Precautions for rough house inspection are:
1) Pay attention to see if the documents are complete:
1. Residential Quality Assurance Certificate
2. Residential Instruction Manual
3. Completion Acceptance Record Form
4. Area measurement table.
5. As-built drawings of pipeline distribution.
2) Pay attention to whether it conforms to the contract:
1. Check whether the facilities and equipment indicated in the sales contract are missing, and whether the brand and quantity are consistent.
2. Verify whether the area is consistent with the contract, and the problem of overrefund and underpayment.
3. Confirm whether the structure is the same as the original design drawing.
3) Pay attention to the actual quality of the house
After reading the above information, you can go to the acceptance of the house, first of all, you must get the key from the property, including access control, floor key, the key to your own home, the key to the mailbox, etc., conditional business tools, such as vertical level, small hammer, rectangular ruler, ruler, feeler gauge, mirror, spool, etc., in addition to the best to bring the following tools: plastic basins, newspapers, ropes, etc.
-
When the developer notified them to take over the house, they were inevitably very excited, and the house was finally ready to be renovated and moved in. However, the acceptance of the rough house is a link that many people have ignored, the acceptance of the rough house is very important, and you must not ignore the simple and necessary acceptance of the whole room because you are too happy to get the key to the new house or other reasons, because the acceptance of the rough house directly affects whether the decoration can be carried out smoothly and completed with high quality.
1. Doors and windows: the door is the easiest place to be forgotten, now the residential installation is an anti-theft door, after opening the door, you should carefully observe and touch the surface of the door with your hands to see if it is smooth, whether there are scratches or places that have been hit, and then visually see if the door frame is not correct, because the door frame is not correct will directly affect the use of actual life in the future, and you should try the lock back and forth to see if it can be opened and closed normally, if you encounter a problem, you should reflect it to the property in time to replace.
2. Wall and ground: In the acceptance of the rough house, the wall and ground are the largest and most critical places. We should check whether the walls and floors of all rooms are flat, and whether the walls of the kitchen and bathroom are hollow.
3. Water: In the rough room, the bathroom and kitchen are all good water pipelines, but most of them do not have faucets. You can take a bucket of water and pour it into the pipe to see if the water is happy and there is no blockage.
The floor of the bathroom should be waterproof, but it is impossible to do the water shielding test due to the conditions during the house inspection, so we should let the decoration workers do a water shielding test before decoration, and see if there is water leakage after 24 hours.
The above are some of the things that need to be paid attention to in the acceptance of the rough house, in addition, when the house is inspected, it is necessary to check whether each room has electricity, and each room is equipped with a simple light bulb to see if they are normal. The socket in each room must not be forgotten, now there are simple test pens on the market are not very expensive, we can use the test pen to test whether each socket has electricity.
-
Many people are very happy when they get their new home and want to renovate it in a hurry. However, the rough house needs to be inspected before delivery, and many people don't know much about the details of the house inspection, so what are the precautions and details for the acceptance of the rough house? What are the advantages and disadvantages of a rough house?
First of all, inspect the wall to see if there are cracks and hollowing in the wall; secondly, check whether the quality of water pipes and wires is high-quality and complete; Then check the waterproofing and pipes, such as whether there are traces of water leakage in the waterproof kitchen and bathroom, and whether there are leaks or anti-odor elbows and other equipment in the pipe joints; Finally, inspect the floor, floor height, doors and windows, etc., to see if there are any defects
What are the advantages and disadvantages of a rough house?
First, the advantages. 1. The decoration is more individual or wild.
First of all, compared with the hardcover room, the rough room can choose the decoration style according to its own preferences and living habits, and it will not be the same as the hardcover room. It is a great choice for young people who are looking for individuality.
2. Decoration construction can be checked.
Secondly, when the rough house is decorated, whether it is the choice of materials or the decoration design, the owner can participate, and even all the materials are customized by their own choice, so the quality is more guaranteed. 3. Low economic pressure.
Finally, compared with the hardcover room, the price of the rough house is lower, and the later decoration can also be self-controlled, and the decoration grade is determined according to the actual economy.
2. Disadvantages: 1. It takes a lot of time.
The rough house needs to be decorated by itself, and it takes a lot of time to find a decoration company, select a designer, buy building materials, and supervise on site. For young people with busy work, there is not much time and energy. If you give it to your parents, you are worried that you won't be able to pretend that you won't be able to achieve the effect you want.
2. The decoration is more troublesome.
If the owner is a layman and does not know much about decoration and building materials, it is easy to be fooled when buying, and in terms of soft decoration, the collocation is unreasonable, which is not only costly, but also does not achieve the expected effect.
Summary: The above is the introduction of the rough house inspection precautions and details and what are the advantages and disadvantages of the rough house, I hope to help friends in need, if you need to know more about the relevant knowledge in the later stage, welcome to pay attention to Qeeka Home information.
