The basic way of flow construction.
First, wait for the rhythm of the flow of construction.
Definition: It refers to a flow construction method in which the flow beat of the same construction process is equal on each construction section, and the flow beat between different construction processes is also equal, also known as congruent beat flow or synchronous distance flow.
Organizational steps: 1. Determine the construction sequence and decompose the construction process.
2. Determine the flow direction of the starting point of the project construction and divide the construction section.
3. Calculate the flow beat value according to the construction requirements of equal beat flow.
4. Determine the flow step distance, k=t
5. Calculate the construction period of flow construction.
Duration calculation: t=(m+n 1) k+ zj, j+1 gj, j+1 cj, j+1
Second, the flow of water construction at different beats.
Definition: It refers to a flow construction method in which the flow rhythm of the same construction process is equal in each construction section, but the flow beat between different construction processes is not equal to the complete collapse. It is divided into: general heterotempo flow and exponential beat flow.
1) General heterorhythmic flow construction.
Definition: It refers to the flow construction method in which the flow beat of the same construction process is equal on each construction section, and the flow beat between different construction processes is not equal or multiple.
Organizational steps: 1. Determine the construction sequence of the flow and decompose the construction process.
2. Determine the flow direction of the starting point of construction and divide the construction section.
3. Determine the flow rhythm.
4. Determine the flow step.
5. Determine the total duration of the plan.
Duration calculation: t= k+tn+ zj, j+1 gj, j+1 cj, j+1
2) Exponential beat flow.
Definition: refers to the same construction process in each construction section of the flow beat is equal, and there is an integer multiple relationship between the flow beat of different construction processes.
Duration calculation: t (m n1 1)kb zj,j+1 gj,j+1 cj,j+1
3. Rhythmless flow construction.
Definition: It refers to a flow construction method in which the flow beat of the same construction process is not completely equal in each construction section, and it is a common form of flow construction.
Organizational steps: 1. Determine the construction sequence of the flow and decompose the construction process.
2. Determine the flow direction of the starting point of construction and divide the construction section.
3. Calculate the flow beat according to the corresponding formula.
4. Determine the flow step distance between two adjacent professional task forces.
5. Determine the total duration of the plan.
Duration calculation: t= k+tn+ zj, j+1 gj, j+1 cj, j+1
It generally includes the following contents: engineering pay-off, earthwork excavation, concrete pouring, steel bar binding, formwork installation, brick wall masonry, steel (wood) structure manufacturing and installation, stone paving and other decoration, sketches and furniture placement; Terrain arrangement, seedling planting, etc.
First, the general situation of the project.
This project is a vertical storage tank insulation project, the height of the storage tank is 10 meters, the diameter is 5 meters, the insulation material is polyurethane foam board, and the insulation thickness is 100mm. The construction site is an industrial park. >>>More
[Legal Analysis].:Construction organization design: >>>More
The basis for the preparation of the design of the construction organization generally includes the following parts: >>>More
Six-storey brick-concrete structure construction organization design. >>>More