What is a high die support and what is the specific definition?

Updated on technology 2024-02-28
10 answers
  1. Anonymous users2024-02-06

    High formwork support refers to the formwork support operation when the formwork height is greater than or equal to 8m.

    The Ministry of Housing and Urban-Rural Development's Jianzhi [2009] No. 87 document "Measures for the Safety Management of Dangerous Sub-project Projects" stipulates:

    1. Concrete formwork support project in the sub-project with greater risk: erection height of 5m and above; erection span of 10m and above; The total construction load is 10kn m and above; Concentrated line load of 15kn m and above; The height is greater than the width of the supporting horizontal projection and is relatively independent and has no contact components.

    2. Concrete formwork support project in the sub-project with greater risk of exceeding a certain scale: erection height of 8m and above; The erection span is 18m and above, and the total construction load is 15kn m and above; Concentrated line loads of 20 kN m and more.

    Note: Sub-projects with greater risk than a certain scale need to be demonstrated by experts.

  2. Anonymous users2024-02-05

    Let me explain to you, the high formwork happens to be the one I have more contact with in my work.

    1. The Ministry of Housing and Urban-Rural Development's Jianzhi [2009] No. 87 document, the notice of the "Measures for the Safety Management of Dangerous Sub-project Projects" states: erection height of 5m and above; erection span of 10m and above; The total construction load is 10kn m2 and above; Concentrated line load of 15kn m and above; The concrete formwork support project with a height greater than the support horizontal projection width and relatively independent without contact components is a sub-project with greater risk.

    Erection height 8m and above; erection span of 18m and above; The total construction load is 15kn m2 and above; If the load of the concentrated line is 20kn m or more, it is "a sub-project with a greater risk of exceeding a certain scale". (Note: "This class requires expert argumentation").

    2. The Ministry of Housing and Urban-Rural Development's Jianzhi [2009] No. 254 document, "Guidelines for the Supervision and Management of Construction Safety of Tall Formwork Support Systems for Construction Projects" is explained in the notice:

    The tall formwork support system refers to the formwork support system of the concrete component formwork at the construction site of the construction project with a support height of more than 8m, or an erection span of more than 18m, or a total construction load of more than 15kN, or a concentrated line load of more than 20KN.

    The construction unit shall, in accordance with the current relevant national standards and specifications, be organized by the technical person in charge of the project to prepare a special construction plan for the tall formwork support system in combination with the actual project. And it can be implemented only after expert demonstration.

    If you need more information, you can leave an email and I will send you the document to see.

  3. Anonymous users2024-02-04

    Definition of high formwork:

    1. Ministry of Housing and Urban-Rural Development.

    The notice of the "Measures for the Safety Management of Sub-projects with Greater Risk" [2009] No. 87 explains:

    Erection height of 5m and above; erection span of 10m and above; The total construction load is 10kn m2 and above; Concentrated line load of 15kn m and above; The concrete formwork support that height is greater than the width of the support horizontal projection and is relatively independent without connecting member.

    The project is a sub-project with greater risk. Erection height 8m and above; erection span of 18m and above; The total construction load is 15kn m2 and above; If the load of the concentrated line is 20kn m or more, it is "a sub-project with a greater risk of exceeding a certain scale".

    2. The Ministry of Housing and Urban-Rural Development's Jianzhi [2009] No. 254 document, "Tall Formwork for Construction Projects.

    Support System Construction Safety Supervision and Management Guidelines" is stated in the notice:

    The tall formwork support system refers to the construction site of the construction project.

    Formwork support systems with concrete component formwork support height exceeding 8m, or erection span exceeding 18m, or construction total load greater than 15kn, or concentrated line load greater than 20kn. The construction unit shall, in accordance with the current relevant national standards and specifications, be organized by the technical person in charge of the project to prepare a special construction plan for the tall formwork support system in combination with the actual project.

    The main content of high mold monitoring:

    The first is displacement monitoring, and the monitoring equipment is a displacement sensor.

    Then there is the inclination monitoring of the rods, and the monitoring equipment is a cassette fixed inclinometer.

    Finally, there is the axial force monitoring of the pole, and the monitoring equipment is a load cell.

  4. Anonymous users2024-02-03

    The so-called high formwork is the general name of the construction of steel pipe erection and formwork engineering construction with a height of up to 5 meters and above in the construction of large-scale frame structures.

  5. Anonymous users2024-02-02

    Summary. High formwork support refers to the formwork support operation when the formwork height is greater than or equal to 8m.

    Can you elaborate on that a little bit more?

    High formwork support refers to the formwork support operation when the formwork height is greater than or equal to 8m.

