The basis for the preparation of the construction project supervision plan is: the laws, regulations and policies related to the construction of the project promulgated by the state, which is the highest level of the laws and regulations related to the construction of the project. Laws, regulations, regulations and policies related to project construction promulgated by the location of the project or the department to which it belongs.
The various standards and norms for engineering construction also have legal status and must also be observed and enforced.
Supervision planning refers to the preparation under the auspices of the chief engineer, approved by the technical person in charge of the supervision unit, used to guide the project supervision agency to carry out the supervision work in an all-round way of the guiding documents.
Supervision planning should be signed entrusted supervision contract and received after the design documents began to prepare, after the completion of the supervision unit must be reviewed and approved by the technical person in charge of the supervision unit, and should be held the first site meeting.
before reporting to the construction unit.
Supervision planning should be presided over by the chief engineer, professional supervision engineer.
Participate in the preparation. <>
-
As an indispensable and important system of engineering construction, construction supervision has been implemented in China for more than 20 years, and a large number of infrastructure projects, residential projects, industrial projects, and a large number of public construction projects have implemented compulsory supervision in accordance with national regulations. Over the years, practice has proved that construction project supervision has played a very important role in ensuring the quality and investment efficiency of construction projects, and has been widely recognized by the society. Construction project supervision refers to the supervision and management of the implementation of the project construction by the supervision unit entrusted by the project legal person in accordance with the construction documents of the project approved by the state, the laws and regulations related to the construction of the project, the construction supervision contract and other engineering construction contracts.
The scope of engineering construction supervision includes: large and medium-sized engineering projects; municipal and public works projects; **Invest in the construction and development of office buildings, social development projects and residential projects; Projects constructed by foreign capital, Sino-foreign joint ventures, foreign loans, grants, and donations. The main contents of engineering construction supervision are:
control the investment, construction period and quality of project construction; Carry out project contract management and coordinate the working relationship between relevant units.
Article 5 of the "Regulations on the Quality Management of Construction Projects" must strictly implement the basic construction procedures and adhere to the principle of survey, design, and construction first. The people** at or above the county level and their relevant departments shall not exceed their authority to examine and approve construction projects or simplify capital construction procedures without authorization. Article 6 The State encourages the adoption of advanced science, technology, and management methods to improve the quality of construction projects.
-
Answer]: a, c, e
This question examines the basis for the preparation of construction project supervision planning. The basis for the preparation of supervision and planning: engineering construction laws, regulations and standards; The external environment of the construction project is adjusted, such as checking the research data; ** Approved engineering construction documents; Contract documents for construction project supervision; construction contracts; the reasonable requirements of the construction unit; The relevant engineering information output during the implementation of the slip core of the project.
-
What you are asking is the basis for the preparation of the project supervision plan? The basis for this is as follows:
According to today's headlines, the basis for the preparation of construction project supervision planning is the laws, regulations and policies related to engineering construction promulgated by the state, which is the highest level of laws and regulations related to engineering construction.
Supervision planning should be signed entrusted supervision contract and received after the start of the design documents, after the completion of the supervision unit must be approved by the technical person in charge of the supervision unit to approve the search for approval, and should be submitted to the construction unit before the first site meeting, supervision planning should be prepared by the chief engineer of the chief engineer Nada Nai Chang Chun, professional supervision engineer to participate in the preparation.
Just follow the questions prompted, don't think too complicated. >>>More
Construction Engineering.
Application (Registration) Time: >>>More
Responsibilities of a professional supervising engineer.
First, what is included in the supervision plan.
1. The contents of the supervision plan include: >>>More