What process does it take for a steel structure workshop to be built?

Updated on society 2024-04-30
6 answers
  1. Anonymous users2024-02-08

    First, the steel structure construction procedures.

    1. The construction unit shall receive the registration form of the construction steel structure project from the construction administrative department or its authorized agency.

    2. Fill in the registration form carefully according to the content and requirements of the registration form.

    3. Submit the registration form to the competent department of the construction unit for review and signing.

    4. Submit the registration form to the construction administrative department, and submit the project approval documents and construction project planning permits, land use certificates, investment licenses and capital certificates.

    Second, the steel structure construction content;

    1. The name of the steel structure workshop.

    2. Construction site.

    3. Investment scale.

    4. Funding**.

    5. The amount of investment in the current year.

    6. The scale of steel structure engineering.

    7. Commencement and completion dates.

    8. Contracting method.

    9. Preparation for the construction of steel structure projects.

    3. Main charging standards: According to the regulations of the Ministry of Finance and the Price Bureau and the "Charging License" issued by the County Price Bureau, the collection standard of urban municipal facilities supporting fees is 3% to 5% of the investment amount; The management fee for the preparation of the project quota shall be calculated and charged according to the investment amount in accordance with the provisions of the Provincial Department of Construction and the Department of Finance Qiong Jianding [2001] No. 77.

    For projects with a construction area of 7,000 m2 or more than nine floors, if there is no condition to build an air defense basement, the owner shall pay 1,300 yuan per square meter per square meter to the county civil air defense department according to the total construction area as an underground air defense unified construction fee after the owner's application for approval.

  2. Anonymous users2024-02-07

    1. The steel structure workshop needs to be applied for construction: preliminary design review (5 working days).

    1. Application form;

    2. Notice of filing or approval of the project by the Planning Commission (copy);

    3. The general plan of the planning approval plan (check the original, and the copy must be stamped with the official seal of the construction unit);

    4. Survey and design contract (copy);

    5. Preliminary design documents: two samples of elevation renderings, a preliminary design specification, a set of preliminary design drawings (including 1 general plan, 1 initial construction drawing, 1 preliminary knot drawing, 1 preliminary water drawing, 1 preliminary design drawing of strong current, 1 preliminary design drawing of weak current, 1 preliminary design drawing of HVAC, etc.), and 1 copy of the basement floor plan, 1 copy of the general preliminary drawing of water supply and drainage, and 1 preliminary design drawing of the TV broadcasting system of the residential project (there is no special initial design drawing of TV broadcasting, which can be replaced by the initial design drawing of weak current), 1 copy of lightning protection map (for projects with a building height of more than 80m), a horizontal plane map of the floor where the transfer tank (pool) is located, and 1 copy of the geological survey report.

    6. An electronic document of the preliminary design document, including a full set of preliminary drawings, design descriptions, renderings, etc.

    Second, the installation process.

    1. Steel structure installation procedure.

    Steel column installation, inter-column support installation, steel crane beam temporarily in place, roof beam, roof support, steel crane beam and other correction and fixation maintenance structure installation.

    2. Steel column installation.

    1) Due to the large weight and length of the steel column, it is impossible to make and transport it once, so it adopts the method of segmented production, on-site assembly as a whole and then hoisting, and intends to divide the steel column into two sections. The steel column is transported to the site in two sections: the lower lattice part and the upper H-shaped steel column. The weight of the steel column is about 6 tons, the height in place is about 17 meters, and the 50-ton truck crane can meet the lifting needs, supplemented by a 25-ton truck crane for lifting.

    2) The lifting adopts stand-alone rotary lifting. Before lifting, the wooden square should be padded at the position of the steel column base plate to avoid the steel column from being damaged during the lifting process. When the steel column is lifted, the crane should be hooked and rotated at the same time, so that the steel column is vertically off the ground, and the column is put into the mouth of the cup.

  3. Anonymous users2024-02-06

    The same as the factory building, planning permits and construction permits are required, and the fire protection may be a little different, depending on which type of plant you belong to!

  4. Anonymous users2024-02-05

    Go to the Construction Committee to apply for a construction permit.

  5. Anonymous users2024-02-04

    Legal analysis: 1. Application; 2. Notice of filing or approval of the project by the Planning Commission (copy); 3. The general plan of the planning approval plan (check the original, and the copy must be stamped with the official seal of the construction unit); 4. Survey and design contract (copy); 5. Preliminary design documents: two samples of elevation renderings, one preliminary design manual, one set of preliminary design drawings (including 1 general plan, 1 initial construction drawing, 1 preliminary knot drawing, 1 water preliminary drawing, 1 preliminary design drawing of strong current, 1 preliminary design drawing of weak current, 1 preliminary design drawing of HVAC, etc.); 6. An electronic document of the preliminary design document, including a full set of preliminary drawings, design descriptions, renderings, etc.

    Legal basis: Administrative Measures for the Registration of Individually-owned Industrial and Commercial Households

    Article 6: The registration items of individual industrial and commercial households include: (1) the name and domicile of the proprietor; (2) the form of composition; (3) Business scope; (4) Business premises. Where a name is used by an individually-owned business, the name shall be a registration item.

    Article 7: The name and domicile of business operators refers to the names of citizens applying for registration as individual industrial and commercial households and the detailed residential address of the place of their household registration.

    Article 8 The form of composition includes individual business and family business. Where a family is a business, the names of the family members participating in the business shall be filed at the same time.

    Article 9 The scope of business refers to the type of industry to which individual industrial and commercial households carry out business activities. Based on the applicant's application and with reference to the category standards in the Industrial Classification of the National Economy, the registration authority shall register the business scope of individual industrial and commercial households.

  6. Anonymous users2024-02-03

    Every step of the construction of the steel structure store is very professional and systematic. Of course, it is reflected in the standard of construction technology, which is to make every construction detail better. In the detailed construction process standards, mastering the key points is also the key to achieving better results in construction.

    The weight of the frame columns, beams and other components of the plant is relatively light, and the lifting can be carried out by using NK250 type 25T truck crane. The steel structure hoisting adopts the principle of "first middle, then outside, first column and then beam, first down and then up".

Related questions
7 answers2024-04-30

When buying, you need to look at whether the design and use column of the real estate certificate is residential or non-residential, and if it is a residential, submit the materials according to the normal process of buying a house, issue a certificate of qualification to buy a house, and sign the contract. >>>More

12 answers2024-04-30

1. First of all, the new owner's valid ID card certificate, and then the motor vehicle registration, transfer, cancellation, and transfer registration form. In addition to these two things, it is also necessary to prepare the original car configuration indicators. If it is a foreign household registration, a temporary residence permit is also required. >>>More

3 answers2024-04-30

According to the regulations on work-related injury insurance, the declaration of work-related injuries needs to be handled in accordance with the following regulations: >>>More

9 answers2024-04-30

For many loan buyers, the term prepayment is not unfamiliar. Many people will choose to repay the loan early in the later stage of the loan because they have sufficient funds. The specific process of prepayment is: making an appointment, submitting materials, signing the application, etc. >>>More

14 answers2024-04-30

Find"Measures for the management of pawns"Look, it's not that easy.