Olympiad Engineering Problems I think it s difficult

Updated on educate 2024-03-03
16 answers
  1. Anonymous users2024-02-06

    Let the workload of B be x, then the workload of A is 3x 2, there are y workers, there are workers 3y (1+3)=3y 4 at site A in the morning, there are y 4 people at site B, 3y 4+y 4*7 12=43y 48 at site A in the afternoon, and y-43y 48=5y 48 at site B

    A is just done, 3x 2=3y 4 2+43y 48 2=79y 96B's work x=y 4 2+5y 48 2+4=17y 96+479y 96=(17y 96+4)*3 2 Is the question correct??

  2. Anonymous users2024-02-05

    Every 1 12 batches of workers is considered as a squad, and its efficiency is to complete x number of work sites per day.

    Then 9x 2+7x 2=3 2,x=3 16 from site A, the part that has been done at site B is 3x 2+5x 2=3 4, and the remaining work is 1-3 4=1 4

    Let several squads do this work, and to do it in one day, it takes 4 or 3 squads.

    Then 4 3 squads = 4 people.

    All workers = 12 squads = 36 people.

  3. Anonymous users2024-02-04

    In the afternoon, seven-twelves of the workers went to site B.

    What is the meaning? What happened to Seven Twelve? Did you drop the word?

  4. Anonymous users2024-02-03

    Let's take a look at the parts that will be completed in 4 days.

    The ergonomics is increased by 50%, and the same work is completed for the original 1+50%=3 2, and the time taken is the original 2 3

    To complete this part of the work according to the original ergonomics, it is required:

    1 (1-2 3) = 3 days.

    With the original method, to complete the whole work, it is required: 4 + 3 = 7 days to look at the part after 200 meters.

    With the original method, it was needed: 2 (1-2 3) = 6 days then 200 meters were repaired by the old method, and it was used in: 7-6 = 1 day to repair 200 1 = 200 meters per day.

  5. Anonymous users2024-02-02

    Analysis: After doing it for 4 days, then the following tasks will be completed in a new way: 1 50% 2 days to complete, then the subsequent tasks will be planned to be:

    2 1 3 days, a total of 4 3 7 days If you do 200 meters first, the remaining tasks will be: 2 50% 4 days then the previous 200 tasks are actually used:

    7 4 2 1 days actually do it every day: 200 1 200 meters.

  6. Anonymous users2024-02-01

    After improving work efficiency, if the work is completed according to the planned time, 1 + 50% = portions will be done for another 1 day, and 50% more than planned every day, then the planned number of days is 4+ days.

    Completed 2 days ahead of schedule, indicating that the plan will take days.

    Then it is planned to repair 200 (7-6) = 200 meters per day.

  7. Anonymous users2024-01-31

    I said I don't want equations.

    The column formula can be considered in this way, if the first 4 days also use the new construction method, then the completion of the whole project can be 1 + (4-4 days, these 7 3 days are equivalent to the original total construction days (1-1, so that the original total construction days are 7 days. If you want to list a general formula, it is [1+(4-4 days; In the second process, only 2 days ahead of schedule was completed, which was 7 3-2 = 1 3 days more than all according to the new construction method, and the extra 1 3 days was due to the fact that the first 200 meters were constructed according to the old method, so it took (1 3) (1-1 days) to repair 200 meters according to the old construction method, so that the original plan was to repair 200 1 = 200 meters per day.

  8. Anonymous users2024-01-30

    This topic can do that.

    The original plan was to repair x meters per day, and it would take y days to complete.

    4x+ solution: y=7 that is, the original plan was to be completed in 7 days.

    Simplification: 200+

    Solution: x = 200 meters.

  9. Anonymous users2024-01-29

    The original plan was to repair x meters per day and complete it in y days.

    4x+ solution: y=7

    That is, it was originally planned to be completed in 7 days.

    Simplification: 200+

    Solution: x = 200 meters.

  10. Anonymous users2024-01-28

    Let the work efficiency of A be A, and the work efficiency of B is, according to the title: 36 A + 28 B = (A + B) * 48

    36 A + 28 B = 48 A + 48 B.

    So, 12 A = 20 B.

    A = 5 3 B.

    Then remove the 42 days that A did alone from the total workload, 48 A + 48 B - 42 A = 6 A + 48 B.

