How to write a good supervision diary, how to write a good supervision diary

Updated on society 2024-03-23
13 answers
  1. Anonymous users2024-02-07

    Daily image progress; the entry of materials, machinery and equipment; Supervision and inspection: the quality problems found, how to require the construction unit to rectify, the review after rectification, such as the construction unit has not rectified or refused to rectify, whether to issue a supervision notice, whether to report the matter to the construction unit.

    Extended information: engineering supervision refers to a professional service activity in which the supervision unit with relevant qualifications is entrusted by Party A to monitor the construction of Party B on behalf of Party A in accordance with the construction documents of the project approved by the state, the laws and regulations related to engineering construction and the engineering construction supervision contract and other engineering construction contracts. Engineering supervision is a kind of paid engineering consulting services; It is commissioned by Party A; The main basis of supervision is laws, regulations, technical standards, relevant contracts and documents; The criteria of supervision are law-abiding, integrity, fairness and science; The purpose of supervision is to ensure the quality and safety of project construction, improve the level of project construction, and give full play to the investment benefits.

    The construction project supervision unit is entrusted by the construction unit to control the quality, cost and progress of the construction project in accordance with laws and regulations, engineering construction standards, survey and design documents and contracts in the construction stage, manage the contract and information, coordinate the relationship between the relevant parties of the project construction, and perform the service activities of the statutory duties of construction project safety production management.

  2. Anonymous users2024-02-06

    The supervision log is a record made by the project supervision agency on the weather and site conditions, supervision work and construction progress of the day. 1. Record the main work content and related matters of the supervision of the day

    1) Construction site inspection, side station, witness sampling, parallel inspection and supervision (including oral notice, coordination, etc.). 2) Acceptance of various processes (including measurement, pay-off, etc.).

    3) In addition to the process of the construction unit of various inspection and review situation (such as concrete pouring review, engineering materials and accessories

    Equipment inspection, construction hoisting machinery installation and dismantling review, construction plan review, subcontractor qualification review

    Progress review, project cost review and other applications).

    4) Supervision of safety production management (review of special plans and safety technical measures, on-site safety production status and correction.

    violations, etc.).

    5) Meetings convened (see minutes for details).

    6) The occurrence and handling of abnormal events (such as quality and safety accidents, suspension and resumption of work, claims, etc.).

    7) Other major work items that should be recorded.

    2. The handling of each item recorded in the log shall be closed. If there is more content in the record, you can add an additional page (on the back of **). 3. Large and medium-sized projects should be filled in by bidding sections (or areas) and specialties, and the specific division scope shall be determined by the chief engineer.

    4. The supervision log shall be prepared by the professional supervision engineer designated by the chief engineer.

  3. Anonymous users2024-02-05

    Starting from the work content of the supervision party, record the progress of the supervised project, the construction content, the construction quality, the corresponding work and effect of the supervision, and the responsibility and supervision party's suggestions and measures need to be clarified when encountering engineering problems.

  4. Anonymous users2024-02-04

    1. Beginning: Explain the specific time, detailed weather conditions and the name of the recorder, and record the weather conditions of the day in detail, including the temperature in the morning, noon and evening, the maximum temperature and minimum temperature of the day, the size of the wind, the amount of rainfall, etc.

    2. Main content: It is necessary to introduce the specific parts of the construction on the day, the number of construction personnel, the use of raw materials and equipment, the construction progress, construction technology, acceptance results of various departments, and the problems encountered in the construction process and their solutions.

    3. The next work arrangement: the main content of the supervision log records the work of the day, and the supervision personnel need to make the following work arrangements according to these, which is conducive to ensuring the smooth progress of the entire construction, however, many supervisors often do not pay enough attention to this content, once there is a problem, the entire progress will be affected.

  5. Anonymous users2024-02-03

    The journal of the superintendent should be written like this:

    1. Daily filling content: the date of the day, the weather of the day, the location and construction content of the operation, the number of workers, the main materials consumed by the main equipment operated, etc., and the main construction matters.

    2. Daily work records:

    1. During the construction process, the team conducts on-site inspection and supervision, and records the evidence when seen.

    2. The entry of main materials, operating equipment and large-scale equipment.

    3. Measurement lofting and construction acceptance in operation.

    4. Review of construction team qualification materials and final results.

    5. Design and construction drawings are disclosed and relevant matters that need special attention.

    6. The content materials and receipt records and recipient records of the notices issued by themselves.

    7. Important matters and feedback raised by the owner.

    8. The construction team will give feedback on the needs of the owners.

    9. The relevant matters determined by the regular meeting of the morning shift and the evening shift and the matters that need to be coordinated and completed.

