1. First, double-click to open the Microsoft Project application.
2. In the pop-up dialog box, define the name, start time, and finish time. Generally, the start and completion time is the start and completion time of the project. The name can be simply defined as a working day.
3. When defining the completion time, double-click to enter the pop-up dialog box. Define the working hours of the working day, and the rebirth mode is defined as weekly, check the week.
6. Sunday. Once the start completion time is defined, the software calculates how many times it should be reborn.
4. Press the Enter key to confirm, and then you can see that it has been unified for weeks.
6. Sunday is set as a working day.
-
Tools - Change Working Hours - Exception Dates - Details.
1. Exceptional working hours.
2. Rebirth mode - weekly.
Sixth, day. 3. Repetition range - from time to time.
You try it.
-
The number of hours or days specified in the resource or project calendar that the task cannot be scheduled because work cannot be done at that time, so Project should not schedule a task at that time. For example, non-working hours can include lunch breaks, weekends, and holidays. (e.g., weekends and evenings) and special holidays (e.g., holidays).
In addition, you don't need to change the resource's resource calendar (resource calendar: A calendar that specifies working and non-working hours for a single resource. A resource calendar is different from a base calendar, which specifies working and non-working time for multiple resources.
You can control a work resource (work resource: A resource of people and equipment that performs work to complete a task. A work resource consumes time (work hours or working days) to complete a task.
Availability (availability: Indicates when and how much time a resource is available for assigned work. Availability is determined by the following factors:
The project and resource calendars, the start and finish dates of the resource, or the extent to which the resource is available for work. and any units (unit: The number of resources assigned to a task.
Maximum units are the maximum number of units available for a resource. For example, if you have three plumbers, the maximum unit is 300% or three plumbers working full-time. Availability reflects availability.
Project uses this information to determine if a resource is overallocated. Note that the working time calendar and resource availability do not apply to material resources (material resources: Items or other consumables that are used to complete tasks in a project.
Tip: The Project Working Hours side pane provides an easy way to set project working hours. On the Project Wizard toolbar, click Tasks. Click Define regular working hours, and then follow the instructions that appear in the side pane.
-
1. First open the new office project document, and then click the "Project" menu bar.
2. Then click the "Change Working Hours" button to enter the Change Working Hours page.
3. Then on the Change Working Hours screen that opens, switch to the "Work Week" option.
4. After switching to the work week option, click the "Details" button behind the work week to enter the details interface.
5. Then select the date "Sunday", check "Set the following specific working hours for the listed dates", and fill in the start time and end time.
6. Finally, select the date "Saturday", repeat the operation in the fifth step of the setting, and click the "OK" button after the setting is completed to complete the change of working hours.
-
Based on the default "standard" calendar in the project software, you can change it so that all days are working days, or you can create a new calendar that is a working day every day. The so-called standard calendar is a five-day work week, from Monday to Friday, and if you work every day, that is, Saturday and Sunday are also working days, and we call it a "7-day workweek" calendar for the time being.
Let's take a new "7-day workweek" calendar as an example to explain the steps:
Click "Change Working Hours" under the "Project" menu, and then create a new calendar in the pop-up window, as shown in the following figure, the calendar name is entered casually, there are two options under the name, select "New Base Calendar".
In the "7-day work calendar", click on "Work Week" below, then click on "Details", in the pop-up window, use the Ctrl key to select both Saturday and Sunday, then there are 3 options on the right, select the 3rd "Set the following specific working hours for the listed days", and then enter 8:00-12:00 and 13:
00-17:00, click OK.
In"project"menu below"Project information"In the pop-up window, for Calendar, select "7-day workweek", so that the default calendar for all tasks will be 7-day workweek. As shown in the figure below.
The last step is not required, but it is recommended. Right-click and select on the timescale in the Gantt chart area"Timescale", and then select"Non-working hours"and select from the drop-down menu at the calendar below"7-day work week"That's it, so that in the Gantt chart area, there will be no shaded areas on Saturday and Sunday.
-
1. First open the new office project document, and then click the "Project" menu bar.
2. Then click the "Change Working Hours" button to enter the Change Working Hours page.
3. Then on the Change Working Hours screen that opens, switch to the "Work Week" option.
4. After switching to the work week option, click the "Details" button behind the work week to enter the details interface.
5. Then select the date "Sunday", check "Set the following specific working hours for the listed dates", and fill in the start time and end time.
6. Finally, select the date "Saturday", repeat the operation in the fifth step of the setting, and click the "OK" button after the setting is completed to complete the change of working hours.
-
1. First open the new office project document, and then click the "Project" menu bar.
2. Then click the "Change Working Hours" button to enter the Change Working Hours page.
3. Then on the Change Working Hours screen that opens, switch to the "Work Week" option.
4. After switching to the work week option, click the "Details" button behind the work week to enter the details interface.
5. Then select the date "Sunday", check "Set the following specific working hours for the listed dates", and fill in the start time and end time.
6. Finally, select the date "Saturday", repeat the operation in the fifth step of the setting, and click the "OK" button after the setting is completed to complete the change of working hours.
-
1. First open the new office project document, and then click the "Project" menu bar.
2. Then click the "Change Working Hours" button to enter the Change Working Hours page.
3. Then open the Change Working Hours interface and switch to the "Work Week" option.
4. After switching to the work week option, click the "Details" button behind the work week to enter the details interface.
6. Then select the date "Sunday", select "Set the following specific working hours for the listed dates", and fill in the start time and end time.
7. Then select the date "Saturday", repeat the operation in the fifth step of the setting, and click the "OK" button after the setting is completed to complete the change of working hours.
-
1. First open the new office project document, and then click the "Project" menu bar.
2. Then click the "Change Working Hours" button to enter the Change Working Hours page.
3. Then on the Change Working Hours screen that opens, switch to the "Work Week" option.
4. After switching to the work week option, click the "Details" button behind the work week to enter the details interface.
5. Then select the date "Sunday", check "Set the following specific working hours for the listed dates", and fill in the start time and end time.
6. Finally, select the date "Saturday", repeat the operation in the fifth step of the setting, and click the "OK" button after the setting is completed to complete the change of working hours.