Which sub items in the project need to fill in the inspection batch?

Updated on society 2024-05-16
11 answers
  1. Anonymous users2024-02-10

    1. First of all, it is recommended that you go to the architecture bookstore to buy a copy of "Architectural Data ** Filling Sample", this book is a complete set of information According to your project situation, fill in according to the above! 2. Where there is an inspection batch, there is not necessarily a concealment, but there must be an inspection batch where there is a concealment. 3. You use the internal data software to do it, and there are ready-made ** according to the actual situation of the project.

    4. Which places to fill in the content of the inspection batch are based on the actual situation of your project

  2. Anonymous users2024-02-09

    1. Fill in the inspection form with full height until the full height can be measured.

    Second, the inspection batch form required by the order period, such as mortar, concrete 28 days old to fill in. (And the date should be filled in the day "such as: March 29, should be filled in the year, month, and day in the evaluation results and acceptance conclusion columns" to know whether it is qualified or not.)

    However, the date of the project that can be inspected should also be filled, and the brackets should be enclosed with "such as March 1", do not fill in the year, month, and day in the assessment results and acceptance conclusion column, otherwise it is unreasonable, and the report will not come out, and the assessment results and acceptance conclusions cannot be obtained).

    3. The acceptance of the sub-project is a summary of the inspection batch. At this time, it may be concluded that the assessment of mortar and concrete should be filled in and there is a sub-conclusion.

  3. Anonymous users2024-02-08

    Basically, all sub-projects in the sub-projects such as foundation engineering, main engineering, and decoration engineering must be inspected and approved.

  4. Anonymous users2024-02-07

    Sub-projectsIt refers to the subdivision of the subdivision of the subdivision project, which is the basic item constituting the subdivision project, also known as the project sub-item or sub-head, which can be produced through a relatively simple construction process and can be calculated with an appropriate unit of measurement.

    Inspection batch(inspection lot) refers to the inspection body composed of a certain number of samples that are aggregated for inspection under the same production conditions or in a prescribed manner. It is an architectural term, and attribute is the basic unit of project quality acceptance, which is applied to construction and bridge engineering.

    Inspection batches are usually divided according to the following principles:1. The quality of the inspection batch is basically uniform and consistent, and the sampling should conform to the principles of randomness and authenticity.

    2. Implement the principle of process control, and divide inspection batches according to the construction order, the need to facilitate quality acceptance and control of key processes.

  5. Anonymous users2024-02-06

    The fourth article of the "Unified Standard for Construction Quality Acceptance of Construction Projects" GB50300-2001 "the division of construction project quality acceptance" and appendix B "division of construction engineering division (sub-division) project and sub-project division" are very clear. There are many inspection batch items in the sub-project. Such as:

    The steel bar sub-items include, steel bar processing inspection batch, steel bar installation inspection batch, steel bar concealment acceptance inspection batch, etc. Familiar with the unified standard of acceptance, familiar with the construction process, it will be easy to master. As long as you put your mind to it, there is nothing you can't learn.

  6. Anonymous users2024-02-05

    Sub-project: A sub-project is further divided according to the main types of work, materials, construction technology, equipment categories, etc., which can be composed of one or several inspection batches.

    Inspection batch: an inspection body composed of a certain number of samples that are aggregated for inspection under the same production conditions or in a prescribed manner. The inspection batch can be divided according to the needs of construction, quality control and professional acceptance, according to the layer, construction section, deformation joint, etc.

  7. Anonymous users2024-02-04

    Inspection batchIt refers to the test body composed of a certain number of samples that are aggregated for inspection under the same production conditions or in a prescribed manner.

    Sub-projectsIt refers to the construction unit divided by the main types of work, materials, construction technology, equipment categories, etc.

    Divisional Engineering. It refers to the construction unit determined according to the professional nature and building part.

    Unit engineering. Buildings and structures with independent construction conditions and independent use functions are a unit project.

    Individual projects. Refers to a group of complete engineering projects with separate design documents that can independently exert production capacity or benefits after completion.

    The nature of the individual works.

    From the perspective of construction, a single project is an independent system, and the overall construction deployment and management objectives of the project.

    Under the guidance of the company, it will form its own project management plan and objectives, and complete and deliver it on schedule in accordance with its investment and quality requirements.

    For example, in industrial and civil construction projects, the production workshop, office building, and residential building in a factory construction project can be called a single project; The teaching buildings, canteens, dormitories, etc. in a school construction project can also be called a single project; It is an integral part of infrastructure projects.