    1. Concrete formwork support project in the sub-project with greater risk: erection height of 5m and above; or erection span of 10m or more; or the total construction load is 10kn m and above; or the lack of key load in the centralized line load bucket is 15kn m and above; or concrete formwork support projects whose height is greater than the width of the support horizontal projection and are relatively independent and have no contact components. 2. Concrete formwork support engineering in sub-projects with greater danger of exceeding a certain scale

    Erection height 8m and above; or erection span of 18m and above, or construction total load of 15kn m and above; or concentrated line load of 20kn m and above. Note: The danger of sub-projects exceeding a certain scale requires expert demonstration.

  6. Anonymous users2024-02-01

    Summary. Kiss, high formwork belongs to the more dangerous sub-project in the concrete formwork support project: erection height of 5m and above; or erection span of 10m or more; or the total construction load is 10kn m and above; or concentrated line load of 15kn m and above; or concrete formwork support projects whose height is greater than the width of the support horizontal projection and are relatively independent and have no connecting components.

    Hello, dear.

    Hello dear, High formwork refers to the formwork operation when the height of the formwork is greater than or equal to 5m.

    Kiss, high formwork without key belongs to the more dangerous sub-project in the concrete formwork support project: erection height of 5m and to talk about imitation; or erection span of 10m or more; or the total construction load is 10kn m and above; or the concentrated line load is 15kn m or more; or concrete formwork support projects whose height is greater than the width of the support horizontal projection and are relatively independent and have no connecting components.

    Kiss, tall mold should be expertly demonstrated. <>

    Kiss, more than one is aware of the first closure of the scale of the greater risk of cracking the concrete formwork support project: erection height of 8m and above; The erection span is 18m and above, and the total construction load is 15kn m and above; Concentrated line loads of 20 kN m and more.

    The tall formwork support system refers to the formwork support system with the concrete component formwork support height of the construction project of the rolling sail construction project exceeding 8m, or the span of the imitation hail setting exceeding 18m, or the total construction load is greater than 15kn, or the concentrated line load is greater than 20kn.

  7. Anonymous users2024-01-31

    1. Different erection heights

    The height of the high-support formwork is 5m and above. The height of the tall formwork is 8m and above.

    Second, the erection span is different:

    The height of the formwork is erected with a span of 10m and above. The span of tall formwork erection is 18m and above.

    Third, the total load of the construction is different

    The total load of the construction of the high-support formwork is 10kn m2 and above. The total load of tall formwork construction is 15kn m2 and above.

    Fourth, the concentrated line load is different:

    The load of the concentrated line of the high-support formwork is 15kn m and above. The load of the concentrated line of the tall formwork is 20kn m and above.

  8. Anonymous users2024-01-30

    Summary. Greater than or equal to 8m

    High formwork refers to the formwork operation when the height of the formwork is greater than or equal to 8m. The following projects are high formwork: 1. Concrete formwork support engineering in the sub-project with greater risk

    Erection height of 5m and above; or erection span of 10m or more; or the total construction load is 10kn m and above; or concentrated line load of 15kn m and above.

    How many meters high is considered a high formwork.

    More than or equal to 8m high formwork refers to the formwork operation when the height of the formwork is greater than or equal to 8m. The following projects are high formwork: 1. Concrete formwork support engineering in the sub-project with greater risk

    erection of slip baggage height of 5m and above; or erection span of 10m or more; or the total construction load is 10kn m and above; or concentrated line load of 15kn m and above.

    Mainly in Guangzhou.

    In Guangzhou, isn't it said that more than meters is a high formwork.

    8 meters or more.

  9. Anonymous users2024-01-29

    Summary. Kiss <>

    We are glad to answer for you: more than 8 meters is considered a high formwork, and the support system with a support height greater than or equal to 8m is referred to as a high formwork. Among them, the high formwork support system that meets one of the following conditions needs to be reviewed by experts:

    1. The height of the horizontal concrete component formwork support system is greater than or equal to 8m or the span is greater than or equal to the total construction load is greater than or equal to 15kn or the concentrated line load is greater than or equal to 20knm.

    How many meters high is considered a high formwork.

    Kiss <>

    We are glad to answer for you: more than 8 meters is considered a high formwork, and the support system with a support height greater than or equal to 8m is referred to as a high formwork. Among them, the high-support sensitive jujube mold system that meets one of the following conditions needs to be reviewed by experts:

    1. The height of the formwork support system of the horizontal concrete bridge dismantling component is greater than or equal to 8m or the total construction load is greater than or equal to 15kn or the concentrated line load is greater than or equal to 20kn.

    Does the cast-in-situ formwork with a floor height of 8 meters need expert demonstration?