-
The rough house should pay attention to check whether the wall is smooth; Check whether the reserved position of the strong and weak current box meets the standard; Check that the kitchen wall water pipes are in place; Check whether the waterproofing of the bathroom is in place; Check that the balcony railings are in place; Check whether the window railing at the bay window location has any details such as installation.
First of all, see if the area of the house is consistent with the area of the house, it is best to bring a ruler to roughly measure it to see what the actual area is, and it is reasonable to have an error. According to the regulations, if the area error is within plus or minus 3%, it can be settled according to the facts, and if it is exceeded, the contract can be terminated and compensation can be claimed.
We need to check the walls and floors of all rooms to see if they are flat and whether the walls are hollow. It is best to have a professional tool such as a level, and if you don't have it, you can also use a table tennis ball to test whether the ground is level.
Other details
Doors and windows are an important barrier to ensure the safety of living, when checking doors and windows, you can gently push and pull the doors and windows by hand to see if there is a problem, whether they can be locked, and whether the windows can be fixed, otherwise it may affect the safety of life and property. Of course, doors and windows are also an important channel for indoor and external air exchange, if the doors and windows are not well sealed, they may leak, which will affect the indoor temperature in winter, and dust will enter, bringing inconvenience to cleaning.
Then look at whether the water meter and electricity meter are operating normally, and then check whether the sockets in each room can be energized normally, and whether the location and installation are reasonable. Then check whether the water flow is normal, if the flow rate is too small, you should consider whether it is a problem with the smooth flow of pipes or water pressure.
-
Go to the relevant acceptance specifications.
-
1. No matter how clever the staff of the developer accompanies the house inspection are, the owner must adhere to the principle, whether it is a big problem or a small problem, as long as it is found, it must be recorded and written on the relevant documents or **, if the house can not be accepted, it must be written clearly the reason for the acceptance and let the developer sign and seal.
2. The "Residential Quality Assurance Certificate", "Residential Instruction Manual" and "Completion Acceptance Record Form" presented by the developer should be seen in the original, not the copy.
3. Before the completion of the house and the preparation of the signature decoration, the structural safety and equipment use safety of the county house must be repaired by the construction unit until it is qualified.
Rough house inspection process.
1. Wall acceptance.
The acceptance of the wall in the inspection of the new rough house mainly depends on whether the wall is cracked and hollow. How to do it: Hit the wall with a small wooden hammer or something, if the sound from the wall is not real, it indicates that there is a hollow drum here, make a mark, and then fill it with putty when decorating.
It is also necessary to check whether the putty on the wall is waterproof.
2. Top acceptance.
The acceptance of the top surface in the new rough house is mainly to see whether the top surface is cracked, and to check whether the yin and yang angles of the top surface and the wall are on a horizontal line.
3. Acceptance of doors and windows.
For the acceptance of doors and windows in the new rough house, it is necessary to check the firmness and strength of the doors and windows, and to test their functions, mainly to see whether the doors and windows are smooth or stuck. Make sure that the surface of the doors and windows is smooth and free of serious scratches, and that the material is intact and that there are no cracks or cracks. In addition, it is also important to check the hardware to see if it is installed correctly and firmly.
4. Circuit acceptance.
The circuit acceptance in the process of inspection of the new rough house is very important, it is necessary to see whether the installation of the socket and the location of the smart switch is reasonable, and at the same time, it is also necessary to judge whether the circuit should be modified during the decoration, and the inspection of the function of the switch and socket can not be ignored, and try to see if each socket can be energized.
-
Most of the owners are in the state of the rough house, after a small number of friends will choose the hardcover room, the rough house is the whole house in the original state, need to decorate themselves, but before the decoration of the rough house, the rough house inspection is also essential, smooth house inspection, can reduce the trouble in the later stage, to avoid various problems, the following will introduce the precautions for the rough house inspection, share the 5 basic house inspection details.
First, the wall and ground acceptance
When inspecting the rough house, we should first pay attention to the wall and the ground, and we must check whether the walls and floors of all rooms are flat, and whether the walls of the kitchen and bathroom are hollow. If the wall is uneven, it will bring a lot of trouble to the future decoration, and the ground is not flat enough will also affect the future tiling or flooring. If there is a hollow place on the wall of the bathroom and kitchen, it is easy to fall off after the tile is pasted in the future decoration.
To see if there is a hollow drum on the wall, you can use a small hammer to test the posture, and judge whether there is a hollow drum on the wall by the sound made when beating.
Second, the waterway acceptance
In the rough house, the bathroom and kitchen are all well-wired, but most of them do not have faucets. We can take a bucket of water and pour it into the pipe to see if the water is happy and there is no blockage. The floor of the bathroom should be waterproof, but it is impossible to do a water shielding test due to conditions during the house inspection, so we should ask the decoration company to do a water shielding test before decoration, and see if there is any water leakage after 24 hours.
