What are the construction organization design specifications and what is the basis for compilation

Updated on society 2024-03-05
6 answers
  1. Anonymous users2024-02-06

    If you have it in the books, find it yourself.

  2. Anonymous users2024-02-05

    <> construction organization design is a comprehensive document prepared for the construction project to guide the construction of technology, economy and management. If the construction drawing design is to solve the problem of what kind of building products to build, then the construction organization design is to solve the problem of how to build. Due to the influence of building products and their construction characteristics, before the start of each project, the construction organization design must be prepared according to the characteristics and construction conditions of the project.

    The basic task of construction organization design is to determine the economic and reasonable construction plan according to the relevant national technical policies, construction project requirements, and the principles of construction organization, combined with the specific conditions of the project, and make overall arrangements for the proposed project in terms of manpower and material resources, time and space, technology and organization, so as to ensure that the construction task is completed with high quality, low consumption, high speed and safety in accordance with the established goals.

    Type of classification. At present, according to the requirements of the construction industry management model, the construction organization design is mainly divided into two categories:

    1. Guiding construction organization design.

    Including the general design of the construction organization and the construction organization design in the bidding stage.

    The guided construction organization design is faced with the part of a single project, a group project or a bidding project with a large amount of content or uncertain factors. It is only to determine the general principle, and it does not have the guiding nature of engineering construction.

    2. Implementing construction organization design.

    Including the construction organization design of the unit project and the construction organization design of the sub-project project.

    The implementation of the construction organization design, according to the characteristics of the project or as a supplement to the general principles that have been determined by the general design of the construction organization, the content of its expression is detailed, perfect, pertinent, and is the basis of the construction of the project.

    Methodology and principles of preparation.

    1. Preparation method.

    The preparation of the construction organization design should not only consider the technical needs, but also consider the needs of the performance of the contract, and should be compiled into a project management planning document integrating technology, economy, management and contract, the guiding document for the performance of the contract, and the basis for the settlement and claim of the project. For large-scale or complex projects, it should be prepared in stages or in parts (divisions, divisions); The preparation should be completed prior to the implementation of the project for which it is addressed. The construction organization design (plan) of the subcontracted construction division (sub-item) project shall be summarized in the construction organization design of the project in the form of an annex.

    2. Preparation principle.

    Pay attention to the role of the organization of the project in the construction.

    Increase the degree of industrialization of construction.

    Pay attention to management innovation and technological innovation.

    Pay attention to the target control of engineering construction.

    Actively adopt advanced construction technology at home and abroad.

    Make full use of time and space, reasonably arrange the construction sequence, and improve the continuity and balance of construction.

    Rational deployment of the construction site to achieve civilized construction.

    3. Basis for compilation.

    The preparation of the construction organization design is based on: plan documents, design documents, contract documents, basic information of the construction area, relevant standards, norms and laws, as well as information and experience of similar construction projects.

    Epilogue. Before preparing for the preparation of the construction organization design, we must carefully analyze and study the bidding documents and materials of the construction party, and do a good job in all aspects of investigation and research in detail to ensure that the real first-hand information is obtained, and the mature construction organization design is compiled.

  3. Anonymous users2024-02-04

    1. Strictly abide by the construction period quota and the project completion and delivery deadline stipulated in the contract.

    Large-scale construction projects with a long total construction period should be constructed in phases and batches according to the needs of production, and put into operation or put into use in supporting facilities, so as to shorten the construction period in fact and give full play to the economic benefits of the state's construction investment as soon as possible.

    While determining the phased and batch construction projects, attention must be paid to making the set of projects delivered in each phase can play an independent role, so that the main projects can be constructed at the same time as the relevant ancillary auxiliary projects, so that they can be delivered for use immediately after completion.

    1. Reasonably arrange the procedures and sequence of the construction project.

    Building construction has its own objective law, and organizing construction in accordance with the procedures that reflect this law can ensure that various construction activities promote each other and are closely connected, avoid unnecessary duplication of work, speed up construction, and shorten the construction period.

    When arranging construction procedures, the following points should generally be taken into account:

    1) It is necessary to complete the relevant construction preparations in a timely manner to create good conditions for formal construction.

    2) During the formal construction, the site should be leveled, the pipe network should be laid, the road should be built and other full-site works and permanent buildings that can be used for construction, and then the construction of each project should be carried out.

    3) For the construction sequence of individual houses and structures, it is necessary to consider not only the spatial order, but also the order between the types of work. The order of work considers the problem of time overlap, it must ensure quality, create conditions between different types of work, make full use of the working surface, and gain time.

    2. Use the assembly line operation method and network plan to arrange the schedule.

    3. Properly arrange the construction project during the winter rainy season.

    For those projects that must enter the winter rainy season, seasonal construction measures should be implemented to increase the number of construction days throughout the year and improve the continuity and balance of construction.

    5. Implement the technical policy of multi-level technical structure, and promote the development of technological progress and construction industrialization according to time and local conditions.

    6. Proceed from reality, make a comprehensive balance of manpower and material resources, and organize balanced construction.