    Kiss, formwork projects with a beam height of more than 8 meters or a span of more than 18 meters, as well as tool formwork such as sliding formwork and climbing formwork, all need expert demonstration. The expert demonstration is organized by the construction unit, and the construction unit, the supervision unit and the industry are dedicated to the participation of the owner, to demonstrate the feasibility, safety and operability of the plan, and to implement the smart training according to the plan after the demonstration is qualified.

    The ceiling height is 8 meters.

    Whether it's a clear height or a floor height.

    Expert argumentation is required.

    Kiss, it is a floor height of 8 meters, which needs expert argumentation.

    Is it the height of the building.

    Kiss, not a single layer is 8 meters high, it is the height of the beam and plate formwork more than 8m, and the height of the horizontal concrete component formwork support system is 8m

  10. Anonymous users2024-01-28

    The support system with a support height greater than or equal to 8m is referred to as high formwork.

    Among them, the high support formwork system that meets one of the following conditions needs to be reviewed by experts:

    1. The height of the horizontal concrete component formwork support system is greater than or equal to 8m or the span is greater than or equal to 18m.

    2. The total construction load is greater than or equal to 15kn or the concentrated line load is greater than or equal to 20kn m.

    Precautions: 1. Concrete formwork support project in the sub-project with greater risk: erection height of 5m and above; or erection span of 10m or more; or the total construction load is 10kn m and above; or concentrated line load of 15kn m and above; or concrete formwork support projects whose height is greater than the width of the support horizontal projection and are relatively independent and have no connecting components.

    2. Concrete formwork support project in the sub-project with greater risk of exceeding a certain scale: erection height of 8m and above; or erection span of 18m and above, or construction total load of 15kn m and above; or concentrated line load of 20kn m and above.

    Hazardous engineering: If the dangerous project is subcontracted and the subcontractor prepares a special construction plan, the special project shall be jointly reviewed by the technical person in charge of the general contractor and the technical person in charge of the subcontractor and signed by the official seal of the unit. For dangerous projects exceeding a certain scale, the construction unit shall organize and convene an expert demonstration meeting to demonstrate the special construction plan.

    If the general construction contracting is implemented, the general construction contractor shall organize and convene an expert demonstration meeting.

    Before the expert demonstration, the special construction plan shall be reviewed by the construction unit and the chief engineer. Experts shall be selected from the expert database established by the competent departments of housing and urban-rural construction of local people, and shall meet the professional requirements and the number shall not be less than 5. Personnel who have an interest in the project shall not participate in the expert demonstration meeting as an expert.

Related questions
6 answers2024-02-28

When you fall in love with someone, don't care about the romance of love and many kinds of love methods, this everyone's way of loving is different, don't be dissatisfied, too greedy, you will lose rare true love, some people say that love will not last long, I think it is wrong, love has a long time, because you do not protect true love, it will lead to love is short-lived, will think that it will not last long. To love someone, you have to trust each other, to love someone, to understand each other, to love someone, to be tolerant of love, to love someone, to be broad-minded, to love someone, to respect each other's thoughts and opinions, to love someone, to support him (her) behind his (her), not to block Love someone to face when he (she) can't accompany you, don't complain, to say to him (her) with a smile I'm very good, very happy Love someone to hide your inner fragility and grievances, don't let him (her) know Love someone too much too much love, Maybe some people can't do it The important point is that love should be selfless and unrepentant, love should be clean and pure, without a trace of impurities, willing to do anything for him (her), when you fall in love, let him (her) be happy, as long as he (she) is happy, is the most important!!

8 answers2024-02-28

Excessive growth of virtual capital.

A bubble economy refers to a macroeconomic situation in which the value of assets exceeds the value of the real economy, and it is easy to lose the ability to sustain development. Bubble economies tend to be supported by a lot of speculative activity, and due to the lack of support from the real economy, their assets tend to burst easily, hence the name bubble economy. >>>More

7 answers2024-02-28

You need to be extroverted and eloquent, but in fact, you can't learn too many things, and they are all learned from society

4 answers2024-02-28

Signal and system are used in China's higher education, and the rise of signal and system in China's higher education is not long, but it is a compulsory core basic course for electronics majors, and the course is mainly based on mathematical analysis, which involves mathematical and physical methods, concepts, etc. are widely used in many fields such as communication, signal and information processing, electronics, computer science and technology, automatic control, circuits and systems. The relevant concepts and analytical methods covered in this course are its main areas of study. >>>More

6 answers2024-02-28

There are two kinds, the benign one is a tumor, which can be surgically removed! Malignancy is more troublesome, the popular saying is a bit scary, called bone cancer, this disease is more difficult to cure, the possibility of amputation is very high, and even if the amputation is done, there are very few who have survived 5 years!