Can anyone describe the EPC tender process?

Updated on home 2024-04-26
10 answers
  1. Anonymous users2024-02-08

    The process is as follows: for the owner, the process is: determine the project Commissioned design Organize the bidding agency Issue the bidding notice Bidder prequalification Notify the qualified bidder ** Bid Organize the pre-bid inspection Hold the pre-bid meeting Pre-bid meeting minutes and addendum Bidding and bid opening Bid evaluation, award and award.

    For contractors, the process is: track the project Select a local person Select a partner or subcontractor Prepare prequalification materials Obtain bidder qualification Purchase of bids Bid preparation Bid.

  2. Anonymous users2024-02-07

    Typical Project Bidding and Bidding Procedures:

    The owner determines the project, entrusts the design, organizes the bidding agency, issues the bidding notice, pre-qualifies the bidder, and notifies the qualified bid.

    People's ** Bidding Organize pre-bid inspection Hold pre-bid meeting Pre-bid meeting minutes and addendum Bidding and bid opening Bid evaluation

    Winning and awarding bids.

    Contractor Track the project Select local ** people Select partners or subcontractors Prepare pre-qualification materials Obtain bids.

    Person Qualifications Purchase Bids Bid Preparation Bids.

    Under the EPC project, the contractor needs to consider the design, procurement and construction of the project as a whole, and it is often the total price of the lump sum, the complexity of the work is greatly increased, and the risks assumed by the general contractor are also enormous because the general contractor bears the responsibilities of engineering design, schedule control, safety assurance, quality control and cost, so the contractor needs to carefully consider whether to bid and how, and improve the accuracy of decision-making.

    1.Preparation.

    The main tasks of the preliminary preparation include:

    1) Preparation of prequalification documents.

    2) Study the bidding documents.

    3) Decide on the overall implementation plan of the bidding.

    4) Selection of subcontractors.

    5) Determine the main procurement plan.

    6) Participate in on-site investigation and pre-bid meetings.

    2.Preparation of tenders.

    The preparation of the tender is the most critical stage of the preparation of the bid, and the bidding team mainly completes the following tasks:

    1) Tender Master Plan.

    2) Preparation of technical solutions.

    3) Design, planning and management.

    4) Formulation of construction plan.

    5) Procurement strategy.

    6) Management plan preparation.

    7) General contracting management plan.

    8) General contracting management, organization and coordination.

    9) General contracting management control.

    10) Subcontracting strategy.

    11) General contracting experience strategy.

    12) Business plan preparation.

    13) Cost analysis.

    14) Value appreciation analysis.

    15) Risk assessment.

    16) The elevation gold decision is to establish a first-class model.

    3.Completion and submission of tenders.

    1) Check and revise the tender.

    2) Handle the bid guarantee deposit business.

    3) Submission of tenders.

  3. Anonymous users2024-02-06

    What is the standard? . . Procurement tenders? Construction tenders? Design Tender ???

  4. Anonymous users2024-02-05

    EPC refers to the whole process or several stages of contracting for the design, procurement, construction and trial operation of the engineering construction project in accordance with the contract entrusted by the owner. So what project can be done for EPC bidding? Let's take a look at friends who are not yet clear!

    The EPC project general contracting model can be adopted for the following projects with clear requirements for construction scope, construction scale, construction standards and functions:

    1) Use the own funds (financing, loans) of state-owned enterprises and institutions to complete large and medium-sized projects;

    2) Financial fund construction projects (such as new construction, reconstruction and expansion of schools, affordable housing and other housing projects, municipal roads, municipal supporting facilities, etc.);

    3) Professional engineering projects with special requirements for the construction period (such as greening, lighting, etc.);

    4) The construction project adopts BIM technology or adopts the prefabricated guessing group construction method.

    For projects with high personalization requirements, complex situations, and large changes in construction requirements and standards (such as underground projects, monumental buildings, stadiums, etc.), it is not suitable to adopt the general contracting method.

    Advantages of EPC tendering.

    1.Emphasize and give full play to the leading role of design in the whole process of engineering construction. The emphasis and play of the leading role of design in the whole engineering construction process is conducive to the continuous optimization of the overall scheme of engineering project construction.

    2.Effectively overcoming the contradiction between design, procurement and construction and disconnecting each other is conducive to the reasonable connection of design, procurement and construction at all stages, and effectively realizes the schedule, cost and quality control of the construction project in line with the construction project contract, so as to ensure better investment benefits.

    3.The main body of responsibility for the quality of construction projects is clear, which is conducive to investigating the quality responsibility of the project and determining the bearer of the quality responsibility of the project.

    The above content is an introduction to "what projects can be EPC bidding", I hope these contents will be helpful to you. If you want to know more about the bidding information, please log in to the bidding network to view!

  5. Anonymous users2024-02-04

    Summary. 1. Public bidding: public bidding for all units seeking to participate in the announcement of the handling agency and procurement publicity, generally mediated by means of competitive negotiation and pricing auction, and finally the project results will be awarded to the final winning bidder.

    2. Invitation to bid: Invitation to bid refers to the bidding method in which the handling agency locks several competent bidders for a certain project, and then selects the final winning bidder among these units. 3. Competitiveness**:

    Competitive auction, also known as pricing auction, refers to the auction method in which the tenderer publishes the contract details on the national procurement network, and the purchaser retains the lowest price as the negotiated price, and the final weighing is used as the contract.