3. Circuit acceptance
During the rough room inspection, it is necessary to check whether each room has electricity, and each room is equipped with simple light bulbs to see if they are all normal. The socket in each room must not be forgotten, now there are simple test pens on the market are not very expensive, you can use the test pen to test whether each socket has electricity. If you don't have a test pen, you can use a dirt method to trap the ridge, and you can test it with a mobile phone charger or a hair dryer.
Fourth, the acceptance of doors and windows
The door is the most forgotten place, and the main concern of the homeowner after opening the door with the key is to see what the house is like, and the appearance of the door and other issues are left behind, which is absolutely undesirable. Now the residential installation is an anti-theft door, after opening the door, you should carefully observe and touch the surface of the door with your hands to see if it is smooth, whether there are scratches or traces of the place where the ruler has been hit, and then visually see if the door frame is correct, because the door frame is not correct will directly affect your use in actual life in the future, and you should try the lock back and forth to see if it can be opened and closed normally, if you encounter a problem, you should reflect it to the property in time to replace.
5. Ventilation system
Ventilation systems are a big issue that is often overlooked during home inspections. Flues and exhaust ducts are places that are easy to leave hidden dangers for daily life in the future.
The above is to share with you the precautions for rough house inspection, 5 basic house inspection details of the relevant knowledge, I hope to help you with home inspection, if you want to know more about home improvement knowledge, please pay attention to home improvement network.
-
In the face of today's high housing prices, people will decorate through careful decoration design, especially young people who pursue individuality, and can decorate according to their own preferences. How to inspect a rough house.
Rough house inspectionMeasuring the height of the floor, many people will overlook, we subtract the margin of 3cm, and then pay attention to the purchase contract of the surface layer of the floor with a floor thickness of 20cm, and the rest of the house is clear.
Rough house inspection
Looking at the structure of the house, not doing rough house structure, and the size of the grandchildren in each place, you can determine if the house is tilted, you can use special equipment that can be used to fix the heavy rope, and then check down the slope of the wall skirt you can. If the error exceeds 3cm, the decoration will be seriously affected.
Rough house inspection
Look at the structure of the wall. Spots on the wall will take up a lot of space, and when storing, you should pay attention to whether there are cracks in the plaster layer on the wall, cavitation and other problems in the plaster layer. The flatness of the wall surface is relatively normal between 3-5 mm.
1. All exterior finishes of the rough interior, such as balconies and non-mulching, must be done in accordance with the design documents.
2. The general parts of rough houses and public facilities, electrical equipment and various pipelines should be completed according to the design documents, and the test projects should be completed according to the regulations.
Rough house inspectionThe pipes must pass hydrostatic tests, as well as ball tests and approved work such as heating and thermal commissioning. The roofing works have completed water storage and water testing.
Rough house inspectionEach room of a coarse house that is poured on site using a roof or prefabricated floor must be leveled with putty without plaster. The seam of the plate is dense and crack-free, the surface is smooth, and the color is uniform. The concrete in the base of each rotten room in the door must be compressed to ensure a strong bond without cracks.
Rough house inspectionTo ensure that the floor of the building is level, only long walls can be used to ensure its leveling. If there are cracks and there are no leaks of barbed wire and rebar, please note that the walls are not visible and have **. If there is a problem with the wall during testing, the developer can fix it and sign it.
Rough house inspection, Door and window inspection The most important thing is to check if the track is smooth, if there is a window window, pay attention to whether it can be closed, if you sign first and then ask the developer to deal with the problem, then you probably won't do a good job.
You can get it for free
Precautions for the delivery of rough houses: (1) First check the developer's "Residential Quality Assurance Certificate", "Residential Instruction Manual", "Construction Engineering Quality Certificate", "Real Estate Development and Construction Project Completion Comprehensive Acceptance Certificate" and "Completion Acceptance Record Form". (2) Inspect the house first and then go through the procedures. >>>More
The precautions for rough blank house inspection are as follows: house layout and configuration, house body, pipeline, strong and weak electricity and waterproof engineering. Rough embryo room inspection is an indispensable step before the house, master the precautions of the rough embryo inspection, and get twice the result with half the effort. >>>More
The steps and methods of water and electricity decoration of the blank room are as follows: >>>More
The precautions and details of hardcover room inspection include living room floor tiles, building materials brand, anti-theft door, interior door material, and window. >>>More
When receiving the house, it is necessary to pay attention to: check the three books, one certificate and one table, the three books refer to the "Residential Quality Assurance Certificate", "Residential Instruction Manual", "Construction Engineering Quality Certificate", one certificate refers to the "Real Estate Development and Construction Project Completion Comprehensive Acceptance Certificate", and one table refers to the "Completion Acceptance Record Form". >>>More