How to write a supervision log? How to write the supervision log supervision work content

Updated on tourism 2024-08-06
7 answers
  1. Anonymous users2024-02-15

    Remember the date. Meteorological conditions.

    1. Explain that you have been patrolling the site; 2. Contact the construction party to confirm that the operation will be stopped in rainy days (record the date and time of the shutdown); 3. Urge the construction unit to take safety precautions for construction in the rainy season. Record it.

  2. Anonymous users2024-02-14

    The supervision log supervision work is as follows:

    The first line should be clearly written the specific time of the log, the detailed weather conditions and the name of the recorder, in which, the record of weather conditions is very important, because many construction processes are greatly affected by the weather, the supervision log of this project needs to record the weather conditions of the day in detail, including the temperature of the morning, noon and evening three periods, the highest temperature and the lowest temperature of the day, the size of the wind, the amount of rainfall and so on.

    Before writing the main content, it is necessary to introduce the specific parts of the construction on the day, the number of workers, and the use of raw materials and equipment. The main content of the log should include the construction progress of the whole day, the construction process, the acceptance results of each department, the problems encountered in the construction process and the solution, if there is a meeting on the same day, it is also necessary to record the time, place and content of the meeting.

    In this, the problems encountered in the construction process and the construction process need to be emphatically written, the start and end time of each process should be recorded in the construction process, the specific process steps, the inspection and acceptance of each process, what problems are encountered in the construction process, the consequences of the problem and how the problem is solved, to record these contents need to be carefully followed up by the supervision personnel, check the process in time, judge the problems that may occur, and assist in solving the problems in a timely manner.

    The main content of the supervision log records the work of the day, and the supervisors need to make the following work arrangements according to these, which is conducive to ensuring the smooth progress of the entire construction, however, many supervisors often do not pay enough attention to this content, once there is a problem, the entire progress will be affected.

    What is a Supervision Log?

    The supervision log is the original record of the supervision of the supervision of the implementation of the supervision activities of the supervising engineer, and is an important information for the implementation of the supervision entrustment contract, the preparation of the supervision completion documents and the handling of claims, extensions and changes; It is also an important, the most original and reliable material for analyzing engineering quality problems; It is also the most basic component of the project supervision file.

  3. Anonymous users2024-02-13

    The contents of the supervision log are date, weather, etc. The supervision log often only records the time, and ignores the accuracy of the meteorological record and the quality of the project has a direct relationship, because when pouring concrete, concrete curing, early strength, demolition strength and other construction activities are closely related to the temperature, wind and rainfall, and heavy rain will affect the construction of deep foundation pit and so on.

    The content characteristics of the supervision logThe meteorological situation must be recorded clearly and in detail, the progress of the project, the distribution of construction personnel, the operation parts, the image of the progress of the rationalization of the proposals, etc., should be recorded, the construction inspection of the concealed project, the problems of construction quality and how to solve the rectification of all kinds of accidents The list of personnel, the quality of the supervision log record.

    It is necessary to record the rectification situation, whether the rectification and acceptance meet the requirements, the personnel participating in the acceptance, the causes and consequences should be recorded clearly for traceability, the sampling test of various standards in parallel, the production and testing of mortar concrete test blocks, the coordination of the day, whether there are results, and the entry and inspection of materials and equipment on the site.

  4. Anonymous users2024-02-12

    Daily image progress; the entry of materials, machinery and equipment; Supervision and inspection: the quality problems found, how to require the construction unit to rectify, the review after rectification, such as the construction unit has not rectified or refused to rectify, whether to issue a supervision notice, whether to report the matter to the construction unit.

    Extended information: engineering supervision refers to a professional service activity in which the supervision unit with relevant qualifications is entrusted by Party A to monitor the construction of Party B on behalf of Party A in accordance with the construction documents of the project approved by the state, the laws and regulations related to engineering construction and the engineering construction supervision contract and other engineering construction contracts. Engineering supervision is a kind of paid engineering consulting services; It is commissioned by Party A; The main basis of supervision is laws, regulations, technical standards, relevant contracts and documents; The criteria of supervision are law-abiding, integrity, fairness and science; The purpose of supervision is to ensure the quality and safety of project construction, improve the level of project construction, and give full play to the investment benefits.

