Can the 110KV line work after the rain after power outage maintenance?

Updated on society 2024-04-27
29 answers
  1. Anonymous users2024-02-08

    Can the 101 kV line work after a power outage? You can continue to work after the rain stops, but you can't do it when it rains, and you are afraid of connecting to electricity.

  2. Anonymous users2024-02-07

    The 110kV line can be repaired after a power outage, but it cannot be repaired during the rain, and can only be repaired after the rain stops.

  3. Anonymous users2024-02-06

    It is okay to wait for the rain to stop and then carry out the work, but not if there is water, because it is still very dangerous.

  4. Anonymous users2024-02-05

    After the power outage and maintenance of the 110kV line, I think it is necessary to wait a little longer, because there is still stagnant water, and it is easy to be afraid of leakage.

  5. Anonymous users2024-02-04

    Can the 110 kV line work after a power outage?

    The 110 kV line should not work immediately after the rain. Because of the 110 thousand volt line, even if there is a power outage, he has wind power. It is very dangerous to work in the future, but even if you have to work in the future, you should do a good job of grounding and work only after a little sunny weather.

  6. Anonymous users2024-02-03

    No, this can't, you can't do these power outages on rainy days.

  7. Anonymous users2024-02-02

    This work can definitely be repaired after the rain, because if it rains, it is not so safe, and it is more dangerous.

  8. Anonymous users2024-02-01

    Can the 110kv route work after power outage and maintenance? I think. After the power outage and maintenance of the 0kv line, it is best not to work, because it will be better to connect the dots in the future.

  9. Anonymous users2024-01-31

    Yes, you can continue to work after the power failure of the line, because the rain has stopped at this time, and there will be no safety problems in the work now.

  10. Anonymous users2024-01-30

    His can work for his lines, his power outage can be repaired and can work after that, and all of us, try not to work in the rain or there is danger.

  11. Anonymous users2024-01-29

    The line is overhauled and overhauled in a power outage, and it cannot work when it rains, because the insulation is reduced when it rains, and then it is easy to cause electric shock accidents.

  12. Anonymous users2024-01-28

    Check the circuit, don't wait until after the rain.

  13. Anonymous users2024-01-27

    Can the 110kV line work after power outage maintenance? It is best not to work after the power failure and maintenance of the 110 line. Because I am afraid that there will be any failures after the rain.

  14. Anonymous users2024-01-26

    This situation is not possible, the main reason is that he is prone to some leakage after the rain, and there are certain safety hazards in this regard.

  15. Anonymous users2024-01-25

    High-voltage lines like this need to be overhauled after the air has dried out after the rain has stopped.

  16. Anonymous users2024-01-24

    1. After receiving the power outage notice, the electrician pulls down the relevant knife switch and retracts the fuse. And lock the operating handle, and hang a warning sign at the same time, and add a protective shield around the equipment that has not yet had a power outage.

  17. Anonymous users2024-01-23

    Like the 110 kilowatts are caught in the power outage, of course it is okay to work after the rain, but you must pay attention to the insulation, do not get electrocuted.

  18. Anonymous users2024-01-22

    If it is a power outage, it can still be repaired normally after the rain.

  19. Anonymous users2024-01-21

    I suggest that you can find a professional to help you repair it, and if one of your machines is broken, you can find a professional to help you repair it.

  20. Anonymous users2024-01-20

    In the "Electrical Safety Work Regulations - Line Part", it is clearly required that the following steps must be strictly followed during power outage maintenance:

    1. Power outage. 2. Electricity test.

    3. Set up a grounding wire.

    4. Hang signs and install fences.

    It can be seen that the erection of grounding wires is an indispensable link.

    Although I don't know what the landlord is talking about, the grounding wire must still be put on, as for how to ride, there is a strict erection process. Different grounding wires have different shapes, but they all follow the steps below:

    1. Use the grounding wire that is qualified, has passed the test, and the voltage level is the same or above as the voltage level of the erection wire.

    2. The operator must wear shielding clothing and be familiar with the operation process.

    3. The transmission line must pass the electroscope to confirm that there is no electricity before setting up the grounding wire.

  21. Anonymous users2024-01-19

    No, because you don't know where it's easy to leak.

  22. Anonymous users2024-01-18

    The 110kv line can work after a power outage and maintenance.

  23. Anonymous users2024-01-17

    Does the 110 kW line outage inspection work with hook? Try not to work after the rain?

  24. Anonymous users2024-01-16

    Can this wireless line work after going in every day? This should be okay, let's learn more about some news about the rectification of power outages in the past.

  25. Anonymous users2024-01-15

    110 kV line, power outage maintenance, can work after rain.

  26. Anonymous users2024-01-14

    Generally, this kind of bank should be able to work, you can check it.

  27. Anonymous users2024-01-13

    The 110 K V line can work after power outage maintenance, but no.

  28. Anonymous users2024-01-12

    Geophysics.

    Atmospheric sciences. Marine sciences.

    Mechanics of Agricultural Engineering.

    Environmental science. Psychology and Statistics.

    Systems Science. Mining machinery.

    Instrumentation. Energy power.

    Electrical information. Civil surveying and mapping.

    Environment & Safety.

    Chemicals & Pharmaceuticals.

    Transportation. Marine Engineering.

    Aerospace. Engineering Mechanics.

    Bioengineering. Public security technology.

    Materials science. Material water conservancy.

    Forestry Engineering. Light industry, textiles, and food.

    Electronic Information Science.

    The main categories are these, and each school is divided into different small majors!

  29. Anonymous users2024-01-11

    National Catalogue of Undergraduate Majors in Ordinary Colleges and Universities:

    There are all the majors and a detailed introduction to each of them.

Related questions
2 answers2024-04-27

Hello, I am glad to answer for you (* 110kV line frame construction scheme cable laying: process: material 1 transportation, storage - cable pipe laying and cable tray installation - insulation resistance test before cable installation - cable laying. >>>More

9 answers2024-04-27

1. The difference between 110kV and 220kV power grid relay protection >>>More

11 answers2024-04-27

2 Power System Primary Part 6

Brief description of the project area 7 >>>More

7 answers2024-04-27

It is the rated voltage of the cable, it is its working voltage range, and it has nothing to do with how many square meters the cable is.

17 answers2024-04-27

In this way, you can calculate separately, the floor, whether it is in line with the wooden floor or floor tiles, the average of the work with materials (including flooring, cement mortar, and labor) is 110 yuan per square meter (of course, depending on the brick you buy**, I calculate 800 * 800 bricks 50 yuan a piece, and the wooden floor is 75 square meters); The second is the wall of 110 square meters of the house wall is about 280-290 square meters, each square meter of latex paint is calculated according to 20 yuan (but also depends on the quality of your latex paint, I count according to 330 a bucket, 18L), the line is generally not at home if there is no ceiling, do not do smart home, simple decoration is 110 square meters with 2000 is about the same. Then these three items add up to 110 * 110 + 280 * 20 + 2000 = 19,700, about 20,000, which is what you can do by finding workers or guerrillas**, and finding a company will add up to 27,000 yuan. >>>More