The foundation of the building needs to collect those materials

Updated on society 2024-05-13
12 answers
  1. Anonymous users2024-02-10

    Earthwork excavation, backfilling, foundation trench inspection, etc.

  2. Anonymous users2024-02-09

    First, first enter the venue to prepare:

    1. Project commencement report, construction permit, construction organization design, materials and equipment for review.

    2. Concrete mix ratio design and material inspection.

    3. On-site acceptance. Temporary facilities (schemes), safe and civilized construction preparations.

    4. Engineering survey and positioning records.

    Should be all prepared:

    Basic information table of construction projects.

    Construction approval materials (project approval documents requested from the construction unit).

    Construction project planning permit (planning permit requested from the construction unit), notice of winning the bid for the construction project (notice of winning the bid from the construction unit), construction contract (construction contract requested from the construction unit).

    Supervision contract (supervision contract requested from the supervision unit).

    A copy of the qualification and personnel certificate of the construction unit.

    Copies of project supervision institutions and relevant certificates.

    A copy of the qualification and personnel certificate of the design unit.

    A copy of the qualification and personnel certificate of the survey unit.

    Copies of project construction institutions and related certificates (including qualification certificates, personnel employment certificates (project manager, technical leader, constructor, budget officer, quality inspector, safety officer, material officer, surveyor, sampler, data clerk, drainage, heating, electrical engineer).

    Drawing triage records and design change documents.

    Design documents and design changes before the start of construction.

    Construction site quality management inspection records and schedules.

    1. A package of quality responsibility system.

    2. The main professional types of work operation certificates (tower cranes, scaffolding workers, gantry frames, electric welders, butt welders, straight ribbing, electroslag welders) (ask for each team).

    3. The qualification contract of the subcontractor.

    4. Construction drawing review (construction drawing review certificate).

    5. Geological survey documents.

    6. Construction organization design, construction plan and approval.

    There are others.,I'm not all out here.,If you need it, you can hit it in the (library) (construction materials first enter the site to prepare) to **a.,All of the above need to be done to enter the site Of course, that is also sent by me = =!

  3. Anonymous users2024-02-08

    1. Pile foundation information (including test piling records, pile construction records, pile position technical review records, pile concealment acceptance records, pile foundation sub-item inspection batches, pile deviation records plus the corresponding pile certificate, such as pipe pile pipe pile certificate, bored pile pile pile is cement and steel bar, pile acceptance record).

    2. Earthwork excavation (earthwork excavation sub-section inspection and approval, if there is support earthwork, different information should be done according to the support method, foundation inspection groove, foundation groove pay-off record, etc.).

    3. Concrete foundation (concrete foundation sub-item inspection batch, steel bar concealment, concrete concealment, cushion concealment, technical review, concrete construction diary, concrete curing record, concrete collapse test record, etc.).

    4. Underground waterproofing (underground waterproofing sub-section inspection batch, waterproof concealment, waterproof inspection record) grinding bridge posture.

    5. Foundation brick masonry (foundation brick masonry sub-section inspection batch, technical review, concealment, etc.).

    The quality acceptance record of the project of the foundation division.

    Infrastructure acceptance records.

    There are also a series of reports such as raw material testing reports, welding reports, test block reports, pile foundation inspection reports, foundation core drilling reports, and mortar rebound reports in the project.

    If there is a basement civil air defense, a complete set of civil air defense materials must be made.

  4. Anonymous users2024-02-07

    Building construction management materials include:

    Construction site quality management inspection imitation late record;

    Notice of Winning the Bid;

    Project budget (final) account celebration;

    Contracting contracts;

    construction permits;

    List of personnel and post certificates of quality assurance system;

    Commencement report; Supervise the inspection and preparation of the receipt notice;

    Engineering Quality Warranty.

    Enterprise standard (provided during construction).

    Building construction refers to the production activities in the implementation stage of engineering construction, the construction process of various buildings, and it can also be said to be the process of turning various lines on the design drawings into physical objects at designated locations. It includes foundation engineering construction, main structure construction, roofing engineering construction, decoration engineering construction, etc. The place where the construction work is carried out is called the "construction site" or "construction site", also called the construction site.

  5. Anonymous users2024-02-06

    1. No support earthwork; 2. There is a supporting earthwork; 3. Ground treatment; 4. a pile foundation; 5. Underground waterproofing; 6. a concrete foundation; 7. Steel structure.

  6. Anonymous users2024-02-05

    The Basic segment includes:

    Seven subdivisions.

    1.Unsupported earthwork sub-division project: AEarthwork excavation sub-item BEarthwork backfill sub-item 2There is a support earthwork sub-division project:

    3.Foundation Treatment Sub-Division Engineering:

    4.Pile foundation sub-division project:

    5.Underground waterproofing sub-division project:

    6.Concrete Foundation Sub-Division Works:

    7.Masonry Foundation Subdivision Project:

  7. Anonymous users2024-02-04

    This is explained in the appendix following the Code for Acceptance of Construction Works.