    1. Public bidding: public bidding for all units seeking to participate in the public bidding by means of the announcement of the handling authority, the public announcement of the purchase of the first purchase, and the mediation of pure knowledge by means of competitive negotiation and pricing auction is generally adopted, and the project results are finally awarded to the final winning bidder. 2. Invitation to bid:

    Invitation to bid refers to the bidding method in which the handling authority locks in several competent bidders for a certain project, and then selects the final winning bidder among these units. 3. Competitiveness: Competitiveness, also known as pricing auction, refers to the auction method in which the tenderer publishes the contract details on the national procurement network, and the merchant follows the contract details, and the purchaser retains the lowest price as the negotiated price, and the final weighing is used as the auction method of the contract.

    I'm sorry I don't understand, but can you elaborate on that?

    1. Public bidding: in the form of the charter to issue a bidding notice, to the majority of enterprises to solicit bids, bidding enterprises with reference to the bidding documents agreed in the internal shortage of Qingrong bidding, and participate in the competition, and finally negotiate to determine the way of winning the bidder. Second, directional bidding:

    It is also called designated bidding, according to the actual needs of the construction enterprise, before the tender announcement is issued, a certain number of enterprises are included in the scope of bidding, and the bidding method of directional bidding is directly issued to the enterprise. 3. Inquiry and bidding: According to the actual needs of the construction enterprise, the company will issue a separate inquiry and a rubber price bidding for the capable enterprise, and the enterprise is required to give a detailed plan according to the bidding documents for the construction enterprise to choose the bidding method.

  6. Anonymous users2024-02-03

    EPC refers to the whole process or several stages of contracting for the design, procurement, construction and trial operation of the engineering construction project in accordance with the contract entrusted by the owner.

    As the name suggests, EPC recruitment is that the owner selects a company that has the ability to meet its own requirements according to certain criteria to serve itself.

  7. Anonymous users2024-02-02

    It is through bidding that Sun Min chooses a unit that can be from design, procurement to construction, and Jian Zhi finally completes the trial operation for the handover of Xiang Kaiweimu. Generally, the total price bidding is implemented, and the quality, safety and progress management of the whole process of the project are responsible. Personal opinion, for reference only.

  8. Anonymous users2024-02-01

    Legal analysis: With the increase of the EPC model, what are the regulations on the bidding and bidding of EPC projects at the national level, and whether these regulations are understood by the public and related industries. In the design, procurement or construction within the scope of the project, if any of the items must be tendered in accordance with the law and meet the scale standards stipulated by the state, the general contractor shall be selected by means of bidding.

    The project approval, approval or filing procedures shall be completed before the contract is awarded. **In principle, the investment project shall be awarded after the preliminary design approval is completed.

    Legal basis: Article 342 of the Civil Code of the People's Republic of China: Where rural land is contracted through bidding, auction, public consultation, etc., and the ownership certificate is obtained through registration in accordance with law, the land operation right may be transferred by leasing, buying shares, mortgaging or other means in accordance with law.

  9. Anonymous users2024-01-31

    It's too complicated, and I don't have a ready-made manuscript at hand, so let's summarize it briefly. The EPC model is a contracting mode that implements the whole process or several stages of the design, procurement, construction, and trial operation of the agreed engineering construction project, which is different from the traditional contracting mode of engineering construction projects. There are many specific introductions on the Internet, so I won't say more, you can find them casually.

    First of all, it doesn't matter if the project adopts the EPC model or not. It is still the traditional separate contracting model, which requires bidding conditions before bidding.

    1. The first condition for having the bidding conditions is that the project should go to the local development and reform department or the construction administrative department to handle the project approval. Of course, you need to entrust (find) a qualified engineering consulting company to prepare a feasibility study report, depending on the different and nature of your project, to see whether it is approved or approved.

    2. As the tenderer, the bidding activities shall be organized in strict accordance with the bidding scope, bidding method and bidding organization form stipulated by the project approval department. In this regard, it is necessary to make it clear in the scope of bidding that the EPC model is used for bidding. The premise, of course, is that the necessity is fully stated in the feasibility study.

    3. Entrust the consulting engineer to provide complete preliminary design drawings of each specialty. It doesn't have to be detailed into the construction drawings.

    4. Entrust the relevant qualified bidding company.

  10. Anonymous users2024-01-30

    The process is as follows: for the owner, the process is: determine the project Commissioned design Organize the bidding agency Issue the bidding notice Bidder prequalification Notify the qualified bidder ** Bid Organize the pre-bid examination and inspection Hold the pre-bid meeting Pre-bid meeting minutes and addendum Bidding and bid opening Bid evaluation, award and award.

    For contractors, the process is: track the project Select a local person Select a partner or subcontractor Prepare prequalification materials Obtain bidder qualification Purchase of bids Bid preparation Bid.

Related questions
9 answers2024-04-26

BlackBerry ranges from the low-end 7230 to the latest 700 U.S. knife bold. >>>More

3 answers2024-04-26

Small dimple (featChoi Zhuoyan) lyrics:

I'm still looking for a lean back and a hug. >>>More

9 answers2024-04-26

Human nature is cheap, and I think that people who speak are amazing. >>>More

14 answers2024-04-26

There are five subjects in the tax accountant examination, among which "Tax Law I" is the most basic subject considered by many candidates, so what is the study method of this subject? Is it difficult? >>>More

5 answers2024-04-26

Deng Zhongxiang sorted out "Wang Zengqi's Prose Reading Notes". >>>More