Registered paint factory method].
1. The minimum registered capital is 500,000 yuan, and the minimum first phase can be 100,000 yuan, and the rest should be in place within 2 years.
Second, the registration procedures are mainly several, industrial and commercial business license, tax registration, organization **, etc.
Third, the coating belongs to the chemical industry, it is very difficult to apply, you need to make a project feasibility study report, you need to make an environmental impact assessment report, and then you need to be approved by the Environmental Protection Bureau.
Fourth, it is best to have a ready-made chemical plant to rent first, to go through land acquisition procedures, you can generally go to the development zone of Baoding to apply for construction land, the development zone to attract investment, there are supporting incentive policies, but there are many procedures, the most important is the project report, feasibility study report, environmental impact assessment report, these are a few, it is estimated that it will not be able to do it in half a year.
Fifth, as for the production technology and formula of coatings, it is better to ask a professional.
Sixth, it is recommended that if there are funds in hand, you can go to Baoding to find out if there is a paint factory to be transferred, now the economic situation is not good, and the construction industry is also sluggish, there should be a ready-made paint factory will be transferred, that will save a lot of things, not only all the above procedures do not have to be done, but also there are ready-made technical personnel.
-
1. Approve the name.
The time is 1-3 working days, and after determining the company type, name, registered capital, shareholders and capital contribution ratio, you can go to the industrial and commercial bureau to submit an application for name verification on-site or online. If the name verification is passed, if it fails, you need to bring a new verification name.
2. Submit materials.
The time is 5-15 working days, after the name verification is passed, confirm the address information, executive information, business scope, and submit a pre-application. **After the pre-trial miracle is passed, go to the industrial and commercial bureau to submit the application materials according to the appointment time. Receipt of a notification of approval for registration of establishment.
3. Obtain a license.
On the day of the appointment, bring the notice of approval of establishment registration and the original ID card of the person handling it, and go to the industrial and commercial bureau to collect the original and copy of the business license and receive the business license.
-
The procedures that need to be handled by the paint factory are as follows:
1. Industrial and commercial registration: First of all, you need to go to the industrial and commercial bureau to handle industrial and commercial registration and complete the company's registration process.
2. Apply for industrial product production license: According to national regulations, the production of coatings needs to apply for an industrial product production license, which can be applied to the local Bureau of Quality and Technical Supervision.
3. Environmental protection approval: In the process of coating production, waste water, waste gas, noise and other pollution will be generated, so environmental protection approval is required, and you can apply to the local environmental protection bureau.
4. Safety approval: There are potential safety hazards in the coating production process, and safety approval is required, so you can apply to the local safety supervision department.
5. Fire approval: A large number of flammable and explosive materials need to be used in the production process of coatings, so fire protection approval is required, and you can apply to the local fire department.
6. Tax registration: After completing the industrial and commercial registration, you need to register with the tax bureau for subsequent tax declaration and tax payment.
7. Bank account opening: After completing the tax registration, you need to open a bank account in a local bank to facilitate the subsequent flow of funds.
8. Equipment installation and commissioning: purchase coating production equipment and install and debug it to ensure the normal operation of high-security equipment.
-
It is necessary to apply for the "Hazardous Chemicals Business License" in advance. The materials that need to be provided are:
Enterprise legal person and shareholder: copy of ID card, 2 one-inch **, business site address, "Safety Management System", "Safety Production Responsibility Letter" and "Accident Emergency Rescue Plan" signed with the township (street)** where it is located, etc.
Materials to be submitted for business license:
Hazardous Chemicals Business License", the original and copy of the identity certificate, the copy of the real estate certificate, the original and copy of the lease contract, the proof of the consent of the interested owner if the business premises are residential as stipulated in Article 77 of the Property Law, the registration application signed by the applicant, and the recent one-inch bareheaded **1, etc.
-
What is the approximate annual output? According to different output, the equipment is different.
Specific equipment can be divided into two types:
1.Complete sets of equipment: reactors, pipelines, platforms, and auxiliary tanks are requiredSingle equipment: sand mill, mixer, etc.
In the second case, the cost can be slightly lower.
Needless to say, when the factory and workers arrive, we must prepare for these:
1. The more operating funds, the better.
2. Qualified paint formula, don't play without this thing, of course, you can also hire a senior engineer 3. Sufficient raw material resources, to be stable, not swaying.
4. Sufficient equipment.
5. Legal procedures.
With these can be produced!
It is also needed: 1. The marketing team, at least an experienced coating professional sales staff should lead it, otherwise it is useless to produce it and sell it.
2. Packaging design and canning factory contact.
3. Data design.
4. Sales policy setting.
5. Submit the inspection report to the Quality Supervision Bureau.
-
The premise is that you have to have the funds for a land license and most importantly for environmental quality system certification.
-
Procedures required to run a paint factory:
1. Licenses for the establishment of the company (industrial and commercial business license, tax registration certificate, etc.) 2. Factory, land, land-related licenses (land use certificate, etc.) 3. Before construction, it is necessary to find a design institute to make a feasibility study report, and then go to the first to go through the project approval procedures (economic and information bureau or ***), and then entrust a qualified unit to do environmental assessment, safety assessment, job assessment, and expert review.
4. After completing the above, find the design institute to come out with the preliminary design and pass the review (including fire protection design review) 5. The design institute will issue the construction drawings.
6. Find the construction unit and construct according to the drawings.
7. After the construction is completed, the trial production (environmental protection bureau trial production application, etc.) 8. Fire protection acceptance.
