Construction organization design.
Main research contents.
1) Analysis of project overview and characteristics.
Analyze and summarize the nature, scale, construction location, construction method, building and structural characteristics, the period of delivery in phases and batches, and the construction unit.
requirements and conditions that may be provided; the climate, topography, geology, hydrology and transportation of the region; Construction force, construction conditions, resources, etc. And find out the main construction characteristics (difficulties) of the project.
2) Construction plan.
Choose. According to the analysis of the general situation and characteristics of the project, combined with the resources available for investment, the construction tasks are fully deployed, and the overall sequence and flow direction of the construction are determined; Selection of construction methods and construction machinery for major types of work; Determine the construction sequence of each part of the project.
Qualitative and quantitative analysis of several construction schemes available for the proposed project was carried out to select the best construction scheme.
3) Preparation of construction schedule.
The construction schedule is the embodiment and arrangement of the construction plan in time. The preparation of the construction schedule should adopt advanced planning theories and methods (such as flow construction, Gantt diagrams).
Vertical diagram, network diagram, etc.) reasonably determine the construction sequence and the operation time of each process, so that the construction period, cost and resource utilization can achieve the best combination state, that is, the resource balance, the construction period is reasonable, and the cost is low.
4) Construction preparation work plan.
Determine the content, start and end time, the size of the project, the number of people who complete the work and the specific person in charge of the construction preparation.
5) Demand plan for labor, construction machinery, transportation equipment, main building materials, components and semi-finished products to solve the best problems.
6) Construction plan design.
Its purpose is to solve the construction site.
plane and spatial arrangement. That is, the various resources (such as materials, components, machinery, transportation, etc.) and the temporary facilities and sites required for production and life are optimally arranged on the construction site to ensure that the whole site can be organized, orderly and planned civilized construction.
7) Main technical and economic indicators.
Carry out a comprehensive technical and economic benefit evaluation of the preparation of the construction organization design: such as the use of construction period, quality, cost, safety and other indicators.
-
It is mainly the main content of the drawing design and the detailed construction plan.
-
Summary. Hello! We're glad to answer your questions! ~<
Pro, a series of textbooks for the education and training program for outstanding engineers in civil engineering: The construction organization comprehensively and systematically expounds the theories and methods of civil engineering construction organization according to the training objectives of application-oriented talents and the requirements of civil engineering professional specifications, as well as the new norms and standards in construction organization design and network planning, supplemented by cases, and pays attention to the cultivation of readers' application ability. In the arrangement of content, comprehensive xing and practical xing are highlighted.
The conditions for the completion of the study of the construction organization design are:
You're grinding! We're glad to answer your questions! ~<
Pro, the conditions for the completion of the research of the construction organization design are the research conditions, the application environment, and the purpose of the work.
Hello! We're glad to answer your questions! ~<
According to the training objectives of application-oriented talents and the requirements of civil engineering professional specifications, as well as the new norms and standards in construction organization design and network planning, the construction organization comprehensively explains the theory and method of civil engineering construction organization, supplemented by cases, and pays attention to the cultivation of readers' application ability. In the arrangement of content, comprehensive xing and practical xing are highlighted.
-
Summary. Good afternoon, dear! Housing construction organization design refers to the planning, design and organization of construction projects before construction.
Its main research contents include:1Construction organization plan:
Design the overall plan of construction of construction projects, including construction strategy, construction organization principles, construction arrangement, schedule, resources, etc. 2.Construction process design:
Formulate the detailed process flow and acceptance criteria of the construction. 3.On-site management program:
Including on-site safety management, construction environment control, construction period and quality management. 4.Personnel organization design:
Formulate the organizational structure of the construction team, organize the professional division of responsibilities of the personnel, coordinate management and on-site supervision during the construction process, etc. 5.Safety and environmental protection measures:
Carry out detailed design of construction safety and environmental protection requirements to ensure that safety and environmental protection issues in the construction process are fully considered.
Good afternoon, dear! The organization design of housing construction is a work that refers to the planning, design and organization of construction projects before construction. Its main research contents include:
1.Construction organization plan: design the overall plan of the construction of the construction project, including the construction strategy, construction organization principles, construction arrangement, schedule, resources, etc.
