Collect project bidding information - report to the leader to review the project information - purchase the bidding documents - organize personnel to prepare the bidding documents, including personnel and qualifications, and report to the leadership for review - review the bidding documents after the preparation - deliver the bidding documents before the bidding deadline.
Notice of winning the bid - signing the contract - appointing the project leader - organizing the supervision personnel to enter the site - organizing the supervision project inspection and inspection - the assessment of the project leader.
-
Project supervision does not necessarily need to be tendered. The project supervision that needs to be tendered is as follows:
1. Large-scale infrastructure, public utilities and other projects related to social public interests and public safety;
2. Survey, design, construction, supervision and procurement of important equipment and materials related to engineering construction.
What conditions should be met for supervision bidding.
The conditions that should be met for supervision bidding are as follows:
1. If the preliminary design documents shall be subject to examination and approval procedures, they have been approved;
2. The construction funds have been implemented;
3. The project legal person or the institution undertaking the project management has been established in accordance with the law.
Legal basis: Article 3 of the Tendering and Bidding Law of the People's Republic of China.
Bidding must be carried out for the following engineering construction projects within the territory of the People's Republic of China, including the survey, design, construction, supervision of the project, and the procurement of important equipment and materials related to the construction of the project
1) Large-scale infrastructure, public utilities and other projects related to the public interest and public safety;
2) Projects that use all or part of state-owned funds for investment or state financing;
3) Projects that use loans and aid funds from international organizations or foreign countries.
The specific scope and scale standards of the projects listed in the preceding paragraph shall be formulated by the development planning department in conjunction with the relevant departments and submitted for approval.
If the law or the scope of other projects that must be tendered have provisions, follow those provisions.
-
Summary. Dear, hello, no, you can't bid your own supervision. Regulations on the implementation of bidding and bidding:
Article 13 of the tendering agency in its qualification license and the tenderer entrusted within the scope of the bidding business, no unit or individual shall illegally interfere. The bidding business of the bidding agency shall comply with the provisions of the Bidding Law and these Regulations on the tenderer. The bidding agency shall not bid or bid in the bidding project, nor shall it provide consultation to the bidders of the bidding project.
The bidding agency shall not alter, lease, lend or transfer the qualification certificate.
Hello, I have seen your question, and I am sorting out the answer, please wait for a while, hello, hello, you can't bid for your own supervision. Regulations on the implementation of bidding: Article 13 of the bidding agency in its qualification license and the tenderer entrusted to carry out the bidding business, no unit or individual shall illegally interfere.
The bidding business of the bidding agency shall comply with the provisions of the Bidding Law and these Regulations on the tenderer. The bidding agency shall not bid or bid in the bidding project, nor shall it provide consultation to the bidders of the bidding project of the distribution chain. Bidding institutions shall not sell, alter, lease, lend or transfer qualification certificates.
-
According to the provisions of the Bidding Law, only legal persons or other organizations have the right to cast land bids with codes. Since a branch office does not have an independent legal personality, it is a branch of the head office, a representative of a company in a certain place, on behalf of the head office to conduct business there, and can engage in the same business scope as the company, but its civil liability arising in the course of operating the business is borne by the company. Therefore, for projects that carry out bidding and bidding work according to the Bidding Law, for public bidding, the branch that has obtained the business license has the right to participate in the bidding as long as it obtains the authorization of the head office.
However, for inviting bids, if the invitation is from the head office, the branch cannot participate in the bidding, even if it has the authorization of the head office.
Article 25 of the Tendering and Bidding Law stipulates that the bidder is a legal person or other organization that responds to the bidding and participates in the bidding competition. If individuals are allowed to participate in the bidding of scientific research projects tendered in accordance with the law, the bidding individuals shall apply the provisions of this model on stupid bidders. Article 26 stipulates that the bidder shall have the ability to undertake the bidding project.
If the relevant provisions of the state have provisions on the qualifications of bidders or the bidding documents on the qualifications of bidders, the bidders shall have the prescribed qualifications.
-
Construction project supervision bidding can be divided into two ways: open bidding and invitation to bid.
1.Open tender.
Public bidding refers to the construction unit to invite unspecified project supervision units to participate in the bidding by means of tender announcements.
State-owned funds occupy a controlling or dominant position and other projects that must be supervised and tendered in accordance with the law, shall be entrusted with the supervision task by way of public bidding. The disadvantage of public bidding is that the workload of preparing for bidding, prequalifying and evaluating the bidding is large, therefore, the bidding time is long and the bidding cost is high.
2.Late sale bids are invited.
Invitation to bid refers to the process of inviting the construction unit to participate in the bidding by inviting the specific project supervision unit to participate in the bidding, selling the bidding documents to it, and selecting the bidder from among the bidders who meet the bidding qualification requirements in accordance with the bid evaluation methods and standards specified in the bidding documents, and signing the construction project supervision contract with the winning bidder.
Invitation to tender is a limited competitive tender, also known as selective tendering. Adopting the method of inviting bidding, the construction unit does not need to issue a bidding announcement and does not conduct prequalification (but can organize the necessary qualification review).
There are too many things to write about this, so I'll tell you about it briefly, and you should buy a book and let it go. >>>More
Offices and branches are relatively reliable, why say relative, because you have to find a company that operates on the ground, preferably for ten years, so as to have a guarantee, this part is reliable, it can definitely be open to bidding, but if you find an intermediary or an empty shell of the bag company, as soon as you come up, you will say that you can open a branch, anything, do you want to think about the lunch that falls from the sky, is there any legal risk of this kind of it, is it notorious? If you join this kind of company, can you bid for the project publicly? And will they take your money and run away? >>>More
The two different forms of organization cannot be converted from the point of view of registration.
After the company is declared bankrupt or dissolved, if the liquidation team of the company confirms that the company's existing assets and creditor's rights are greater than the debts owed and sufficient to repay all the debts of the company after clearing the company's property and preparing the balance sheet and property list, the company's liquidation team shall pay off the debts to the creditors in accordance with the statutory order. First of all, the company should pay the liquidation costs, including the expenses required for the evaluation, custody, sale and distribution of the company's property, the cost of public announcement, the remuneration of the members of the liquidation team, the fees of the entrusted certified public accountants and lawyers, and the litigation costs. secondly, pay employees' wages and labor insurance premiums; Again, pay the taxes owed; Finally, there is the repayment of other corporate debts. When settling your company's debts, you should pay attention to the following: >>>More
A branch office cannot use the construction qualification of the head office, but the head office can authorize the branch office to use its qualification to participate in the bidding. >>>More