    The construction project supervision unit is entrusted by the construction unit to control the quality, cost and progress of the construction project in accordance with laws and regulations, engineering construction standards, survey and design documents and contracts in the construction stage, manage the contract and information, coordinate the relationship between the relevant parties of the project construction, and perform the service activities of the statutory duties of construction project safety production management.

  5. Anonymous users2024-02-11

    1.The supervision log should be true, accurate and comprehensive to record the project progress, quality, safety related issues, and the wording should be accurate, rigorous and standardized.

    2.The problems that occur and the ways to solve them, the methods are recorded, which is not only easy to find, but also conducive to the owners and the competent departments to have a more comprehensive understanding of the content of the supervision work and the performance of the supervision work.

    3.Major events and major construction activities should be recorded in the supervision log, especially the safety and quality hazards existing in the construction and important suggestions and requirements for the contractor.

    4.Through years of exploration, reform, the introduction of advanced systems, China's supervision market is gradually maturing, supervision personnel should also continue to improve the quality, so that they adapt to the changing environment, supervision log filling is a side reflection of this quality.

    5.A comprehensive and detailed supervision log can not only provide convenience for the supervision work, but also be the basis for project delay and claim.

  6. Anonymous users2024-02-10

    The supervision diary is a very important supervision information, and the project supervision team must record it carefully, in detail, truthfully and in a timely manner. Before recording, the construction situation and supervision work of the day should be summarized and sorted out, so that the writing is clear, the layout is neat, the content is clear, the content is comprehensive. So, how to write a supervision work log?

    Let's take a look!

    First, the construction activities

    1. Construction site and content: the work on the key line, the work of important parts or nodes, and other work that the project supervision team considers necessary to record.

    2. Work, material and machine dynamics.

    Work: the number of operators of the main types of work on site (such as: rebar workers, carpenters, masons, scaffolding workers, etc.), and the main management personnel of the project department (project managers, constructors, quality officers, safety officers, etc.) in place.

    Materials: The entry and exit of the main materials (including components) on the day.

    Machine: refers to the number of main machinery and equipment on the construction site and its operation (whether there is a fault, and the troubleshooting time, etc.), and the entry and exit of the main machinery and equipment.

    Second, the supervision of activities

    1. Inspection: the time or number of inspections, and selectively record the important situations in the inspections according to the actual situation;

    2. Acceptance: the position, content, results and acceptors of acceptance;

    3. Witness: the content, time and witnesses of the witness;

    4. Side station: content, location, person and number of side station records;

    5. Parallel inspection: location, content, inspector and parallel inspection record number;

    6. Engineering measurement: complete the measurement of engineering quantity and change the measurement of contact content (required);

    7. Review and approval: review and approval of relevant plans, inspection batches (sub-items, processes, etc.), raw materials, schedules, etc. (It is sufficient to record the number of the audit and approval form.)

    3. Problems and solutions

    In the past day, through a series of supervision work, what problems have been found in the quality, progress, investment and other aspects of the project, and how to deal with these problems. ,: What is the result of the treatment, should be recorded in detail.

    The handling of some major quality and safety accidents should be carried out in accordance with the prescribed procedures, and the relevant information should be recorded, preserved, and sorted out in accordance with the regulations, and the records in the diary should be concise and to the point.

    4. Miscellaneous

    1. Supervision instructions (supervision notice, memorandum, rectification notice, change notice, etc.);

    2. Meetings and meeting minutes;

    3. Correspondence;

    4. Safe working conditions;

    5. Rationalization proposals;

    6. The inspection of the leading departments of the construction parties or the construction administrative departments;

    5. Duty records

    Signature of the supervisor on duty that day.