  8. Anonymous users2024-02-03

    Soil and water buildings are more important due to the environment in which they are located.

    Harsh, the stability of its foundation is required to be high, and only a solid foundation can ensure the safe operation of hydraulic buildings. Therefore, in the design and construction of the building, it is necessary to check the stability and settlement of the foundation, and take appropriate measures to ensure the stability and settlement requirements of the foundation, so that the hydraulic building can operate safely and stably. In this paper, the treatment of soft clay foundation, the dam body in the soft foundation and the seepage prevention of the foundation are analyzed.

    In one step, the problems that should be paid attention to in the construction of soft soil foundation of hydraulic buildings are specifically elaborated.

  9. Anonymous users2024-02-02

    Raw material test report, witness sampling and re-inspection report of steel bar, sand and cement. Concealed engineering data, formwork installation and dismantling inspection batch, steel bar processing, connection, installation inspection batch, concrete mixing and pouring inspection batch, steel bar welding inspection report, concrete cube strength inspection report. Foundation pit acceptance records, geological exploration reports, etc.

    Finally, there is the inspection form and review form of each sub-project.

    Basic inspection batch acceptance records, sub-project acceptance records, branch acceptance records, material testing and inspection reports, various schemes, basic acceptance reports, supervision of the basic assessment report, basic acceptance notice, acceptance sign-in form.

    1. Foundation groove inspection record.

    Second, the pre-inspection of engineering records.

    3. Engineering positioning measurement and retest records.

    Fourth, the foundation drilling record.

    5. Application for pouring foundation concrete.

    Sixth, the foundation concrete opening identification.

    7. Construction records of foundation concrete projects.

    8. Acceptance record of foundation concealment project.

    9. Quality acceptance record of the basic division project.

    10. Quality acceptance records of earthwork sub-projects.

    11. Backfill sub-project quality acceptance record.

    12. Concrete sub-project quality acceptance record.

    13. Reinforcement sub-project quality acceptance record.

    14. Quality acceptance record of masonry foundation sub-project.

    Fifteenth, the template sub-project quality acceptance record.

    16. Cast-in-situ structure sub-project quality acceptance record.

    After the construction unit submits the application for the construction unit supervision pre-inspection (including on-site physical buildings and data collation) After passing the qualification, notify the quality inspection station Design Institute The acceptance time of the survey unit is officially held After the acceptance is passed, several parties jointly sign and approve.

    The acceptance form of the foundation division (pile foundation sub-division) shall be jointly signed and stamped by Party A, the supervision and design institute, the survey unit and the construction unit.

    Also, don't forget to prepare a sign-in sheet for acceptance.

  10. Anonymous users2024-02-01

    Foundation engineering is usually referred to as the subdivision acceptance of 'foundation and foundation division engineering'.

    According to the division and sub-division of GB50300-2001 "Unified Standard for Acceptance of Construction Quality of Construction Projects";

    Quality certification data, retest reports, concrete and mortar test block data of materials (and semi-finished products) used in each sub-item contained in the foundation and foundation segment;

    All inspection batch acceptance data, sub-acceptance data, and concealed records of each sub-item contained in the division; and on-site inspection test data.

    Records of design changes and negotiations.

    Engineering surveying, pay-off recording.

    Pre-inspection, self-inspection, mutual inspection, and handover inspection records. Concealed engineering acceptance records.

    The foundation and foundation division and the contained subdivisions, sub-divisions, inspection batch quality acceptance records.

    Records of foundation groove inspection.

    The quality acceptance report of the foundation pile project, and the inspection results of the foundation strength (bearing capacity) after the construction of various foundations and various composite foundations in the foundation treatment project.

    Quality acceptance report of foundation treatment project.

    Quality Acceptance Report of Foundation and Foundation Division.

    Supervision evaluation report.

  11. Anonymous users2024-01-31

    Foundation and Foundation DivisionConcrete Foundation Subdivision,,

    Reinforcement sub-item. Template sections.

    Concrete sub-items, and then according to the on-site inspection of these inspection batches, raw materials to be sent for inspection have a plan, the tonnage of the amount of grasp.

    Make a summary after that**, check it when the foundation is accepted.

    Nothing else, what step do you have to go to see the scene? You just need to do the information inspection of which part.

  12. Anonymous users2024-01-30

    The standards are not the same, you are writing information.

Related questions
14 answers2024-05-13

Money, open joints.

Network. Gives you a way to open up the joints. >>>More

12 answers2024-05-13

You can learn the movements of hip-hop dance first, and I think this is the best way to know which strength you want to practice in the process of doing the movements.

11 answers2024-05-13

1.Of course, you have to study formal architectural design. >>>More

6 answers2024-05-13

<>Conditions required for Grade B qualification for architectural design: >>>More

7 answers2024-05-13

The personnel requirements and equipment for the Class B qualification in the construction industry are as follows: >>>More