    6*5 3B + 48B.

    30 B + 48 B.

    78B. So it takes 78 days for Huan B to complete the task.

  11. Anonymous users2024-01-27

    28 1 48 = 7 12 A B 28 cooperative.

    1-7 12 = 5 12 A 36-28 = 8 days to complete.

    5 12 8 = 5 96 A is done every day.

    Something is wrong with your numbers. Check where you made a mistake.

  12. Anonymous users2024-01-26

    24.100% sure, if you find the answer the same as mine, mine, I'll tell you about the process.

  13. Anonymous users2024-01-25

    The amount of work done by the five engineering teams per day is as follows: From the question, the engineering team does 1 12 (1) per day The engineering team does 1 7 (2) The engineering team does 1 8 (3) per day The engineering team does 1 42 (4) (2) -(1): i.e. 5 84 more per day is written as - =5 84 (1) - (4): that is, 5 84 is written as -=5 84 (2) -(4):

    That is, do 5 42 more per day than write - =5 42 so: can calculate =1 24 can calculate , or you can not calculate (1) + (3): get + =5 24 so + =5 24- =5 24-1 24 = 1 6 i.e. five engineering teams work together to do 1 6 per day

    Therefore, the cooperation of the five engineering teams will take 6 days to complete.

    The word in the question indicates what each engineering team does every day.

  14. Anonymous users2024-01-24

    It takes 6 days.

    1 3 4 42 A It takes 8 days for the engineering team Then it takes 4 days for the two engineering teams to put all the teams together.

    That is, the engineering team is a group, the engineering team is a group, the engineering team is a group, the engineering team is a group, and all these teams are combined to complete the project.

    Then it is equivalent to 3 engineering teams to complete the project, it takes 1 (1 12 + 1 7 + 1 4 + 1 42) = 2, then it takes 2 * 3 = 6 days for the engineering team to complete.

  15. Anonymous users2024-01-23

    No. 1, 2, 3 valves per minute 1 20

    No. 2, 3, 4 valves per minute 1 21

    No. 1, 3, 4 valves per minute 1 28

    Valves No. 1, 2, 4 are 1 30 per minute

    1 20 + 1 21 + 1 28 + 1 30 = 1 6 is three times the working efficiency of 1, 2, 3 and 4 valves.

    1 6 divided by 3 equals 1 18 is 1, 2, 3, 4 valve efficiency and 18 points to complete.

  16. Anonymous users2024-01-22

    A and B cooperated for six days and completed: 8*8 81=8 8 Then B completed in 81 days: 8-8 8=8 8 that is, B completed in one day:

    8 8) 81 = 8 81 A completes in one day: 8 81-8 81=8 88 then A alone: 8 [8 88]=88 days, B to:

    8 [8 81] = 81 days.

Related questions
9 answers2024-03-03

3 people spent a total of 9*3 27 yuan; The 2 yuan taken by the waiter is actually 3*9=27 yuan; The boss received 25 yuan, and the waiter took 2 yuan and earned 25 yuan + 2 yuan 27 yuan, so for the customer, they paid 9 yuan for the accommodation, so 3 x 9 yuan = 27 yuan + returned) 3 yuan = 30 yuan; For the boss (paid by the customer) 30 yuan - the waiter hid it) 2 yuan - (returned by the waiter) 3 yuan = (actual income) 25 yuan; For the waiter (paid by the customer) 30 yuan - (returned to the customer) 3 yuan - (handed over to the boss) 25 yuan = (the waiter hid) 2 yuan expenditure There is no problem with income.

20 answers2024-03-03

First: the front and back of the three cakes are marked as A1, A2, B1, B2, C1, C2 The order of frying is: A1 and B1 together, A2 and C1 together after one minute, B2 and C2 together after one minute, and it takes three minutes to complete. >>>More

11 answers2024-03-03

100รท1=100s

4 x 10 3 x 10 >>>More

4 answers2024-03-03

As long as you're willing to do the math, it's easy to do...... >>>More

35 answers2024-03-03

It seems that Xiaobai, it's good to fight more, Aoshan is not zero honor if he loses, he has to occupy the other party's tower, and he will have honor when he occupies the opponent's territory, and he will have some honor when he occupies a place, and zero honor is that you don't occupy any of the opponent's territory, and you have lost your own place. >>>More