Enterprises need the following information to do EIA:
First, the materials for EIA handling.
1. Certificate of filing and registration of the development and reform department.
2. Land use certificate.
3. A copy of the business license.
5. Legal person ID card.
Copy. 6. Floor plan of the factory.
7. Neighborhood diagram.
8. Submit the EIA unit to prepare the EIA report.
9. After the EIA report is completed, it will be submitted to the environmental protection department for approval, and at the same time, it will be publicized online.
10. After the approval of the EIA report is completed, the project will start construction.
Second, the procedures for EIA.
1. After the construction unit submits the project application, the municipal (county) environmental protection bureau shall conduct environmental protection examination and approval in accordance with the capital construction procedures. Project proposal after review.
Regarding the environmental protection part, determine the preliminary opinions on the project; Approval of environmental impact statements; Review of the feasibility study report.
or design a brief for environmental protection; Review of the preliminary design.
In the environmental protection chapter, the preliminary design review opinion is issued; Review the construction design drawings of the construction project, and approve the "three simultaneities" of environmental protection of the construction project.
Review the notice to ensure that "design, construction, and production at the same time" must be ensured.
2. Time limit for EIA procedures: sign the approval opinion within 3 days of receiving the environmental impact registration form; Sign the approval opinion within 5 days of receiving the environmental impact report form; Approval within 7 days of receipt of the environmental impact report; The review opinion will be issued within 1 month of receiving the preliminary design environmental protection chapter; Receipt of the "Three Simultaneous" Submission Form for Environmental Protection of Construction Projects and other documents and drawings submitted by the construction unit for review according to the requirements of the regulations shall be issued within 1 month; After receiving the trial production application report and relevant information, and after on-site inspection, it will be approved within 2 weeks; Receipt of completion acceptance.
The application materials shall be approved within 1 month (including the necessary on-site inspection).
3. Application materials for EIA procedures: the geographical location of the construction project.
Schematic diagram, construction project environmental impact approval report, project layout schematic diagram, project construction approval document or filing approval document, planning compliance certificate, enterprise name certificate, power of attorney of ** person.
Environmental impact registration form and permit procedure of construction project: acceptance - on-site investigation - registration form review - decision.
-
According to the relevant rules and regulations, the publicity of the enterprise EIA can be publicized in the first place, the industry or the local portal, the newspaper, and the first place. At present, the credibility of newspapers and newspapers is strong, but the publicity process is complex, and newspapers and newspapers will charge high fees. Without affecting the publicity, you can go to the industry ** publicity, self-registration, self-release, and the publicity can be completed in a few minutes, which has the same effect as other official ** or **.
There are many domestic public announcements, such as EIA enthusiasts, EIA forums, easy EIA, first EIA, etc., the first two are forums, and the latter two are industries. Newspaper can be operated directly on the mobile phone Alipay or WeChat applet, search on the homepage of Alipay: run the government, the provincial and municipal newspapers in it are very detailed, and you can choose the newspaper according to your own situation.
From a few tens to a few hundred dollars. Hurry up and see
-
According to the degree of impact of construction projects on the environment, the State implements classified management of environmental protection of construction projects in accordance with the following provisions:
1) If the construction project may have a significant impact on the environment, an environmental impact report shall be prepared to conduct a comprehensive and detailed evaluation of the pollution generated by the construction project and the impact on the environment;
2) If the construction project may have a slight impact on the environment, an environmental impact report form shall be prepared to analyze or make a special evaluation of the pollution and environmental impact of the construction project;
3) If the construction project has little impact on the environment and does not need to carry out environmental impact assessment, the environmental impact registration form shall be filled.
According to this provision, an environmental impact report shall be prepared for the establishment of a chemical plant, and a report form or registration form shall be prepared according to the sensitivity of the area and the business area of the restaurant.
-
Whether an EIA is required for a project or not, and whether the EIA is a report or a report form is based on the Ministry of Environmental Protection's "Catalogue of Classified Management of Environmental Impact Assessment of Construction Projects".
It is necessary to compare the specific construction project and its scale with the "Catalogue of Classified Management of Environmental Impact Assessment of Construction Projects" to determine whether to do an EIA, and whether to do an EIA report or a report form.