9. During the trial production period, environmental protection acceptance, safety assessment acceptance, job evaluation acceptance 10, and safety production license are obtained.
11. Officially put into production.
-
There are a lot of procedures, such as air, noise, and environment.
-
Specific equipment can be divided into two types:
1. Complete sets of equipment: reactors, pipelines, platforms, and auxiliary tanks are required.
2. Single equipment: sand mill, mixer, etc.
In the second case, the cost can be slightly lower.
Needless to say, when the factory and workers arrive, we must prepare for these:
1. The more operating funds, the better.
2. Qualified paint formula, don't play without this thing, of course, you can also hire a senior engineer.
3. Sufficient raw material resources should be stable and not swaying.
4. Sufficient equipment.
These include processes such as bleaching and refining (vegetable oil), resin synthesis and lacquering. Due to the limitations of technical strength and economic conditions, most of the resins required for coatings are provided by professional manufacturers. Large-scale paint factories generally produce most of the resins and paints by themselves, and a small part of them are purchased from professional production factories in order to improve product quality, enhance market competitiveness, and obtain maximum benefits.
-
Industrial and commercial business license, tax registration certificate, land use certificate, environmental protection bureau trial production application, fire protection acceptance, etc.
1. Industrial and commercial business license.
A business license is a certificate issued by the administrative authority for industry and commerce to industrial and commercial enterprises and self-employed persons to allow them to engage in a certain production and business activity. The format shall be uniformly prescribed by the State Administration for Industry and Commerce. Its registration items are:
Name, address, person in charge, amount of funds, economic composition, business scope, business mode, number of employees, business period, etc.
2. Tax registration certificate.
The tax registration certificate is a registration certificate issued by a taxpayer engaged in production or business operation when he or she declares for tax registration with the competent tax authority of the place of production or business operation or the place where the tax liability occurs.
3. Land use certificate.
The land use certificate is a legal document that confirms the right to use the land. The content of land registration and the style of land ownership certificate shall be uniformly prescribed by the land administrative departments. The data and numbers in the certificate, such as the name of the unit, the number of land, the location, the change of land, etc., must be consistent with the land registration form.
The attached map of the land use certificate can be obtained according to the base map of the current land use status or the thorough drawing of the cadastral map.
4. Application for trial production of the Environmental Protection Bureau.
Trial production is a report that requires the environmental protection department to approve production before formal production, and it is necessary to apply for environmental protection acceptance in formal production.
5. Fire acceptance.
Fire protection acceptance refers to the fire department of enterprises and institutions when the completion of the fire inspection of the qualified investigation, the construction unit for fire protection acceptance needs the fire bureau to carry out safety inspection, at the same time need to issue electrical fire inspection certificate, electrical fire inspection has been included in the Ministry of Public Security in the fire acceptance of the compulsory inspection of the project.
-
1. Site selection - generally there must be an opinion (now ** has a plan, most of the chemical plants are in the chemical industrial park).
2. Project approval - the chemical design institute needs to prepare the "feasibility study report" and submit it to *** for approval 3. EIA - find an EIA company to prepare the "EIA report" and submit it to the Environmental Protection Bureau for approval of the project land approval - land.
4. The safety pre-assessment report (completed by the safety assessment company) shall be submitted to the Safety Supervision Bureau for approval 5. The design of the chemical plant (the work completed by the chemical design institute).
Preliminary design. Compile the "Special Article on Safety Facility Design".
Construction drawing design.
Construction drawing design and review - third-party drawing review, meteorological bureau, fire protection 6, construction unit.
Acquisition of construction permits - land planning department.
Construction - Quality Supervision Station.
Completion acceptance and handover of as-built data - almost all of the above departments require a production license - depending on your product.
The above specific requirements are different for each place, consult the relevant departments in detail, and please correct if there is something inappropriate.
I am from the Chemical Design Institute, and I have Class A qualification for engineering design in the chemical, construction and other industries. Undertake all kinds of chemical plant design, paint plant design, ink plant design, resin plant design, oil depot (chemical depot) design, gas station and civil construction engineering design, etc. It has the qualifications to compile the "Feasibility Study Report", "Safety Facilities Design", "Fire Protection" and so on.
It is suitable for the design and consulting business of small and medium-sized enterprise engineering projects such as new construction, expansion, relocation, and transformation!
What procedures are required for the above factories, welcome QQ (851392928) or call (18666090322) for consultation.
If you have the right to a property or have a legal lease contract, you can apply for a business license. The Administration for Industry and Commerce does not care whether the building is temporary (5 years) or permanent (50 years). It is impossible to allow you to operate for 5 years without a business license, nor will it be that you will not be allowed to do it without a permanent building, and if you are not allowed to do it, you will not be managed and you will be allowed to operate without a license. >>>More
Applying for a business license is divided into three steps, the first step is the name pre-approval, that is, the name of the enterprise to be established, and its name needs to be pre-approved. After the name pre-approval is approved, the second step is to submit the information for the business license to the industrial and commercial registration authority. The materials to be submitted include the "Application for Registration of Company Establishment", the articles of association signed by all shareholders of the company to be established, the identity certificates of the shareholders, the employment documents and copies of the ID cards of the directors, supervisors and senior officers, the certificates of the designated representative or the entrusted person, the ID card of the person and its copy, and the certificate of use of the company's registered address. >>>More
The process of applying for an individual business license and an enterprise business license is as follows: >>>More
ID card and photocopy (temporary residence permit and photocopy are also required for foreigners). >>>More
There is no need to pay tax to apply for a business license for aquaculture. >>>More