    10. Record of major abnormal events that occur on the site and its impact on the entire construction 11. Other important matters that need special attention.

    Extended Materials. The supervision log is the original record of the supervision of the supervision of the implementation of the supervision activities of the supervising engineer, and is an important information for the implementation of the supervision entrustment contract, the preparation of the supervision completion documents and the handling of claims, extensions and changes; It is also an important, the most original and reliable material for analyzing engineering quality problems; It is also the most basic component of the project supervision file.

  6. Anonymous users2024-02-02

    Hello, the supervision log should be true, accurate and comprehensive to record the project progress, quality, safety related issues, the wording should be accurate, rigorous and standardized. The problems that occur and the ways to solve them, the methods are recorded, which is not only easy to find, but also conducive to the owners and competent departments to have a more comprehensive understanding of the content of the supervision work and the performance of the supervision work.

    Major events and major construction activities should be recorded in the supervision log, especially the safety and quality hazards existing in the construction and important suggestions and requirements for the contractor. Through years of exploration, reform, the introduction of advanced systems, China's supervision market is gradually maturing, supervision personnel should also continue to improve the quality, so that they adapt to the changing environment, supervision log filling is a side reflection of this quality. A comprehensive and detailed supervision log can not only provide convenience for the supervision work, but also be the basis for project delay and claim.

    The recording content of the supervision log should include the following points:

    1. Date and weather.

    2. Commencement, completion time and construction of unit projects and branch projects.

    3. The contractor's organizational structure and personnel dynamics.

    4. The entry and use of the contractor's main materials and equipment.

    5. The supervision unit deals with different problems.

    6. Acceptance of sub-projects, sub-divisions and unit projects.

    7. Record the problems and solutions that affect the quality, progress, cost and safety of the project, the management of contracts and residences, and the activities of supervision meetings, inspections, and random inspections.

    8. Review records.

    9. Record of key time and location.

    Extended information: the supervision log is the original record of the supervision of the implementation of the supervision activities of the supervision engineer, and is an important information for the implementation of the supervision entrustment contract, the preparation of the supervision completion documents and the handling of claims, extensions and changes; It is also an important, the most original and reliable material for analyzing engineering quality problems; It is also the most basic component of the project supervision file.

  7. Anonymous users2024-02-01

    Daily image progress; the entry of materials, machinery and equipment; Supervision and inspection: the quality problems found, how to require the construction unit to rectify, the review after rectification, such as the construction unit has not rectified or refused to rectify, whether to issue a supervision notice, whether to report the matter to the construction unit.

    Extended information: engineering supervision refers to a professional service activity in which the supervision unit with relevant qualifications is entrusted by Party A to monitor the construction of Party B on behalf of Party A in accordance with the construction documents of the project approved by the state, the laws and regulations related to engineering construction and the engineering construction supervision contract and other engineering construction contracts. Engineering supervision is a kind of paid engineering consulting services; It is commissioned by Party A; The main basis of supervision is laws, regulations, technical standards, relevant contracts and documents; The criteria of supervision are law-abiding, integrity, fairness and science; The purpose of supervision is to ensure the quality and safety of project construction, improve the level of project construction, and give full play to the investment benefits.

    The construction project supervision unit is entrusted by the construction unit to control the quality, cost and progress of the construction project in accordance with laws and regulations, engineering construction standards, survey and design documents and contracts in the construction stage, manage the contract and information, coordinate the relationship between the relevant parties of the project construction, and perform the service activities of the statutory duties of construction project safety production management.

  8. Anonymous users2024-01-31

    I'm also a supervisor, so I'll give you a total of a supervision diary for reference.

    The format of the supervision diary should be the same (main construction).

    1. The number of on-site construction personnel is about 200, and all types of work are complete. (Here we should indicate the number of workers and the type of work on site).

    Second, today's entry of 5,000 aerated blocks is fully qualified to handle the entrustment, witness the sampling and inspection.

    Entrust C35 concrete test block 3 groups with the same conditions for the main body 20 layers.

    It mainly indicates the situation of the material composition and the entry test of the components).

    3. The inspection found that there were leakage of steel bars and displacement of steel bars in the process of reinforcement clamping at the top of the 25th floor.

    A notice has been issued to require the construction unit to immediately rectify (mainly the quality and acceptance.

