5. Before concealing the concealed project, the construction unit shall notify the relevant units for acceptance, and shall form an acceptance.
It should be notified to the supervision unit for acceptance.
3. The personnel of all parties participating in the acceptance of the construction quality of the project shall have the prescribed qualifications.
There are quality inspection stations, supervision, construction units, etc., and the supervision unit should have supervisors, professional supervision engineers, and directors who are responsible.
-
Standard number: GB 50300-2001
Standard name: unified standard for construction quality acceptance of construction projects.
Standard Status: Active.
English title: Unified Standard for Constructional Quality Acceptance of Building Engineering
Alternate case: GBJ 300-1988
Date of implementation: 2002-1-1
Promulgating Departments:Ministry of Construction of the People's Republic of China, General Administration of Quality Supervision, Inspection and Quarantine of the People's Republic of China.
Brief introduction: This standard is applicable to the acceptance of construction quality of construction projects, and serves as a unified criterion for the preparation of construction quality acceptance specifications for various specialties of construction engineering.
-
The "Unified Standard for Construction Quality Acceptance of Construction Projects" is an announcement of the national standard issued by the Ministry of Housing and Urban-Rural Development on June 1, 2014. Approved the "Unified Standard for Construction Quality Acceptance of Construction Projects" as a national standard, numbered GB50300-2013.
The new version of the "Unified Standard" has made important revisions to the original 2001 version of the "Unified Standard", and added a number of new provisions on project quality acceptance. Among them, Article 1 is a mandatory provision and must be strictly enforced. At the same time, the introduction of the standard will affect a series of local standards to be updated, and the supporting standards and specifications will also be adjusted.
The revisions include:
1. Propose appropriate adjustment of sampling re-inspection and test quantity;
2. Propose provisions for formulating special acceptance requirements;
3. Increase the minimum sampling quantity of inspection batches;
4. Increase sub-divisions such as building energy-saving division, aluminum alloy structure, solar water heating system, and ground source heat pump system;
5. Modify the division of sub-projects in structural, electrical, air-conditioning and other sub-projects;
6. Increase the normal inspection of the counting sampling scheme for the first and second sampling judgment methods;
7. Add provisions on pre-acceptance of project completion;
8. Add the provisions that the survey unit shall participate in the acceptance of the unit's project.
-
In the new version of the specification, there must be an implementation note, which will explain the scope of application, the implementation date and the handling of related issues.
-
There is no need to do information according to the new specification, after the implementation of the new specification is for the project that started after the implementation, if your project has started before this (with a construction permit), then you can implement the original specification. I used 03 db for a project from 08 to 12 years.
-
All materials, processes, and organizations after June 1, 2014 must be implemented in accordance with the new version of the standard, and the previously completed matters will not be retroactively supplemented.
The original text of the standard is attached.
-
Answer]: On page 177 of the C book, for the quality acceptance of construction projects, the project should be divided into unit (sub-unit) project, sub-division (sub-division) project and inspection batch. The quality acceptance of the construction process mainly refers to the quality acceptance of the inspection batch and the sub-project and the sub-project.
-
Summary. Hello dear, I have seen your question here and am sorting out the answer for you, please wait a minute.
Unified Standard for Construction Quality Acceptance of Construction Projects GB50300-+2013 stipulates that the quality acceptance of construction projects should be divided.
Hello dear, I have seen your question here and am sorting out the answer for you, please wait a minute.
-
1. Propose appropriate adjustment of sampling re-inspection and test quantity;
2. Propose provisions for formulating special acceptance requirements;
3. Increase the minimum sampling quantity of inspection batches;
4. Increase sub-divisions such as building energy-saving division, aluminum alloy structure, solar water heating system, and ground source heat pump system;
5. Modify the division of sub-projects in structural, electrical, air-conditioning and other sub-projects;
6. Increase the normal inspection of the sampling scheme of macro rents once, and the sampling judgment method of guessing the trillion times twice;
7. Add provisions on pre-acceptance of project completion;
8. Add the provisions that the survey unit shall participate in the acceptance of the unit's project.
9. Add provisions for physical inspection or sampling test;
10. Add the requirement that the inspection batch acceptance should have the original record of on-site inspection;
11. Modify the source of the omen.
Article 1 of the Unified Standard, when the professional acceptance specification does not make corresponding provisions for the acceptance project in the project, the construction unit shall organize the supervision, design, construction and other relevant units to formulate special acceptance requirements. The special acceptance requirements for projects involving safety, energy conservation, environmental protection and other projects shall be demonstrated by experts organized by the construction unit.
First, first enter the venue to prepare:
1. Project commencement report, construction permit, construction organization design, materials and equipment for review. >>>More
In the case of a part-time construction site, it is generally charged according to the completed area, and the specific amount of money per square depends on the area.
The first step is to prepare a business license: before applying for qualifications, the construction company must have a business license. >>>More
First of all, you must ensure your own business level, like the construction industry pays more attention to practical experience, some masters have worked for a lifetime, especially carpenters are more stubborn, you must improve your ability, so that others can convince you that you can manage your people more conveniently, secondly, use different methods for different people, and quietly listen to what others say when they encounter problems that they don't understand, (learn more by themselves) don't talk nonsense for the sake of face, so you will be laughed at by others. I haven't been doing it for long, and anyway, I always remember to learn more.
What you mean is to do the plan for review, and I am the supervisor, who specializes in reviewing this. First of all, the company's qualifications should be complete, the on-site environment should be included, the arrangement of personnel, the arrangement of schedule, the on-site management system, safety and fire prevention measures, measures after the delay of the construction period, and so on.