "Equipment Capacity Registration Form" shall be stamped with the user's seal.

    Generally, the equipment involved in the installation has a power supply bureau.

    Offer (negotiable, but it will make it more difficult to handle - you know this, because of the monopoly).

    Then after approval, the design plan will be issued - review - construction - acceptance - power transmission.

  2. Anonymous users2024-02-06

    It's clear upstairs, I also work on the power grid.

  3. Anonymous users2024-02-05

    Legal analysis: first of all, you need to go to the electricity service hall to declare and fill in the form, and then wait for approval, and the following documents are generally required to apply for the transformer: business license, tax registration certificate, state-owned land use certificate, legal person ID card, power of attorney, authorized person's identity is not cancelled, copies of the organization code, account opening permit; A copy of the approval document of the electrical engineering project. Geographical location map and floor plan of the electricity consumption area. Electricity load (including terminal planning). The necessity of security power and dual power supply.

    Main product varieties, output and production shifts. The main production equipment and production processes allow interruptions in the power supply time. Floor area, floor area and planned completion period. "Construction Land Planning Permit", "Construction Project Planning Permit" or "Construction Project Site Selection Opinion"; Households with increased capacity are required to provide a copy of the electricity bill of the previous month. "Safety Production License", "Project License", "Environmental Impact Assessment Report".

    Legal basis: Electricity Law of the People's Republic of China

    Article 1 This Law is enacted in order to safeguard and promote the development of the electric power industry, safeguard the legitimate rights and interests of investors, operators and users of electric power, and ensure the safe operation of electric power。

    Article 2 This Law shall apply to the construction, production, and use of electric power within the territory of the People's Republic of China.

  4. Anonymous users2024-02-04

    Legal analysis: 1. Allocate the capacity of the transformer according to the capacity within the company, and calculate the capacity of the transformer, 2. Make an application report according to the above situation of expansion, capacity increase, and new construction.

    3. Fill in a report (company name, tax number and other information about the enterprise) according to the situation of the power supply department, and send these materials to the business hall of the power supply department. Someone came to the scene in a week or so. The transmission should be completed within 15 working days.

    Legal basis: Regulations on the Use of Electricity**

    Article 19 The quality of power supply at the receiving end of the user shall conform to the national standards or the electric power industry standards.

    Article 20 The mode of power supply shall be determined through consultation between the two parties in accordance with the principles of safety, reliability, economy, rationality and ease of management, as well as the relevant provisions of the State and the power grid planning, electricity demand and local power supply conditions。

    In areas where public power supply facilities have not arrived, power supply enterprises may entrust units with power supply capacity to supply power nearby. Without the entrustment of the power supply enterprise, no unit shall supply power to the outside without authorization.

    Article 22 Where consumers have special requirements for the quality of power supply, the power supply enterprises shall provide corresponding electricity according to their necessity and the possibility of the power grid。

  5. Anonymous users2024-02-03

    The power supply company conducts on-site surveys to determine the power supply plan. The enterprise entrusts the design unit with design qualifications to design and supply the materials to the design unit. The design drawings must be sent to the power supply company Biyu Search for approval, and a "drawing review opinion" shall be issued.

    Organize material procurement and engineering construction, and the power supply company accepts and receives electricity.

    Article 26 of the Electricity Law.

    The power supply business institutions in the power supply business area shall have the obligation to supply power to the users in the business area in accordance with the provisions of the state; Units and individuals applying for electricity in their business areas shall not be refused to supply electricity in violation of the state's nuclear destruction regulations. Applications for new installation of electricity for repentance, temporary electricity, increase of electricity capacity, change of electricity consumption and termination of electricity consumption shall be handled in accordance with the prescribed procedures. Power supply enterprises shall announce the procedures, systems and charging standards for electricity consumption at their business premises, and provide information on user notices。

  6. Anonymous users2024-02-02

    1. Calculate the capacity of the transformer according to the capacity of the company. 2. According to the above situation, it is an application report for expansion, capacity increase, and new construction. 3. Fill in a report (company name, tax number, etc.) according to the situation of the power supply department, and send these materials to the business hall of the power supply department.

    Someone came to the scene in a week or so. The transmission should be completed within 15 working days. 4. After the on-site investigation, the "Power Supply Plan Bu Zhenjian Agreement" was issued.

    5. Send the drawings to the district bureau for review. After reviewing the drawings, the "Drawing Review Opinion" will be issued. 6. Review the qualifications and billing points of the construction unit.

    7. Sign the "Asset Maintenance Agreement".

Related questions
4 answers2024-03-20

1. The electricity used on the construction site shall comply with the provisions of the "Technical Code for Temporary Electricity Safety on the Construction Site" (JGJ 46-2003). >>>More

7 answers2024-03-20

Capacitance buck calculation method: For example, we connect a 110V 8W bulb with a 1UF capacitor in series, and when connected to a 220V 50Hz AC voltage, the bulb is lit up to emit normal brightness without being burned. Because the current required for a 110V 8W bulb is 8W 110V = 72mA, it coincides with the current limiting characteristic produced by a 1UF capacitor. >>>More

11 answers2024-03-20

How much can the maximum current of transformer 630kva be used Solution: >>>More

7 answers2024-03-20

The following materials are required for commercial electricity: >>>More

6 answers2024-03-20

If you are a customer within the service scope of Guangdong Power Grid Company, the information required for the application and installation business is as follows: >>>More