    For example, a contract section of highway engineering that is independently designed, constructed independently, and can be independently handed over and opened to traffic after completion can become a single project.

  8. Anonymous users2024-02-03

    What is an inspection batch, a unit project, a single project, a sub-project, a sub-project?

    The definitions and characteristics of inspection batches, unit projects, individual projects, sub-projects, and sub-projects are as follows: inspection batch: an inspection body composed of a certain number of samples that are summarized for inspection under the same production conditions or in a prescribed manner; Unit engineering.

    It refers to a project that cannot independently exert production capacity or benefits after completion, but has an independent design and can independently organize the construction; Single project: refers to a project in which a construction project has independent design documents, can independently organize construction, and can independently exert production capacity or benefits after completion; Divisional engineering: It is a component of the unit project and each component of the construction project and installation project; Sub-projects

    It is an integral part of the division project. The characteristics of the above projects are: inspection batch:

    It is the smallest unit of construction quality acceptance, and is the basis for the quality acceptance of sub-projects and even the entire construction project; Unit project: can not play the overall benefit or production capacity independently; Single project: can independently play the overall benefit or production capacity; Divisional Engineering.

    There are different classifications according to the main parts or types of work and installation works of construction works; Sub-project: It is the most basic calculation unit in the construction drawing budget, and the most basic structural element for calculating the consumption of labor, materials and funds, and can be further divided into sub-projects according to different construction methods and different specifications of different materials.

  9. Anonymous users2024-02-02

    1. A single project, a project composed of multiple unit projects, for example, there are 10 buildings in a community, each of which is a unit project, but the construction of the entire community is collectively called a single project.

    2. Unit project: A building (structure) with independent construction conditions that can form an independent use function after completion is defined as a unit project. Taking a factory as an example, the construction of the entire factory is called a construction project, and a production workshop, an office building, and a chimney (structure) are called a unit project.

    3. Divisional engineering: it can be divided according to the construction part and professional nature. The general unit project is divided into nine divisions:

    Foundations and foundations, main structures, roofing, decoration and decoration, water supply, drainage and heating, electrical installation, ventilation and air conditioning, elevator engineering, intelligent buildings. Some unit projects do not include all branch projects. Take a production hall as an example:

    It can be divided into sub-projects such as foundation and foundation, main structure, roofing, decoration and decoration, water supply, drainage and heating, electrical installation, ventilation and air conditioning (see the design drawings for details, only for examples).

    4. Sub-projects: divided according to the main types of work, materials, construction technology, equipment categories, etc. Examples:

    Formwork, steel bars, and concrete are divided by type of work; Gray soil foundation, sand and gravel foundation, broken brick triple soil foundation, geosynthetics foundation is divided by material; Underground diaphragm walls, anchor rods, soil nail walls, and cement soil piles are divided according to construction technology; Water supply pipe installation, drainage pipe installation, heating pipe installation are divided by equipment category, etc., and you can deepen your understanding by looking at the sub-project division table yourself.

    5. Inspection batch: defined as the same conditions in the construction process and a certain number of materials, components or installation items. It is not easy to understand, but it can be understood as an inspection batch of sub-projects.

    The inspection batch can be divided according to the floor, construction section and deformation joint. For example: the main structure of a production workshop (assuming a frame structure) frame column concrete, concrete is a sub-project, the construction may not be completed at one time, can be divided into 1-10 axis, 10-20 axis, 20-30 axis...and so on for each inspection batch; Or by settlement joint, if any

  10. Anonymous users2024-02-01

    1. The division of sub-projects: sub-projects are the subdivisions of sub-projects, and are the basic items that constitute sub-projects, also known as sub-projects or sub-projects, which can be produced through a relatively simple construction process and can be calculated by appropriate units of measurement for construction projects or installation projects. Generally, it is divided according to different factors such as the selected construction method, the materials used, and the specifications of structural components.

    For example, in masonry engineering, it can be divided into sub-projects such as brick foundation, brick wall, brick column, block wall, reinforced brick lintel, etc., and can be divided into excavation, backfill, surplus soil transportation and other sub-projects in earthwork engineering.

    2. The division of inspection batch: the inspection batch is the basic unit (the smallest unit) of project quality acceptance. The test items are the same, the quality requirements and production processes are basically the same, and the test objects are composed of a certain number of components.

    For steel wires of the same grade, the same specification and the same production process, every 60t is an inspection batch.

    Project information includes:

    The first part is the pre-construction information.