-
I just saw it, and I answered one easily. Whether or not to perform the EIA procedures is related to the industry and the process used by your factory, not that you can not do it if you think it will not disturb the people. Specifically, you can check the "Catalogue of Classified Management of Environmental Impact Assessment of Construction Projects" by yourself, check your own industry against the directory, and see if you want to make a registration form, a report form or a report.
EIA has a strong regionality, and it is most reliable to find the source of the EIA unit by yourself. Once you do the EIA, you will generally be required to go to environmental protection facilities, hazardous waste agreements or something, this can't escape the money is more than the EIA fee, otherwise the later acceptance but or you simply did not do the acceptance, if it is found, it will be cool in the later stage or depends on the management department.
-
Article 8 of the Law of the People's Republic of China on Environmental Impact Assessment.
Relevant departments, local people** at or above the level of cities divided into districts and their relevant departments, shall organize environmental impact assessment before the draft of the special plan is submitted for examination and approval. and submit an environmental impact report to the authority that examines and approves the special plan.
-
To do an EIA, it also depends on what material the mat is, if it is artificial leather, styrofoam and other plastics designed with toxic raw materials, it is necessary to do the EIA report, and other types of plastics only need to do the report form.
-
1. Which construction projects need to go through the EIA procedures?
The Law of the People's Republic of China on Environmental Impact Assessment was amended in 2018.
Article 16 The State shall implement classified management of the environmental impact assessment of construction projects according to the degree of impact on the environment。
The construction unit shall, in accordance with the following provisions, organize the preparation of environmental impact reports, environmental impact report forms or fill in the environmental impact registration form (hereinafter referred to as environmental impact assessment documents):
1) If it may cause a major environmental impact, an environmental impact report shall be prepared and a comprehensive assessment of the resulting environmental impact shall be conducted;
2) Where a slight environmental impact may be caused, an environmental impact report form shall be prepared to analyze or make a special assessment of the environmental impact;
3) If the environmental impact is very small and there is no need for environmental impact assessment, the environmental impact registration form shall be filled.
Article 19 The construction unit may entrust a technical unit to carry out an environmental impact assessment of its construction project, and prepare an environmental impact report and an environmental impact report form for the construction project; If the construction unit has the technical ability of environmental impact assessment, it may carry out environmental impact assessment of its construction project on its own, and prepare the environmental impact report and environmental impact report form of the construction project.
Article 22 The environmental impact report and report form of the construction project shall be submitted by the construction unit to the competent department of ecology and environment with the right of examination and approval in accordance with the provisions of the construction unit.
Article 25 Where the environmental impact assessment documents of a construction project have not been examined by the examination and approval department in accordance with the law or have not been approved after examination, the construction unit shall not start construction.
-
What information needs to be prepared for the EIA report, 1. A copy of the industrial and commercial pre-examination enterprise name notice or business license; 2. A copy of the ID card of the legal person; 3. Project approval documents (feasibility study report approval or issuance and modification of Wen He Bihuai); 4. The internal layout of the project; 5. Real estate certificate; 6. Housing lease contract; Real estate projects generally require: development and reform documents, land documents, planning documents (including red line maps), general plans, basement plans (there is no basement) ·· Catering should also provide fume purifiers, purchase wisdom sales contracts, etc., and you can contact the EIA unit directly, and you will be asked to provide what information.
Small and micro enterprises. Construction projects that are not specified in the "Catalogue of Classified Management of Environmental Impact Assessment of Construction Projects" are not included in the EIA management in principle. >>>More
Enterprise EIA publicity means that before the investment and construction of a new project, the enterprise entrusts the EIA agency to conduct an environmental impact assessment of the project, that is, to assess the possible impact of the project after completion, and propose measures to solve or reduce the environmental impact. >>>More
EIA of construction projects is an administrative examination and approval procedure for environmental impact assessment and environmental quality assessment of construction projects in the field in China. Broadly speaking, the environmental assessment of construction projects is the value assessment, judgment and countermeasures of the environmental system status of the proposed project. >>>More
Yes, for the project of preparing the report, it is stipulated that it must be done twice. However, some report table items need to be publicized, which are different from place to place, and there are also once. It shall be implemented according to local regulations. >>>More
That's a lot, in fact, if it is strict, it is needed, such as restaurants, (restaurants), KTV, dance halls, and all kinds of amusement and entertainment venues all need to do EIA, after all, there will always be domestic sewage, domestic garbage, noise and other impacts.