    7. Try to make use of formal projects, original or nearby existing facilities to reduce various temporary projects; Make the best use of local resources, reasonably arrange transportation, loading and unloading and storage operations, reduce the amount of material transportation, and avoid secondary handling; Carefully carry out the closed site planning and arrange the key state to be high, save construction land, do not occupy or occupy less farmland, prevent construction accidents, and achieve civilized construction.

    8. Implement target management.

    9. Combined with construction project management.

  4. Anonymous users2024-02-03

    The following principles should be followed in the preparation of the construction organization design:

    1. In accordance with the relevant national guidelines and policies, strictly implement the national capital construction procedures and abide by the relevant technical standards, regulations and norms, and conform to the regulations of domestic bidding and the practice of international bidding.

    2. Facing the society, conducting in-depth investigations, collecting market information, proposing construction plans according to local conditions according to the characteristics of the project, and conducting comprehensive technical and economic comparisons.

    3. Overall arrangement, comprehensive balance, proper coordination of all sub-projects, continuous and balanced construction.

    4. Actively develop and promote new technologies, new materials, new processes and new equipment in combination with national conditions, and try to adopt all scientific research achievements that have been proved to have significant technical and economic benefits through slow practice, and strive to improve technical and economic benefits.

    The establishment of undertakings refers to the establishment of personnel for the creation or improvement of production conditions, the enhancement of social welfare, and the satisfaction of the people's cultural, educational, and health needs, and the funds are generally used by the units that spend the state's operating expenses.

    It refers to the staffing used by various types of public institutions. Compared with the administrative establishment, the establishment of undertakings is widely used, and the forms of funding include financial allocation, financial subsidies and self-financing. **The establishment department focuses on strengthening the macro guidance for the establishment and management of local government units, and regulates and controls the total amount and structure of the establishment of institutions in all provinces, autonomous regions and municipalities directly under the Central Government.

  5. Anonymous users2024-02-02

    The construction organization design is very critical to the implementation of the whole project, and promotes the progress and development of the project, but the construction organization design is very difficult, the relevant personnel should understand a certain knowledge, let's take a look at the construction organization design content? What are the compilation principles?

    The content requirements of construction organization design are what we must pay attention to, and many friends are very confused about such problems, so let's learn together what are the content of construction organization design?

    1. Description of the project summary and project characteristics.

    2. The overall construction schedule plan and the schedule plan of the main unit project.

    3. The overall construction deployment and the construction plan of the main unit project.

    4. The total demand plan of various resources by year (including labor, raw materials, potato peel processing components, construction machinery, and installation equipment.

    5. Full-site construction preparation plan (including the preparation of "three links and one leveling", the preparation of temporary facilities construction, the utilization of the original roads, houses, power and processing plant conditions, and the setting of institutional organizations, etc.).

    6. Design of the general plan of the construction.

    7. Technical and organizational measures and technical and economic indicators related to quality, safety and cost reduction.

    The above introduction is an explanation of the content of the construction organization design, we should pay more attention to some such problems, and then understand what is the principle of preparation?

    1. Pay attention to the role of the organization of the project in the construction; Increase the degree of industrialization of construction. Pay attention to management innovation and technological innovation. Pay attention to the target control of the construction rock foundation;

    2. Actively adopt advanced construction technology at home and abroad; Make full use of time and space, reasonably arrange the construction sequence, and improve the continuity and balance of construction. Rational deployment of the construction site to achieve civilized construction.

    The above are some of the problems I have explained to you in the construction organization design, I hope these explanations will be useful to you!

  6. Anonymous users2024-02-01

    Hello dear I am happy to answer for you, for your question [what are the basic requirements for the preparation of construction organization design?] This question provides you with the following answers: 1. The sentence is smooth and smooth, the punctuation is correct, and there is no long sentence of more than 30 words.

    2. The table of contents corresponds to the content, and the names of the drawings and tables in the catalog correspond to the charts and charts compiled. 3. The overall construction plan is basically correct. 4. Seasonal construction measures should be prepared according to the season in which the project will be constructed.

    5. The "Construction Organization Design Framework" is a style requirement for standardizing the preparation of construction organization design. When compiling measures, it is necessary to compile the relevant content according to the actual situation of the project site, and it is strictly forbidden to directly quote the content in the "Construction Organization Design Framework". 6. The equipment eliminated by the state shall not be selected.

Related questions
1 answers2024-03-05

The basic way of flow construction.

First, wait for the rhythm of the flow of construction. >>>More

8 answers2024-03-05

and a wide range of savannahs. There is a prairie, wide, that prairie should be very good.

6 answers2024-03-05

It generally includes the following contents: engineering pay-off, earthwork excavation, concrete pouring, steel bar binding, formwork installation, brick wall masonry, steel (wood) structure manufacturing and installation, stone paving and other decoration, sketches and furniture placement; Terrain arrangement, seedling planting, etc.

7 answers2024-03-05

First, the general situation of the project.

This project is a vertical storage tank insulation project, the height of the storage tank is 10 meters, the diameter is 5 meters, the insulation material is polyurethane foam board, and the insulation thickness is 100mm. The construction site is an industrial park. >>>More

2 answers2024-03-05

[Legal Analysis].:Construction organization design: >>>More