    1. Notice of winning the bid and construction permit.

    2. Construction contract.

    3. The supervision contract of the entrusted supervision project.

    4. Construction drawing review approval letter and construction drawing review report.

    5. Quality supervision registration.

    6. Key points of quality supervision and quality supervision work plan.

    7. Geotechnical engineering investigation report.

    8. Construction drawing review record.

    9. The construction organization design or construction plan approved by the supervisor (or owner) 10, the commencement report.

    11. Quality management system registration form.

    12. Construction site quality management inspection records.

    13. Technical disclosure records.

    14. Measurement and positioning records.

    The second part of the quality acceptance data.

    1. Foundation groove inspection record.

    2. Quality acceptance report of foundation pile engineering.

    3. Quality acceptance report of foundation treatment project.

    4. Quality acceptance report of foundation and foundation division.

    5. The quality acceptance report of the main structure division.

    6. Quality acceptance report of special branch project.

    7. Line laying acceptance report.

    8, the foundation and foundation division and the contained sub-divisions, sub-items, inspection batch quality acceptance records 9, the main structure division and the contained sub-divisions, sub-items, inspection batch quality acceptance records 10, decoration and decoration division and the contained sub-divisions, sub-items, inspection batch quality acceptance records 11, the roof division and the contained sub-divisions, sub-items, inspection batch quality acceptance records 12, water supply, drainage and heating division and the contained sub-divisions, sub-items, inspection batch quality acceptance records 13, electrical division and the contained sub-divisions, sub-items, Inspection batch quality acceptance record 14, intelligent division and contained subdivisions, sub-items, inspection batch quality acceptance record 15, ventilation and air conditioning division and contained sub-division, sub-item, inspection batch quality acceptance record 16, elevator division and contained sub-division, sub-item, inspection batch quality acceptance record 17, unit project and contained sub-unit project quality completion acceptance record 18, outdoor engineering division (sub-division), sub-item, inspection batch quality acceptance record.

  11. Anonymous users2024-01-31

    Content from user: Wang Xiaoning.

    Definition: 1. A construction project refers to a construction unit consisting of one or several individual projects in an overall area, which implements independent accounting economically, implements unified management administratively, and has legal personality. Example: a school, a factory, etc.

    2. A single project refers to a project in which it has independent design documents, can independently organize construction, and can independently exert production capacity or benefits after completion. For example, a school's teaching building, laboratory building, library, etc.

    3. The unit project refers to the project that cannot independently exert production capacity or benefits after completion, but has independent design and can independently organize the construction. For example: civil engineering, electrical lighting, water supply and drainage, etc.

    For a unit project with a large building scale, the part that can form an independent function can be regarded as a sub-unit project.

    The difference between a single project and a unit project is mainly to see whether it can independently exert the overall benefit or production capacity after completion.

    4. Branch engineering.

    The sub-project is a component of the unit project, which is the various components of the construction project and the installation project, and is divided according to the main part of the construction project or the type of work and installation project.

    The 10 major divisions of construction engineering include: foundation and foundation, main structure, building decoration, building roofing, building water supply, drainage and heating, building electrical, intelligent building, ventilation and air conditioning, elevator, and building energy conservation engineering.

    When the sub-project is larger or more complex, it can be divided into several sub-sub-projects according to the type of material, construction characteristics, construction sequence, professional system and category. For example, decoration projects can be divided into: ground, doors and windows, ceiling engineering; Building electrical engineering can be divided into:

    Outdoor electrical, electrical lighting installation, electrical power and other sub-division projects. 6. The division of inspection batch of steel structure engineering inspection batch: single-layer steel structure can be divided according to deformation joints; Multi-storey and high-rise steel structures can be divided by floors or construction sections; Steel structure fabrication.

Related questions
3 answers2024-05-16

1.Write a civil complaint, the first part of which states the name, gender, date of birth, ethnicity and place of residence of the plaintiff and the defendant, and the second part of which writes claim aPetition for divorce; b. >>>More

4 answers2024-05-16

Strengthen the re-testing work in the construction survey to reduce the occurrence of errors. >>>More

5 answers2024-05-16

You don't have to take anything except the fourth and sixth grades. Science and engineering are all about strength, not looking at certificates.

6 answers2024-05-16

Well, not everyone is the same. The general relevant needs are: 3C certification standard qualification, company profile, business license (annual inspection is valid), organization ** certificate, tax registration certificate (all copies are stamped with official seal), power of attorney of legal representative (must be original), etc.