    Fourth, twenty-five layers of roof beam plate reinforcement binding, formwork support pipeline pre-embedding, nineteen layers of formwork removal and cleaning mold.

    slabs, three basement floors after masonry masonry masonry. (Project image progress).

    5. At 2 p.m. in the conference room of the construction site, find the regular meeting of the project supervision for details, please refer to the meeting minutes (meeting).

    Sixth, the issuance of the supervision notice on the quality of on-site construction matters see the supervision notice No**Supervision pass.

    knowledge, work contact list, etc.).

    7. The phenomenon of individual workers not wearing safety helmets has been found on the spot, and the construction unit has been required to strengthen the protection of workers.

    Education, to prevent such situations from happening, to check and sign the "Zero Work Method Diary" (security.

    civilized construction situation).

    8. Received the design change of the elevator T5 equipment room. (Drawing review, design changes).

    9. Apply for an economic visa related to drainage, and a single copy of electrical bridge materials (investment control.

    10. The supervisor of the quality supervision station came to the site to inspect and issue a rectification notice for on-site problems.

    Notification No. ** (Superior Inspection).

    Ten. 1. Review the qualification of the curtain wall construction unit (the application for the commencement of the project and the qualification review of the subcontractor.

    Ten. 2. Other records that should be recorded.

    This is based on the situation of our construction site, a diary is established, the content of the item is required in parentheses: The record of the supervision diary must first be detailed, and every bit of what happens on the site every day must be recorded.

  9. Anonymous users2024-01-30

    Like this brother upstairs notation! A page of supervision log is not enough to write, it is recommended to grasp the key points, the construction site should not be so detailed, mainly write the inspection of the supervision and inspection parts, find problems, how to deal with them, and other events related to supervision.

  10. Anonymous users2024-01-29

    What are the main contents of the project supervision diary and the monthly report of the project supervision organization?

  11. Anonymous users2024-01-28

    1. Climate.

    2. Progress.

    3. The name, quantity, origin, proposed part and witness sampling of the raw materials entering the site on the same day.

    4. Acceptance of sub-division and sub-item inspection batches.

    5. Record the project inspection form issued on the same day, the supervision work contact form, the supervision notice, etc.

  12. Anonymous users2024-01-27

    1. Supervise the content of the log.

    The content must be recorded on a daily basis; Date, weather, construction site and work content, number of workers, main equipment and materials used, etc., mark the start and completion of the main sub-items.

    The content of the daily major event record;

    During the construction process, patrol inspection and side station supervision, witness sampling.

    Materials, equipment, components and main construction machinery and equipment entry and acceptance records.

    Construction survey pay-off, project inspection and acceptance results.

    The information of the construction unit is submitted for review and the results of the review.

    Matters related to the handover of construction drawings and engineering changes.

    The main content of the supervision notice (written and oral) issued and the person who issued it and who issued it.

    Relevant matters and handling opinions put forward by the construction unit.

    Relevant matters and handling opinions raised by the construction unit.

    Relevant matters agreed upon at the site meeting and related issues identified in coordination.

    Engineering quality accidents (defects) and treatment plans.

    Abnormal events (events that may lead to claims) and their impact on the construction are related matters related to the arrival of designers on the construction site and handling and support.

    Quality supervision personnel and relevant leaders come to the site to inspect, guide the work and relevant instructions.

    Other important matters are recorded.

  13. Anonymous users2024-01-26

    The supervision diary is a running account, what is done on the site every day, what materials are entered, and what the supervision work does every day must be recorded. If you find something wrong, write it down. If something really happens in the future, it's all evidence.

    In addition, the supervision diary should be consistent with some of the contents on the construction diary.

Related questions
4 answers2024-03-23

How to write a good official document?

1. Effectively comprehend the intention of Lingming's guidance: whether you can truly understand the intention of the leader is a very important part of determining the success of official document writing; >>>More

7 answers2024-03-23

Be calm and self-confident. Psychological tension will make one's thinking suppressed, and only by being relaxed can one's thoughts flow freely. >>>More

4 answers2024-03-23

How to write a personal autobiography?

3 answers2024-03-23

We. Teachers and students from grades 4 and 5 participated in a science and technology activity organized by the school, and the destination was the Shanghai Youth Activity Center. We set off at 8:30 a.m. and took a bus for nearly half an hour to arrive at the Shanghai Youth Activity Center. >>>More

8 answers2024-03-23

1. First of all, we must have the correct attitude and the spirit of hardship and endurance, and at the same time, we must also have the determination to practice the words well. It takes time to hone a good handwriting to make it clear. >>>More