  7. Anonymous users2024-02-09

    The supervision diary is an important supervision information that is not late, and the project supervision team must record it carefully, in detail, truthfully and in a timely manner. Before recording, the construction situation and supervision work of the day should be summarized and sorted out, so that the writing is clear, the layout is neat, the organization is clear, and the content is comprehensive. According to the nature, role and years of experience of the supervision diary, our company makes the following requirements for the recording method of the supervision diary, and the project supervision team is requested to comply with the implementation.

    Here's how I write the construction supervision log, let's take a look.

    Supervision diary recording method:

    First, the construction activities

    1. Construction site and content: work on key lines, important parts or nodes, and other work that the project supervision team deems necessary to record.

    2. Work, material and machine dynamics.

    Work: the number of main types of workers on site (such as: rebar workers, carpentry, masons, scaffolding workers, etc.), and the main management personnel of the project department (project managers, constructors, quality officers, safety officers, etc.) are in place.

    Materials: The main materials (including the composition code skin stuffy parts) of the day in and out of the site.

    Machine: refers to the number of main machinery and equipment on the construction site and its operation (whether there is a fault, and troubleshooting time, etc.), and the entry and exit of the main machinery and equipment.

    Second, the supervision of activities

    1. Inspection: the time or number of inspections, and selectively record the important situations in the inspections according to the actual situation;

    2. Acceptance: acceptance position, content, results and acceptor;

    3. Witness: the content, time and witnesses of the witness;

    4. Side station: content, location, side station person and side station record number;

    5. Parallel inspection: location, content, inspector and parallel inspection record number;

    6. Engineering measurement: complete the engineering quantity measurement work, change the contact content measurement (required);

    7. Review and approval: review and approval of relevant plans, inspection batches (sub-items, processes, etc.), raw materials, schedules, etc. (The number of the relevant review and approval order can be recorded).

    3. Problems and solutions

    Over the past day, through a series of supervision work, what problems have been found in the quality, progress, investment and other aspects of the project, and how to deal with these problems. The handling of some major quality and safety accidents should be carried out in accordance with the prescribed procedures, and the relevant information should be recorded, preserved and sorted out according to the regulations, and the records in the diary should be concise and concise.

    4. Miscellaneous

    1. Supervision instructions (supervision notice, memorandum, rectification notice, change notice, etc.);

    2. Meetings and meeting minutes;

    3. Correspondence;

    4. Safe working conditions;

    5. Rationalization proposals;

    6. The leading departments of the construction parties or the construction administrative departments inspect the situation;

    5. Duty records

    Signature of the supervisor on duty on the day.

Related questions
1 answers2024-08-06

1. Do a good job of pre-control and strictly control the start of work. >>>More

7 answers2024-08-06

With the rapid development of the construction industry, the gold content of supervision engineers has also followed, especially in 2020, a series of reforms of supervision engineers in China, so is there any development prospect for supervision? What is the goal of supervision? With the question in mind, read on. >>>More

9 answers2024-08-06

Do you want to apply for the professional supervision engineer or the national registered supervision engineer? Then you have to make it clear what type and what major you are applying for? The exam is held once a year, and the exam is generally scheduled in mid-May. >>>More

12 answers2024-08-06

Supervising Engineer Exam Application Guide.

In August 1996, the Ministry of Construction and the Ministry of Personnel issued the Notice of the Ministry of Construction and the Ministry of Personnel on the National Supervision Engineer Qualification Examination (Jian Jian 1996 No. 462), and from 1997, the National Supervision Engineer Qualification Examination was officially held. The examination work is jointly responsible for the Ministry of Construction and the Ministry of Personnel, and the daily work is entrusted to the Construction Supervision Association of the Ministry of Construction, and the specific examination work is responsible for the Personnel Examination Center of the Ministry of Personnel. >>>More

15 answers2024-08-06

Responsibilities of a professional supervising engineer.