2.Construction process inspection design: formulate the detailed process flow and acceptance criteria of construction.
3.On-site management plan: including on-site safety management, construction environment control, construction period and quality management.
4.Personnel organization design: formulate the organizational structure of the construction team, organize the professional division of responsibilities of the personnel, coordinate management and on-site supervision during the construction process, etc.
5.Safety and environmental protection measures: Detailed design of construction safety and environmental protection requirements to ensure that safety and environmental protection issues in the construction process are fully considered.
The objectives of the study include:1Improve the efficiency and quality of construction and ensure the quality of the project.
2.Reduce safety accidents and accidents in the construction process and ensure the personal safety of workers on site. 3.
Reduce waste, improve resource utilization, and reduce construction costs in construction. 4.It provides sufficient conditions for the operation and maintenance of the project after construction, and reduces the maintenance cost in the future.
In general, the organization design of housing construction aims to fully plan and organize the construction project in the early stage of construction to ensure the smooth progress and high-quality completion of the construction project.
What is the research direction of civil engineering and housing construction organization design?
8 words. Optimization of construction organization design.
This paper summarizes the practical experience of construction organization design in the past, puts forward optimization suggestions, and provides theoretical support for improving engineering construction efficiency and reducing costs.
Construction organization design and management.
Study the design and management of construction organization plan, process design and on-site management plan, and how to organize the construction process with high efficiency and high quality.
-
12201060 the content and compilation method of construction organization design Review points Construction organization design is an important means to implement scientific management of construction activities, and it has the dual role of strategic deployment and tactical arrangement. It embodies the requirements for the realization of the capital construction plan and design, provides the content of the construction preparation work at each stage, and coordinates the interrelationship between the construction units, construction types and resources in the construction process. 1 Familiar with the content of construction organization design (1) The basic content of construction organization design The content of construction organization design should be combined with the actual characteristics of the engineering object, construction conditions and technical level for comprehensive consideration and consideration, generally including:
Project Overview; Construction Department and construction plan; construction schedule; Basic content such as construction plan and main technical and economic indicators. (2) Classification and content of construction organization design Construction organization design can be divided into: general design of construction organization; Unit engineering construction organization design and division (sub-item) project construction organization design [or division (sub-item) engineering operation design].
2 Familiar with the preparation method of construction organization design (1) The preparation principle of construction organization design: When compiling the construction organization design, the following principles should be considered: pay attention to the role of the organization of the project on the construction; increase the degree of industrialization of construction; Pay attention to management innovation and technological innovation; Pay attention to the target control of engineering construction; Actively adopt advanced construction technology at home and abroad; Make full use of time and space, reasonably arrange the construction sequence, and improve the continuity and balance of construction; Rational deployment of the construction site to achieve civilized construction.
2) The basis for the preparation of the general design of the construction organization of the construction organization and the construction organization design of the unit. (3) the preparation procedure of the general design of the construction organization: The preparation of the general design of the construction organization usually adopts the following procedures:
Collect the relevant information and drawings required for the preparation of the general design of the construction organization, and conduct investigation and research on the characteristics of the project and the construction conditions; Calculate the quantities of major types of work; Determine the overall deployment of the construction; Preparation of construction plans; Preparation of the general construction schedule; Preparation of resource requirements plans; Preparation of construction preparation work plan; Construction master plan design; Calculation of the main technical and economic indicators.
Construction organization design is an important means to implement scientific management of construction activities, which has the dual role of strategic deployment and tactical arrangement. It embodies the requirements for the realization of the capital construction plan and design, provides the content of the construction preparation work at each stage, and coordinates the interrelationship between the construction units, construction types and resources in the construction process. >>>More
Chapter I: Notes on the preparation.
Section 1: Basis for compilation. >>>More
I only have housing construction and municipal administration, and I don't quite understand what a biogas digester is.
There is a forum for the University of Architecture Hall, so go find it.
First, the general situation of the project.
This project is a vertical storage tank insulation project, the height of the storage tank is 10 meters, the diameter is 5 meters, the insulation material is polyurethane foam board, and the insulation thickness is 100mm. The construction site is an industrial park. >>>More